Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1207 | 33 - Relief and recovery | Communicating in Recovery: The Office of Emergency Management: · considers the development of a communications and engagement strategy for major disaster events · progresses the development of the ‘Communicating In Recovery’ Guideline in the Local Recovery Toolkit. |
REC281-1206 | 33 - Relief and recovery | Transition from Response to Recovery: That Region Emergency Management Committees meet post event to: · consider available impact data · determine the need to establish a Recovery Committee · document the rationale for the decision · advise the Office of Emergency Management of the decision. |
REC281-1204 | 33 - Relief and recovery | Transition from Response to Recovery That the Office of Emergency Management, in consultation with the NSW Police Force Emergency Management Unit develops a template for handover of the Response to Recovery Phase of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1163 | 33 - Relief and recovery | Corrections Volunteer Labour Teams |
REC267-1154 | 36 - Volunteers | Coordination of Volunteer Support |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
REC267-1161 | 33 - Relief and recovery | VIP Visits |
REC267-1148 | 33 - Relief and recovery | Planning for Recovery Centres Recovery Centres are a proven means of providing support to affected communities. More comprehensive recovery planning is needed at local levels, including the identification of potential Recovery Centre sites in Local EM Plans to help facilitate streamlined establishment of the Centres in future events. Consideration should be given to developing a clear set of standard messaging regarding |
REC267-1160 | 33 - Relief and recovery | Transition from Response to Recovery |
REC267-1156 | 33 - Relief and recovery | Streamlining NDRRA Grants Processes |
REC267-1155 | 33 - Relief and recovery | MP Recovery Reference Group |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1604 | 8 - Communications and warnings | Governments and other stakeholders consider reviewing their existing emergency management arrangements to ensure public communications are clear and the public is kept informed of the incident response. |
REC233-1603 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy (DBCDE) to work with the Triple Zero Awareness Work Group through Australian Communications and Media Authority's (ACMA) Emergency Service Advisory Committee to review Triple Zero awareness messages with regard to telecommunications outages. |
REC233-1592 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy will work with the Communications Sector Group within the Trusted Information Sharing Network to develop best practice guidance for owners of critical communications infrastructure regarding public messaging during a prolonged telecommunications outage covering: |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
REC215-1877 | 39 - Disaster Risk Management | Regulators can help to achieve improved outcomes by considering the issues identified by this review |
REC215-1876 | 39 - Disaster Risk Management | Fire services can improve outcomes by initiating discussions with landfill operators about fire management planning and emphasising the critical importance of water supplies and early intervention |
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
REC215-1873 | 8 - Communications and warnings | Fire services can improve outcomes by implementing standard procedures that ensure the welfare and safety of crews and the public are not compromised |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
REC204-1920 | 6 - Insurance and legal liability | The Attorney General gives urgent consideration to determining an ex gratia payment for: |
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
REC204-1910 | 6 - Insurance and legal liability | As part of its review of its contract management processes, Tourism WA (with the Board of Tourism WA taking a lead role) should amend its contract template for event sponsorship to ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1735 | 36 - Volunteers | A. The CFA continue to explore and develop initiatives with modern information and communication technologies to maximise the benefits that they may bring to volunteer involvement in the CFA. |
REC197-1770 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, review the arrangements for the reimbursement of volunteer expenses. This review could be done in conjunction with the review of possible reimbursement of employers of CFA volunteers as recommended in Recommendation 5. |
REC197-1734 | 36 - Volunteers | A. Consideration be given to the VFBV being funded directly by Government rather than by the CFA. |
REC197-1745 | 36 - Volunteers | The CFA revisit with the UFU the arrangements relating to Community Education Firefighters/Fire Officers and the use of volunteers in this role. |
REC197-1742 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, develop initiatives and strategies that will maximise the involvement of young people as volunteers and their retention as volunteers. |
REC197-1740 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, develop and introduce an arrangement whereby a volunteer can transfer from one brigade to another and still remain a member of the CFA, without the need to resign. |
REC197-1739 | 36 - Volunteers | The CFA, in consultation with the VFBV and volunteers, develop a systemic exit strategy, which ensures that relevant information is captured consistently across all brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3008 | 1 - Land-use and building regs | That any building fitted with heat-activated closing devices or fire and smoke doors be assessed to establish if it constitutes a fire hazard under section 165 of the Building Act 2000 and that, where appropriate, such doors be replaced with smoke activated doors. |