Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC270-1146 | 12 - EM agency and authority | Strengthens its oversight role as lead agency for mitigating Queensland's bushfire risk to acceptable levels by: · coordinating land managers' efforts to assess and mitigate bushfire risk · formalising the role of fire management groups to manage Queensland's fuel loads, including reporting planned and conducted hazard reduction burns and the effectiveness of hazard reduction burns · amending its bushfire mitigation planning to address prevention, preparedness, response and recovery and to manage Queensland's residual bushfire risk · developing and implementing a coordinated strategy to address arson, deterring would-be offenders and rehabilitating convicted offenders · working with local councils to develop and communicate local bushfire plans for communities located in high risk, bushfire-prone areas |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
REC268-1430 | 26 - Research | Formal research is commissioned or meta-analysis is undertaken to provide a better understanding of the effectiveness of warnings and other relevant message testing. The outcomes are disseminated to all disaster management entities and learnings used to inform practice. |
REC268-1429 | 2 - Emergency powers | A dynamic online list of positions and contact details is published for those able to authorise Emergency Alert, and made accessible to local government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2654 | 26 - Research | That the Department of Health determines the underlying causes for the rapid growth in demand for Queensland Ambulance Service emergency responses and implements strategies to address these causes and reduce the cost per head of population to service this demand. |
REC240-2651 | 13 - Mapping and data quality | That the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomesThat the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1627 | 12 - EM agency and authority | The Emergency Services Agency (ACT Rural Fire Service headquarters) should implement a system to provide assurance to the Chief Officer of the ACT Rural Fire Service that personnel and equipment readiness meets requirements. |
REC228-1626 | 12 - EM agency and authority | The Emergency Services Agency and the Territory and Municipal Services Directorate should clarify the timing of the requirement for meeting firefighter fitness requirements, as set out in ACT Rural Fire Service operating procedures and the Territory and Municipal Directorate’s Enterprise Agreement, and give priority to meeting that requirement. |
REC228-1624 | 12 - EM agency and authority | The Emergency Services Agency should: |
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3049 | 12 - EM agency and authority | ACTAS should enhance its approach to demand modelling in order to better guide current and future ambulance resourcing by: |
REC159-3048 | 12 - EM agency and authority | ACTAS should enhance its approach to risk management by: |
REC159-3046 | 12 - EM agency and authority | ACT Ambulance Service (ACTAS) should revise its Business Plan to address key priorities and activities for each key service delivery function. This would include clearer expected outputs to be delivered annually and their prioritisation. |
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
REC159-3054 | 12 - EM agency and authority | ACTAS should improve systems to manage its non-emergency transport services, provide training and guidance to staff on use of these systems, and implement a quality assurance process. |
REC159-3052 | 12 - EM agency and authority | ACTAS should develop and implement as a matter of priority, appropriate strategies to address declining response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3120 | 12 - EM agency and authority | QFRS provide assistance to brigades in determining and budgeting for their resource needs. |
REC150-3113 | 12 - EM agency and authority | QFRS provide guidance and support to rural fire brigades in the development of their one year operational plan and three year management plan. |
REC150-3119 | 12 - EM agency and authority | QFRS implement a system to collate and analyse brigade funding information. |
REC150-3112 | 12 - EM agency and authority | Queensland Fire and Rescue Service (QFRS) implement a forward planning process specific to rural fire management as part of the QFRS strategic planning process, which involves regional and area offices and incorporates: |
REC150-3118 | 12 - EM agency and authority | QFRS review the financial accountability and audit requirements of the rural fire brigades to reflect their status as part of QFRS. |
REC150-3124 | 12 - EM agency and authority | QFRS establish a suitable process to reliably capture that information. |
REC150-3117 | 12 - EM agency and authority | QFRS ensure compliance with the brigade accountability requirements for funding received by rural fire brigades as specified in the Rural Fire Brigade Manual |
REC150-3123 | 12 - EM agency and authority | QFRS determine the performance information needed to support effective decision making . |
REC150-3116 | 12 - EM agency and authority | QFRS implement a brigade issues management process to capture, manage and report specific brigade issues. |
REC150-3121 | 12 - EM agency and authority | QFRS utilise performance information on brigade activity as a factor in determining brigade resource and funding needs. |
REC150-3114 | 12 - EM agency and authority | QFRS implement a process to review brigade plans and incorporate specific issues identified into forward planning at the area and regional levels. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |