REC321-4206 | 3 - Biodiversity | We recommend that DELWP conducts more effective ecosystem resilience monitoring by: - setting a target for regions on the quantity of ecosystem resilience monitoring assessments that they should complete annually - setting an outcomes-level target that defines desirable values for key ecosystem resilience metrics - reporting publicly against all of the metrics in its Measuring Ecosystem Resilience in Strategic Bushfire Management Planning policy in its fuel management reports. |
REC321-4210 | 3 - Biodiversity | We recommend that CFA (in consultation with FRV) improves its values checks by providing ongoing state-wide support to regional vegetation management officers and leveraging any relevant systems or capabilities from DELWP to conduct values checks through guidance, training and ongoing funding. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4213 | 3 - Biodiversity | We recommend that DELWP improves the effectiveness, consistency and transparency of its environmental and cultural values checks by: - finalising its review of operational values checking processes and committing to an implementation plan - clarifying and formalising principles and procedures, making them publicly available where possible - improving capability and capacity among staff responsible for carrying out values checks, for example through training - developing a long-term program of work and investment to improve the quality, consistency and comprehensiveness of underlying datasets - increasing alignment in regard to values checks between agencies carrying out fuel management. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4197 | 36 - Volunteers | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department develop and resource an ongoing strategy to coordinate spontaneous volunteers that can be activated before, during or after emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1345 | 36 - Volunteers | That issues of animal welfare be given a higher practical priority in the planned burning process on the ground, including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3474 | 24 - Govt responsibility | That the Victorian Government consider all available means, consistent with conservation values, for substantially increasing the access of apiarists to the public land estate. |
REC155-3473 | 24 - Govt responsibility | That the Victorian Government expedite the implementation of its 2006 election commitment to provide four wheel drive clubs with access to management vehicle only tracks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2239 | 24 - Govt responsibility | That any local level agreements developed to address geographically specific risks or issues must be consistent with State-level arrangements. |
REC104-2303 | 24 - Govt responsibility | That Interstate Agreements prepared by the fire agencies be reviewed to include protocols for the joint release of consistent and appropriate information relating to fires burning across State borders. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2328 | 36 - Volunteers | That CFA, VICSES and other volunteer-based emergency service organisations develop proposals in support of the strategies for sustainable volunteerism, and that the State Government advocate these initiatives to the Federal Government. |
REC104-2232 | 24 - Govt responsibility | That Government in the development of its statewide water policy includes appropriate consideration of access to water for firefighting. |
REC104-2256 | 24 - Govt responsibility | That the State Emergency Operations Centre develop and maintain strong and close links with the State Emergency Response Coordination Centre, if collocation is not possible. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2230 | 24 - Govt responsibility | That DSE investigates whether such agreements should exist with other government Departments and agencies, particularly those with officers located in rural Victoria who may be involved in fire response and support operations in the future, based on their expertise and experience. |
REC104-2255 | 24 - Govt responsibility | That the options of collocating the State Emergency Response Coordination Centre with the new State Emergency Operations Centre |
REC104-2321 | 24 - Govt responsibility | That Government confirms that the Model of Fire Cover/Fire Safety Victoria strategy should be a seamless model for the whole of the State and include both private and public land. |
REC104-2225 | 24 - Govt responsibility | That the Victoria Emergency Management Council establish a sub-committee by June 2004 to ensure an all-agency and appropriate industries’ policy framework is developed and agreed in respect to the planning for fire prevention, mitigation and suppression. |
REC104-2254 | 24 - Govt responsibility | That a single state-of-the-art all hazards State Emergency Operations Centre be established for Victoria. This could, if necessary, be implemented in stages, initially incorporating DSE, CFA, MFESB and the State Aircraft Unit. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2247 | 24 - Govt responsibility | That an appropriately resourced, national aerial firefighting strategy is urgently required, and that the Victorian Government make representations to the Commonwealth to support the Australasian Fire Authorities Council recommendations |
REC104-2315 | 24 - Govt responsibility | That the Privacy Commissioner be asked for advice in the development of this model. |
REC104-2192 | 24 - Govt responsibility | That, according to available scientific evidence, a decision regarding cattle grazing in the High Country should not be based on the argument that ‘grazing prevents blazing.’ |
REC104-2331 | 24 - Govt responsibility | That a State Emergency Operations Centre be established to replace the existing separate fire agency centres. This could, if necessary, be initially confined to being a State Fire Operations Centre as recommended in Chapter 18, Part D. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3956 | 24 - Govt responsibility | It is strongly recommended that no public department of possible combination of public departments interested in forests should be permitted to gain control of this authority. |
REC015_3954 | 24 - Govt responsibility | It is recommended that each public department or body which may now or hereafter control forest areas be allowed to pursue its own policy of fire prevention and suppression. As each such body is responsible directly or indirectly to Parliament it must be allowed to carry its responsibility in its own manner. It is strongly recommended that no such department be given authority over any other body in matters relating to fire prevention or suppression. If it is ultimately shown that a department is unfit to discharge the duty involved other measures may be taken. |