REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2463 | 6 - Insurance and legal liability | Principles, applicable to all tourist budgets, covering liabilities for costs and shelter in the event of evacuation should be developed and promulgated as part of tourism marketing. |
REC308-2461 | 24 - Govt responsibility | A strategy should be developed between the key tourism and transport operators, and local and state government. It should address the arrival of visitors and tourists after a disaster, and should ensure that their arrival matches communities’ needs for recovery and return to normal business. The Department of Tourism, Major Events, Small Business and the Commonwealth Games should monitor its implementation. |
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1206 | 33 - Relief and recovery | Transition from Response to Recovery: That Region Emergency Management Committees meet post event to: · consider available impact data · determine the need to establish a Recovery Committee · document the rationale for the decision · advise the Office of Emergency Management of the decision. |
REC281-1204 | 33 - Relief and recovery | Transition from Response to Recovery That the Office of Emergency Management, in consultation with the NSW Police Force Emergency Management Unit develops a template for handover of the Response to Recovery Phase of an emergency. |
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
REC281-1202 | 13 - Mapping and data quality | Impact Assessment Data Collection: The Office of Emergency Management continues to progress the Impact Assessment Data Collection Project and: · incorporate recovery schema in Rapid Impact Assessments · review procedures for collection of Rapid Impact Assessment Data · review and combine current templates into one, single template for Impact Assessment Reports that is used by all agencies · further develop Impact Assessment Guidelines for agency personnel undertaking impact assessments |
REC281-1207 | 33 - Relief and recovery | Communicating in Recovery: The Office of Emergency Management: · considers the development of a communications and engagement strategy for major disaster events · progresses the development of the ‘Communicating In Recovery’ Guideline in the Local Recovery Toolkit. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1420 | 24 - Govt responsibility | The Department of Housing and Public Works should consider preparing an annual communique to asset owners of, and local governments with access to public cyclone shelters, outlining the maintenance and certification process and pre-season status. |
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
REC272-1418 | 24 - Govt responsibility | A state-wide engagement strategy is coordinated to ensure community messaging is consistent across all levels of Queensland’s disaster management arrangements. |
REC272-1416 | 24 - Govt responsibility | A state-wide strategy, including a common definition, is developed for identifying and engaging vulnerable people in emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1151 | 24 - Govt responsibility | Government Communications Coordination |
REC267-1161 | 33 - Relief and recovery | VIP Visits |
REC267-1148 | 33 - Relief and recovery | Planning for Recovery Centres Recovery Centres are a proven means of providing support to affected communities. More comprehensive recovery planning is needed at local levels, including the identification of potential Recovery Centre sites in Local EM Plans to help facilitate streamlined establishment of the Centres in future events. Consideration should be given to developing a clear set of standard messaging regarding |
REC267-1160 | 33 - Relief and recovery | Transition from Response to Recovery |
REC267-1156 | 33 - Relief and recovery | Streamlining NDRRA Grants Processes |
REC267-1155 | 33 - Relief and recovery | MP Recovery Reference Group |
REC267-1163 | 33 - Relief and recovery | Corrections Volunteer Labour Teams |
REC267-1152 | 13 - Mapping and data quality | Impact Assessment Data Sharing Project |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3496 | 21 - Role of Commonwealth Government | The Bureau of Meteorology contact list for severe weather warning be strategically managed in consultation with Emergency Service Organisations, to identify critical contacts. The Bureau of Meteorology must ensure the detail for these critical contacts remains up to date. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3518 | 24 - Govt responsibility | The Department of Premier and Cabinet, the Office of the Emergency Services Commissioner and other relevant departments conduct further work to determine the need for a power to appoint a coordinator of essential services restoration. |
REC156-3492 | 22 - Role of local Gvt | The review of the municipal emergency management planning guidelines being led by the Office of the Emergency Services Commissioner clarify local governments’ role in community information about emergencies. |
REC156-3514 | 24 - Govt responsibility | The State Government endorse the establishment of the Victorian Emergency Information Line and it is developed with appropriate protocols to ensure linkages and information flows to the energy sector. |
REC156-3490 | 24 - Govt responsibility | The Department of Human Services improve its communication with councils to enhance delivery of recovery services. |
REC156-3506 | 26 - Research | The Office of the Emergency Services Commissioner facilitate further research into technologies that will reduce the need for the public to speak to an operator during an emergency as a component of the proposed emergency warning and alert system and Victorian Emergency Information Line. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3486 | 24 - Govt responsibility | The emergency management arrangements include the development of partnerships between the public and private sectors, in particular the involvement of government departments and essential services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3525 | 24 - Govt responsibility | In any future disaster of comparable proportions, consideration should be given to the co-location of the Building Coordination Centre and the principal One Stop Shop. |
REC136-3529 | 24 - Govt responsibility | The Queensland Government should consider the endorsement of transitional arrangements proposed in this report, in order to ensure as far as possible the smooth completion of the recovery and the ultimate return to government operations as usual in the cyclone-affected area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC118-3644 | 21 - Role of Commonwealth Government | That the Prime Minister’s Science, Engineering and Innovation Council requests that the Australian Government, through the Australian Emergency Management Committee, develops an effective pathway to incorporate hazard science into emergency management policy. |
REC118-3643 | 21 - Role of Commonwealth Government | Consolidate the Australian Government decision to establish an Australian Tsunami Warning System through a long-term government commitment to ensure a sustainable and effective national tsunami warning system beyond the current four-year initiative. |
REC118-3642 | 26 - Research | Establish a Regional Centre of Excellence for Tsunamis to focus Australian and international science/research and collaboration on the challenge of understanding tsunamis and mitigating their consequences. |