REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4335 | 16 - Training and behaviour | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services update and deliver training on the workflow reviewed (as per Recommendation 3) of the current Emergency Alert system to all persons responsible at a local, district and state level by 1 November 2022. Training should address system constraints and system complexities in addition to the process of requesting, composing (including Clear Explicit Translatable Language [CETL]), authorising and issuing Emergency Alerts. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
REC309-2474 | 16 - Training and behaviour | The provision of system-wide tools, education, guidance and testing for requests for assistance is strengthened to enhance understanding and outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2464 | 16 - Training and behaviour | The provision of system-wide education, guidance and testing to enhance requests for Assistance is strengthened. |
REC308-2461 | 24 - Govt responsibility | A strategy should be developed between the key tourism and transport operators, and local and state government. It should address the arrival of visitors and tourists after a disaster, and should ensure that their arrival matches communities’ needs for recovery and return to normal business. The Department of Tourism, Major Events, Small Business and the Commonwealth Games should monitor its implementation. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1205 | 16 - Training and behaviour | Department of Premier and Cabinet Regional Coordinators: Continue to build the capability of the Department of Premier and Cabinet Regional Coordinator role in recovery operations by providing: · on the ground support for Regional Coordinators during recovery operations by REMOs or OEM Recovery Team · training and developmental opportunities for Regional Coordinators to prepare them for working in the disaster recovery environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1151 | 24 - Govt responsibility | Government Communications Coordination |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0804 | 26 - Research | Clarify roles, responsibilities and consider funding options for post-event collection of data and flood intelligence. |
REC238-0813 | 26 - Research | Develop and maintain a comprehensive flood model and flood modelling framework for the Hawkesbury-Nepean Valley. |
REC238-0807 | 26 - Research | Develop a comprehensive road evacuation network model for floods in the Hawkesbury-Nepean floodplain to inform evacuation capacity assessments and strategic transport and land use planning, and to assist with the real-time operational management of evacuation during floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3486 | 24 - Govt responsibility | The emergency management arrangements include the development of partnerships between the public and private sectors, in particular the involvement of government departments and essential services. |
REC156-3518 | 24 - Govt responsibility | The Department of Premier and Cabinet, the Office of the Emergency Services Commissioner and other relevant departments conduct further work to determine the need for a power to appoint a coordinator of essential services restoration. |
REC156-3514 | 24 - Govt responsibility | The State Government endorse the establishment of the Victorian Emergency Information Line and it is developed with appropriate protocols to ensure linkages and information flows to the energy sector. |
REC156-3506 | 26 - Research | The Office of the Emergency Services Commissioner facilitate further research into technologies that will reduce the need for the public to speak to an operator during an emergency as a component of the proposed emergency warning and alert system and Victorian Emergency Information Line. |
REC156-3495 | 16 - Training and behaviour | The Department of Primary Industries should work through the appropriate Ministerial Councils to seek alignment of competency standards for line workers across jurisdictions. |
REC156-3490 | 24 - Govt responsibility | The Department of Human Services improve its communication with councils to enhance delivery of recovery services. |