Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3347 | 21 - Role of Commonwealth Government | The proposal of the Productivity Commission’s Research Report (Review of Regulatory Burden on the Upstream Petroleum (Oil and Gas) Sector, April 2009) to establish a NOPR should be pursued at a minimum. |
REC177-3358 | 21 - Role of Commonwealth Government | The body established to undertake a central coordination and facilitation role in the event of any future blowout in Commonwealth waters should undertake to make all relevant information publically available from one, authoritative and easy to access source. |
REC177-3346 | 21 - Role of Commonwealth Government | A single, independent regulatory body should be created, looking after safety as a primary objective, well integrity and environmental approvals. Industry policy and resource development and promotion activities should reside in government departments and not with the regulatory agency. The regulatory agency should be empowered (if that is necessary) to pass relevant petroleum information to government departments to assist them to perform the policy roles. |
REC177-3357 | 21 - Role of Commonwealth Government | In any future similar blowout or offshore emergency situation, the Minister appoint (through either a NOPR or the relevant Department) a senior public servant to establish and oversight a central coordinating body that will facilitate interaction between regulators, industry, AMSA and the owner/operator. Primary responsibility for stopping a blowout should remain with the owner/operator but should be subject to direction from the central coordinating body in consultation with stakeholders (including the owner/operator). |
REC177-3376 | 21 - Role of Commonwealth Government | In carrying out a review of PTTEPAA’s permit and licence, the Minister should have regard to this Report, particularly (i) the adverse findings set out in this Chapter; and (ii) the extent to which PTTEPAA has implemented the Action Plan submitted to the Inquiry, or otherwise addressed the matters canvassed in this Report. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3351 | 21 - Role of Commonwealth Government | In the future, and in the interests of ensuring that all possible well control options are comprehensively pursued to exhaustion, decisions as to well control response options should be the result of collaboration between the regulator and the operator rather than leaving one party to make unilateral judgements as to the appropriateness of various well control operations. The regulator should provide transparent and contemporaneous explanations to the public of all well control options under consideration at any particular time. |
REC177-3375 | 21 - Role of Commonwealth Government | For the purposes of that review, the Minister should issue a ‘show cause’ notice to PTTEPAA under s 276 of the OPGGS Act. |
REC177-3274 | 21 - Role of Commonwealth Government | The Minister should appoint a senior policy adviser to investigate and report on the best means to implement the recommendations contained in this Chapter 3 of this report. |
REC177-3349 | 21 - Role of Commonwealth Government | In the meantime, the Minister should: |
REC177-3372 | 21 - Role of Commonwealth Government | OSCPs should be endorsed by AMSA prior to regulatory approval to ensure that they align with the National Plan. Once field operations commence, the capability of operators should be assessed against their plans, and exercises conducted to ensure the plans remain effective. |
REC177-3348 | 21 - Role of Commonwealth Government | Responsibility for well integrity should be moved to NOPSA (as also proposed by the Productivity Commission). |
REC177-3371 | 21 - Role of Commonwealth Government | The Government should examine the scope for a single environment plan to meet the regulatory requirements of both the OPGGS Act and the EPBC Act. This could possibly be achieved by way of bilateral agreements and accreditation arrangements and/or legislative amendment. |