Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC326-4342 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed. |
REC326-4343 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures a communications plan is in place, including the communication of guidelines to potential applicants. |
REC326-4344 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: establishes and follows guidelines that align with relevant good practice guidance including accountabilities, key assessment steps and clear assessment criteria. |
REC326-4340 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: documents all key decisions and approvals in line with record keeping obligations. |
REC326-4341 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures regular monitoring is in place as part of funding deeds. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4021 | 32 - Doctrine, standards, and reform | The Emergency Plan be amended to better reflect the intent of the Emergencies Act in the establishment of a Management Executive, separate to SEMSOG, on the appointment of an EC. It should describe the role of SEMSOG and the Management Executive as distinct in the emergency management architecture. |
REC316-4049 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the appointment of the EC to be made for a discretionary time period of up to 28 days with the requirement for a legislated review of the appointment to be removed. Alternatively, a period of review should fall within the Chief Ministers discretion for up to seven (7) days following appointment. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4045 | 42 - Culture and Heritage | WHoG desktop exercise should be conducted to test and support relocation and evacuation planning. |
REC316-4028 | 41 - Emergency Management exercises | Any changes to the ECC structure and role be exercised both within ESA and across a WHoG exercise and testing program. |
REC316-4035 | 32 - Doctrine, standards, and reform | Review, refine and implement the joint ESA/EPSDD Arrangement for Fire Management in the ACT with the previous recommendation in mind. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4025 | 32 - Doctrine, standards, and reform | The Emergency Plan and ECC Ops Plan be amended to better articulate the delivery of emergency management vs the delivery of the emergency plan. The Plan should facilitate principles for emergency management and clear role delineations whilst allowing flexibility in how the mechanisms are structured. |
REC316-4052 | 32 - Doctrine, standards, and reform | The ACT Emergencies Act 2004 be amended to clarify that the powers of the EC encompass the power to direct agencies and directorates to share personal information for the preservation of life and protection of Canberrans. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
REC316-4024 | 32 - Doctrine, standards, and reform | The Government consider amendments to the Emergencies Act to include provision for a Deputy ESA Commissioner. |
REC316-4051 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended so that the powers, including delegations, available to an EC be granted on their appointment and remain in place under the same section of the Act for the duration of their appointment rather than being drawn from different sections of the Act that are dependent on the existing alert state for the specified event. |
REC316-4032 | 41 - Emergency Management exercises | Concurrent and/or non–standard emergencies such as energy supply impacts be included in future exercise programs. |
REC316-4040 | 41 - Emergency Management exercises | The PICC be exercised in conjunction with any and all Emergency Plan exercises to test and refine strengthened arrangements. |
REC316-4023 | 41 - Emergency Management exercises | An opportunity to exercise and test the formation and functioning of a Management Executive through desktop and/or limited scenario-based exercises be provided. |
REC316-4050 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the provision for a Deputy Emergency Controller to be appointed, independent of the initial appointment of an EC. The powers and functions of this appointment to be contingent on the absence of the EC. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3810 | 24 - Govt responsibility | That, to ensure updated resource-sharing arrangements are in place, the NSW and Victorian Governments progress and finalise a multi-agency Memorandum of Understanding before the 2020-21 fire season commences. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3864 | 9 - Community education | That, in order to ensure people can access clear information on cross-border fires, the NSW RFS: |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3843 | 17 - Assets and technology | That, in order to improve early fire suppression, the NSW RFS trial initial aerial dispatch in areas of high bush fire risk. The trial should identify the most appropriate and cost-effective mix of aircraft, and any associated infrastructure improvements that would be required. |
REC315-3824 | 1 - Land-use and building regs | That Government commit to shifting to a strategic approach to planning for bush fire, and develop a new NSW Bush Fire Policy similar to the NSW Flood Prone Land Policy in order to accommodate changing climate conditions and the increasing likelihood of catastrophic bush fire conditions; to build greater resilience into both existing and future communities; and to decrease costs associated with recovery and rebuilding. |
REC315-3850 | 3 - Biodiversity | That Government develop and implement a policy on injured wildlife response, rescue and rehabilitation including: |
REC315-3808 | 22 - Role of local Gvt | That, in order to strengthen the capability of local councils in future emergency events: |
REC315-3829 | 4 - Fire season preparation | That, in order to ensure outcomes-based roadside vegetation management to reduce roadside tree fall and grass ignitions in planning and preparing for bush fire, Transport for NSW, working with local government and NSW RFS, establish a consistent framework for roadside vegetation management that analyses road priority, utility, amenity, strategic value and risk. The framework should: |
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3842 | 24 - Govt responsibility | That, in order to prioritise early suppression and keep fires small: |
REC315-3823 | 42 - Culture and Heritage | That, in order to increase the respectful, collaborative and effective use of Aboriginal land management practices in planning and preparing for bush fire, Government commit to pursuing greater application of Aboriginal land management, including cultural burning, through a program to be coordinated by Aboriginal Affairs and Department of Planning, Industry and Environment working in partnership with Aboriginal communities. This should be accompanied by a program of evaluation alongside the scaled-up application of these techniques. |
REC315-3849 | 17 - Assets and technology | That, in order to enhance NSW’s fire fighting capacity, Government trial aerial fire fighting at night in the 2020-21 season with a view to full implementation if successful. |
REC315-3805 | 32 - Doctrine, standards, and reform | That, to strengthen cross-agency accountability and deliver improved bush fire risk management outcomes: |
REC315-3828 | 9 - Community education | That, in order to improve bush fire planning and protection of road infrastructure and to ensure communities, freight movers and fire fighting agencies have appropriate access and egress in a bush fire event, Government, working with local government as needed: |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
REC315-3815 | 17 - Assets and technology | That, in order to equip NSW RFS with comprehensive information on all structures and assets at risk of bush fire, Government ensures that: |
REC315-3837 | 17 - Assets and technology | That, in order to improve firefighter safety, Government fire authorities: |
REC315-3822 | 42 - Culture and Heritage | That Government adopt the principle that cultural burning is one component of a broader practice of traditional Aboriginal land management and is an important cultural practice, not simply another technique of hazard reduction burning. |
REC315-3848 | 17 - Assets and technology | That, in order to enhance NSW’s ability to improve situational awareness, Government expand FRNSW’s Remotely Piloted Aerial Systems (RPAS) capability (both capital assets and trained operators) to major regional centres and ensure the NSW RFS and other NSW government agencies can access this capability as required. |
REC315-3804 | 32 - Doctrine, standards, and reform | That the NSW RFS Commissioner consult with the Fire and Rescue NSW Commissioner and other emergency services to develop a protocol in the event that simultaneous emergency events necessitate the re-allocation of resources while a Section 44 declaration is in place. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
REC315-3813 | 35 - Business and Industry in relation to industry | That, in order to ensure tourism businesses are prepared for natural disasters including bush fires, Resilience NSW work with NSW RFS and Destination NSW to develop bush fire preparedness support for tourism businesses, based on research into existing models. Over time, this support could be expanded to include other natural hazards. |
REC315-3836 | 17 - Assets and technology | That, in order to ensure frontline personnel have appropriate personal protective clothing during bush fires: |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3821 | 4 - Fire season preparation | That government agencies managing land (at all levels and through all agencies) be the best neighbours possible by considering their neighbours when undertaking activities related to bush fire preparation and having clear, two-way communication about these activities, with the aspiration that government landholders will be seen as highly desirable neighbours. |
REC315-3847 | 17 - Assets and technology | That, in order to ensure Australia’s fire fighting aerial capacity capitalises on existing assets and is made up of the right mix, Government: |
REC315-3799 | 9 - Community education | That at the start of each fire season, based on advice from the Bush Fire Coordinating Committee, Government provide a public statement with an evaluation of the likely fire season risk and the effectiveness of the planning and preparation for the upcoming season. This should be based on sophisticated monitoring of the key risk factors and signals for an extreme fire season. It should form the basis for clear public communication about these risks on a regional basis and the actions that Government proposes in preparation. |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3833 | 3 - Biodiversity | That Government invest in long-term ecosystem and land management monitoring, modelling, forecasting, research and evaluation, and harness citizen science in this effort. This will include, among other things: |
REC315-3869 | 42 - Culture and Heritage | That, in order to ensure Aboriginal people can access appropriate support during evacuation, Resilience NSW work with Local Emergency Management Committees and Aboriginal Affairs to ensure: |
REC315-3820 | 32 - Doctrine, standards, and reform | That Government amend the Rural Fires Act 1997 so that all public land management agencies be required to forward complaints received about bush fire hazards to the Commissioner of the NSW RFS. As an interim measure, heads of agencies should commence this practice immediately. |
REC315-3844 | 32 - Doctrine, standards, and reform | That, in order to enhance fire fighting strategies in severe conditions, the NSW RFS implements the following in respect to backburning: |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0954 | 24 - Govt responsibility | That a Ministerial Advisory Council be established to inform the Minister of matters relating to Rural Fire Service and SES volunteers. |
REC241-1011 | 32 - Doctrine, standards, and reform | That the focus of Rural Fire Service Queensland will be the protection of life, property and the environment from the threat and impact of wildfire. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-1026 | 17 - Assets and technology | That the Rural Fire Service Queensland catalogue accurately reflects the range of equipment available. |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-1031 | 32 - Doctrine, standards, and reform | That the State Government recognises the legal status of rural fire brigades as per Crown Law advice and addressed by Recommendations from this Review. |
REC241-1009 | 17 - Assets and technology | That the reflective livery on Rural Fire Service Queensland staff vehicles be kept to a minimum of a light bar and affixed Rural Fire Service Queensland logo. These vehicles are to be appropriate to the task and location. |
REC241-0979 | 24 - Govt responsibility | That the Queensland Government liaise with the Federal Government with a view to securing incentives for employers that recognise loss of income and employee time for emergency operations. |
REC241-1025 | 17 - Assets and technology | That an ‘Options Paper’ be developed by District Inspectors on the suitability and supply of PPE and equipment to volunteers for their district. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1001 | 24 - Govt responsibility | That the extent of forest and plantation fuel load fire risk in South East Queensland requires a designated government resources fire team to manage this risk and proactively conduct fuel mitigation burning; and provide a wildfire response to government land. |
REC241-0973 | 17 - Assets and technology | That all land on which rural fire brigade sheds are located be re-evaluated to formalise enforceable lease agreements. |
REC241-1024 | 17 - Assets and technology | That the Rural Fire Service Queensland revoke its current 20 year maximum age policy on volunteer Brigade vehicles to allow Brigades wanting to retain their vehicle to do so, providing the vehicle has an annual mechanical certificate. A 30 year maximum age policy for vehicles will replace the 20 year policy. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1029 | 17 - Assets and technology | That a policy be developed around the ownership, insurance and safe use and operation of All Terrain Vehicle 4WD vehicles by brigades for fire fighting purposes. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-1042 | 17 - Assets and technology | The issue of red and blue lights for RFSQ and SES vehicles be further pursued by the Department of Community Safety |
REC241-0970 | 17 - Assets and technology | That RFSQ retain responsibility for Air Operations and re-evaluate avenues for cost recovery when aircraft are used by other agencies. The coordination of incendiary tasking to support mitigation should sit with the RFSQ in coordination with other agencies |
REC241-1013 | 32 - Doctrine, standards, and reform | That Rural Fire Service Queensland undertake a risk management process for rural fire Brigade profiles across Queensland based on the principles in the Rural Fire Brigade Risk Management Guide, July 1999, and updated as necessary. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1028 | 17 - Assets and technology | That vehicles are fit for the purpose and the Brigade locality for which they are intended. A group of two volunteers, in conjunction with the Rural Fire Brigades Association Queensland, should be charged with reviewing current models and providing Recommendations on vehicle suitability. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-1039 | 17 - Assets and technology | That the State Government supply and logistics for Personal Protective Equipment and other equipment be urgently reviewed with a focus on timely and cost effective delivery to volunteer members. |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1012 | 17 - Assets and technology | Use of private aircraft to be at the discretion of District Inspector or Incident Control and reimbursement of fuel to be authorised accordingly. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-1027 | 17 - Assets and technology | That Rural Fire Service Queensland, in consultation with Primary Producer Brigade volunteers, redesign and reconfigure slip-on units to bring the total cost below the level required for asset registration. The redesign should allow for the foam system to be optional. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-1036 | 17 - Assets and technology | That each District Inspector prepare a report on vehicles required over the next ten years based on current age of fleet. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3536 | 32 - Doctrine, standards, and reform | The requirement for a rural council to establish a District Bushfire Prevention Committees under section 75 of the SA Fire and Emergency Services Act 2005 is removed. |
REC139-3541 | 32 - Doctrine, standards, and reform | Bushfire Management Committees will have the following functions: |
REC139-3546 | 22 - Role of local Gvt | Local Government to be maintained as an important component of bushfire management in South Australia because of the link with the community. |
REC139-3535 | 32 - Doctrine, standards, and reform | The requirement to establish Regional Bushfire Prevention Committees under section 73 of the SA Fire and Emergency Services Act 2005, is removed. |
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3540 | 32 - Doctrine, standards, and reform | The State Bushfire Coordination Committee will have the following members with experience in bushfire management: |
REC139-3545 | 32 - Doctrine, standards, and reform | SA Country Fire Service to be responsible for Bushfire Management Plan preparation, analysis of future risks trends based on investigation and executive support to Bushfire Management Committees. |
REC139-3534 | 32 - Doctrine, standards, and reform | The SA Bushfire Prevention Advisory Committee established under section 71 of the SA Fire and Emergency Services Act 2005, is removed and replaced with the State Bushfire Coordination Committee. |
REC139-3550 | 32 - Doctrine, standards, and reform | The State Bushfire Coordination Committee work with the Native Vegetation Council to develop more streamlined processes for the prescribed burning of native vegetation for hazard reduction. |
REC139-3539 | 32 - Doctrine, standards, and reform | The State Bushfire Coordination Committee will have the following functions: |
REC139-3544 | 32 - Doctrine, standards, and reform | The area of responsibility for Bushfire Management Committees will be established based on bushfire risk and the capacity of the area to cooperate and collaborate. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
REC139-3538 | 32 - Doctrine, standards, and reform | The requirement to establish a Bushfire Management Committee is inserted into the SA Fire and Emergency Services Act 2005. |
REC139-3543 | 32 - Doctrine, standards, and reform | Bushfire Management Committees be given the appropriate powers under the SA Fire and Emergency Services Act 2005 to ensure that bushfire management strategies that have been identified in a Bushfire Management Plan or any other action to reduce bushfire risk, are completed by individuals, the community, agencies or organisations. |
REC139-3548 | 32 - Doctrine, standards, and reform | The current provisions for permit to light and maintain fire under Section 81 of the SA Fire and Emergency Services Act and Regulations 2005 to be reviewed for improvement with an accreditation for a self-regulation process. |
REC139-3537 | 32 - Doctrine, standards, and reform | The requirement for a rural council to appoint a suitably qualified Fire Prevention Officer under section 77 of the SA Fire and Emergency Services Act 2005 is removed. |
REC139-3542 | 32 - Doctrine, standards, and reform | Bushfire Management Committees will have the following members who reside and/or are employed/assigned in the area of responsibility, with experience in bushfire management: |
REC139-3547 | 32 - Doctrine, standards, and reform | The principle of developing Codes of Practice for Bushfire Management, referenced in the SA Fire and Emergency Services Act and Regulations 2005 be endorsed and further developed by the State Bushfire Coordination Committee. |