Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3813 | 35 - Business and Industry in relation to industry | That, in order to ensure tourism businesses are prepared for natural disasters including bush fires, Resilience NSW work with NSW RFS and Destination NSW to develop bush fire preparedness support for tourism businesses, based on research into existing models. Over time, this support could be expanded to include other natural hazards. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4008 | 35 - Business and Industry in relation to industry | Where dust exists in quantity, and under conditions favourable for ignition, it should be periodically and sufficiently dampened by water |
REC002-4004 | 35 - Business and Industry in relation to industry | Where safety-lamps are used, and the obligation is laid upon the men to cleanse the same, all examinations, tests, and repairs to these should be done by the owners. |
REC002-4003 | 35 - Business and Industry in relation to industry | Where gas exists, and no provisions are made for its constant removal, no shots should be fired, and, where permitted in a gassy mine, shots should be fired only by a man specially appointed, and at such hours when the miners are not within the mine. All shots should be tamped by stone well damped, and only copper or wooden tools should be employed. As far as possible the use of explosives should be discouraged, and skilful mining encouraged. Danger-boards should be placed further from the faces whence gas issues (say), where practicable, 50 yards. |
REC002-4001 | 35 - Business and Industry in relation to industry | The Commission consider that in all mines where gas exists the course of the air should be directed to sweep along the working-faces; in mines worked by Pillar and Stall, bratticing must be resorted to to carry the gas from the face as it issues, and so prevent any accumulation of explosive gases or of gases inimical to life. In cases where gas exists it would be better that no bords should be broken off the back or return heading or supplied with air fouled by dangerous gases. The panel system of working by confining and localising districts, or some modification thereof, might be pursued with advantage. |
REC002-4010 | 35 - Business and Industry in relation to industry | The Commission do not approve of removing any responsibility from the management by increasing the power or number of the Inspectors. The visits of these officials should, so far as possible, be visits of surprise. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2064 | 35 - Business and Industry in relation to industry | Encourage businesses to consider human influenza pandemics in business continuity planning. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2072 | 35 - Business and Industry in relation to industry | Relax the requirement for medical certificates in the event of an outbreak. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1157 | 35 - Business and Industry in relation to industry | Improvements to the Targeting of Government Support to Build Primary Industry Resilience |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1594 | 35 - Business and Industry in relation to industry | When businesses review their business continuity plans they should take into account the prospect of a major telecommunications outage that affects both mobile and fixed voice and data services. |
REC233-1600 | 35 - Business and Industry in relation to industry | Community service providers consider, in consultation with relevant government authorities, reviewing their current privacy practices concerning personal information about vulnerable persons to ensure they are able to appropriately share information during major disruptive incidents. |
REC233-1593 | 35 - Business and Industry in relation to industry | Telstra and other service providers to consider improving processes to assist customers with setting up temporary call diversions during future outages. |
REC233-1599 | 35 - Business and Industry in relation to industry | Providers of personal alert devices consider telecommunications outages in their service continuity plans and provide clear advice to their customers regarding their options during a telecommunications service outage. |
REC233-1591 | 35 - Business and Industry in relation to industry | While noting the importance of voice communications, telecommunications providers should consider as part of their mass outage business continuity planning, options for the provision of interim mobile broadband services for the community e.g. local wireless broadband access hubs (i.e. Wi-Fi). |
REC233-1598 | 35 - Business and Industry in relation to industry | Community service providers consider developing information and advice regarding telecommunications outages for clients managed remotely using telecommunication services, including personal alert devices. |
REC233-1597 | 35 - Business and Industry in relation to industry | Community service providers consider updating their business continuity plans to take into account the possibility of a major telecommunications outage involving both fixed and mobile voice and data services. |
REC233-1595 | 35 - Business and Industry in relation to industry | Department of Broadband, Communications and the Digital Economy to work with the Trusted Information Sharing Network’s Communications Sector Group to develop general telecommunications continuity advice for businesses and individuals to assist in developing continuity plans. |
REC233-1601 | 35 - Business and Industry in relation to industry | Community service providers consider in their business continuity planning how they could assist with facilitating access to telecommunications services for the public during mass outages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1881 | 35 - Business and Industry in relation to industry | Landfill operators must be encouraged to achieve greater compliance with the required outcomes relating to fire that are set out in the BPEM guidelines, particularly with regard to water supplies |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0708 | 35 - Business and Industry in relation to industry | The Queensland Government should work collaboratively with the Commonwealth Government and mine operators to ensure co-ordinated and effective monitoring of salts, metals and other contaminants in marine environments that may be affected by mine discharges. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0763 | 35 - Business and Industry in relation to industry | Seqwater should ensure that the Somerset Dam gallery is not susceptible to flooding during overtopping events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0336 | 20 - Role of police | Victoria Police, under the auspice of the Regional Emergency Response Plan, lead a task force to ensure that the Princes Highway is treated as an asset of significance and an appropriate risk-based approach is adopted to minimise the impact of fire. This approach is to be integrated into regional and municipal fire management plan |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3006 | 20 - Role of police | That the recommendations contained in the Police Operational Debrief Report of 22 October 2007 to 7 November 2007, submitted to the Coroner, be further considered by the Tasmania Police for adoption where considered appropriate by Tasmania Police. |
REC166-2999 | 35 - Business and Industry in relation to industry | That Aurora ensure that regular audits are conducted of all electrical systems of all commercial buildings to confirm that they comply with modern standards. |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3020 | 35 - Business and Industry in relation to industry | ESWG recommends that as far as reasonably practical, arrangements for load shedding be as transparent as possible to give consumers confidence in the process. |
REC162-3013 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to consolidating gas and electricity network status and emergency information on one webpage for central communication. |
REC162-3019 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to the spokesperson role AEMO can undertake during an electricity and/or gas supply shortfall in its covered markets and relevant jurisdictional emergencies, noting that AEMO has clear responsibility for the bulk supply of electricity as outlined in the Power System Emergency Management Plan and the Victorian wholesale gas market, and that for multi-jurisdiction gas supply emergencies, any AEMO spokesperson role would be to reflect NGERAC’s advice. |
REC162-3012 | 35 - Business and Industry in relation to industry | ESWG recommends reviewing AEMO’s Gas Bulletin Board (GBB) to ensure it is effectively communicating all publicly available information to market participants to assist in monitoring daily gas supplies, and any changes to the GBB rules required to improve information and awareness of any potential shortages that will assist the market to make the necessary investments and/or adjustments in maintenance. |
REC162-3018 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of a review of communication protocols with the aim of achieving high level policy consistency of communication across jurisdictions to the maximum extent possible. |
REC162-3011 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to expanding the role of AEMO in providing market information on gas by: |
REC162-3017 | 35 - Business and Industry in relation to industry | ESWG notes NGERAC already informally advises ministers on the possible effects of gas emergencies on electricity supplies. ESWG recommends formalising this role by acknowledging it in NGERAC’s MOU. ESWG also recommends an editorial review of NGERAC’s MOU to ensure accuracy and consistency. |
REC162-3022 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of how to ensure good communication and flow of information between the liquid fuels and other energy sectors. One approach that may be considered is that: |
REC162-3010 | 35 - Business and Industry in relation to industry | Energy Security Working Group (ESWG) recommends consideration be given to government and industry working together to understand that investment opportunities in the energy sector are realised in a timely fashion to better manage potential longer term supply shortfalls. |
REC162-3015 | 35 - Business and Industry in relation to industry | ESWG recommends National Gas Emergency Response Advisory Committee maintain its industry, jurisdiction and consumer representation noting the importance of input from each of these groups in developing its advice. |
REC162-3021 | 35 - Business and Industry in relation to industry | ESWG notes that existing and future contracts and the impending introduction of the Short Term Trading Market will be the primary mechanisms for addressing future gas supply shortfalls. |
REC162-3014 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to leveraging AEMO’s expanded responsibilities in gas markets by undertaking the role of the National Gas Emergency Response Advisory Committee (NGERAC) Secretariat while the Commonwealth continue as Chair, with the Chair’s position to be reviewed once the short term trading market (STTM) commences in June 2010. ESWG also recommends that the review be undertaken by NGERAC jurisdictional members. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3502 | 35 - Business and Industry in relation to industry | The Emergency Services Telecommunications Authority in partnership with Telstra should develop testing regimes that will ensure the integrity of the call queue arrangements and correct configuration of the Recorded Voice Announcements. |
REC156-3493 | 35 - Business and Industry in relation to industry | The electricity distribution businesses and retailers work with the Department of Human Services and hospitals to review the registration, notification and removal process for those on life support machinery. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1804 | 35 - Business and Industry in relation to industry | That the Chief Officer and the Editors of all newspapers and other media outlets develop a Memorandum of Understanding that ensures that all CFS press releases concerning total fire ban days and ongoing bushfire incidents are published in full. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-2004 | 35 - Business and Industry in relation to industry | That the ACT Government and ActewAGL jointly develop and implement protocols that will create a procedure whereby each of the water and sewerage, electricity and gas distribution networks, or parts thereof, can safely and promptly be manipulated, controlled, shut off, isolated or disconnected under emergency conditions. |
REC126-1970 | 35 - Business and Industry in relation to industry | That the Emergency Services Agency reconsider and revise the arrangement that exists between the ACT Fire Brigade and Canberra airport in relation to the provision of assistance |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2121 | 35 - Business and Industry in relation to industry | The Working Group recommends that the Australian Government investigate, in consultation with the finance and banking sector, the development of arrangements to ensure that essential transactions can continue in the event of a catastrophic failure of the banking system that includes access to cash. |
REC116-2102 | 35 - Business and Industry in relation to industry | The Working Group recommends that jurisdictions identify appropriate commercial organisations/bodies able to ensure maintenance of supply of food items and packaged water to commercial outlets in times of disaster. |
REC116-2101 | 35 - Business and Industry in relation to industry | The Working Group recommends that each jurisdiction; |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2221 | 35 - Business and Industry in relation to industry | That CFA and the Plantation Industry jointly develop and agree on Fire Prevention Guidelines for Plantations by June 2004, to be then promoted and distributed by the Industry. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3962 | 35 - Business and Industry in relation to industry | It is recommended that the matter be submitted to experts, of which there are many in the Public Service; and that such experts determine the best manner of construction. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |