REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3474 | 24 - Govt responsibility | That the Victorian Government consider all available means, consistent with conservation values, for substantially increasing the access of apiarists to the public land estate. |
REC155-3473 | 24 - Govt responsibility | That the Victorian Government expedite the implementation of its 2006 election commitment to provide four wheel drive clubs with access to management vehicle only tracks. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3408 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3250 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
REC061-3242 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3415 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |