Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1344 | 25 - Inquiry, audit, lessons management and after action review | That a review of the cross‑tenure approach be undertaken to determine its effectiveness and to address issues that arise in fire prevention on private and public land. |
REC299-1343 | 25 - Inquiry, audit, lessons management and after action review | That the Government conduct a review of fire prevention |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0263 | 12 - EM agency and authority | that QFRS investigate and implement an internal email system for rural fire brigades. |
REC191-0272 | 12 - EM agency and authority | that QFRS establish the position of Assistant Commissioner, Rural Fire Service to lead the proposed Rural Fire Service division within QFRS. |
REC191-0262 | 12 - EM agency and authority | that QFRS include consultation with rural fire brigades as mandatory when boundary changes are proposed. |
REC191-0271 | 12 - EM agency and authority | that QFRS should establish a Rural Fire Service division within QFRS with the aim of integrating and strengthening the relationship between the urban and rural fire services. |
REC191-0270 | 12 - EM agency and authority | that QFRS implement procedures to ensure that rural fire brigades receive written confirmation of the Commissioner’s approval after office bearer elections in compliance with section 81 of the Fire and Rescue Service Act 1990. |
REC191-0269 | 12 - EM agency and authority | that QFRS implement procedures to provide a clear grievance process which is available to rural fire brigade volunteers. |
REC191-0264 | 12 - EM agency and authority | that QFRS update its website to include the Rural Fire Service as part of its www.fire.qld.gov.au web presence. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
REC181-0171 | 17 - Assets and technology | The State, in conjunction with Emergency Management Australia and the Department of Defence, develop an agreement that allows Commonwealth aerial resources that are suitable for firefighting and support activities to be incorporated in preparedness plans and used on days of high fire risk. |
REC181-0170 | 17 - Assets and technology | The Country Fire Authority and the Department of Sustainability and Environment amend their policies on aerial preparedness and standby arrangements, their dispatch protocols and the management of aircraft in order to do the following: ■ require that at locations that attract the risk assessment or preparedness level A on code red days all personnel needed for air operations must be on standby by 10.00 am; ■ establish a system that enables the dispatch of aircraft to fires in high-risk areas without requiring a request from an Incident Controller or the State Duty Officer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3466 | 25 - Inquiry, audit, lessons management and after action review | A comprehensive review of the effectiveness of the increased prescribed burning target in meeting ecological and bushfire suppression needs should be conducted every three years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3255 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board remain a statutory authority. |
REC061-3411 | 12 - EM agency and authority | The Committee recommends that collocation shall occur unless it can be demonstrated to the satisfaction of the Minister that it is inappropriate. |
REC061-3254 | 12 - EM agency and authority | The Committee recommends that: |
REC061-3409 | 12 - EM agency and authority | The Committee recommends that one standard model of fire cover be developed for Victoria as a matter of urgency. |
REC061-3423 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3245 | 12 - EM agency and authority | The Committee recommends that collocation shall occur unless it can be demonstrated to the satisfaction of the Minister that it is inappropriate. |
REC061-3407 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board continue to exist. |
REC061-3421 | 12 - EM agency and authority | The Committee recommends that a new Board be appointed, consisting of nine members nominated by the Minister for Police and Emergency Services and including the Chief Executive Officer who shall not be Chairman. |
REC061-3243 | 12 - EM agency and authority | The Committee recommends that one standard model of fire cover be developed for Victoria as a matter of urgency. |
REC061-3258 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3420 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board remain a statutory authority. |
REC061-3241 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board continue to exist. |
REC061-3256 | 12 - EM agency and authority | The Committee recommends that a new Board be appointed, consisting of nine members nominated by the Minister for Police and Emergency Services and including the Chief Executive Officer who shall not be Chairman. |
REC061-3419 | 12 - EM agency and authority | The Committee recommends that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3949 | 17 - Assets and technology | It is recommended that the A.R.P. dams or earth tanks be kept filled during possible danger periods. |
REC016_3946 | 12 - EM agency and authority | It is recommended that it [The Fire Brigade] endeavour and be encouraged to add to its reserve of members, and that the reserves be fully and efficiently trained. Should fire on a wide, unbroken front attack the town, the brigade, if limited to its present numbers, could not be expected to be able to save the town. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3961 | 12 - EM agency and authority | It is recommended that each forestry officer should be stationed in one district for as long a time as is practicable consistent with justice to the officer. |
REC015_3958 | 12 - EM agency and authority | It is recommended that all members of the police force, members of brigades, municipal engineers and forest officers should be appointed as wardens. |
REC015_3957 | 12 - EM agency and authority | It is recommended that the functions of this authority should be primarily those of defining a general policy of prevention and suppression of bush fires and protection of life and property; of organizing and recruiting local brigades; of maintaining discipline of local brigades and over local fire authorities; and of acting independently, with or without such advice as it may care to take. |
REC015_3955 | 12 - EM agency and authority | The institution of a State Fire Authority is recommended. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |