Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
REC239-2741 | 16 - Training and behaviour | That the annual training calendar identify course, training location and the coordinating authority. |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2757 | 20 - Role of police | That the Queensland Police Service executive team reassesses its preparedness to collaborate with other agencies to deliver a whole of Government approach to delivering community safety. |
REC239-2689 | 20 - Role of police | That, where appropriate, the Commissioner of Police appoints appropriately trained and experienced public service officers to appropriate roles in the disaster management system to support District Disaster Coordinators in their vital roles. |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
REC239-2740 | 16 - Training and behaviour | That impediments to the publication of an annual training calendar of core skills be removed. |
REC239-2752 | 20 - Role of police | That the roll-out of the Queensland Police Service digital technology should take into consideration adopting and facilitating new processes including the police response to domestic violence. |
REC239-2684 | 38 - Agency/Department Reporting | The Chief Executive Officer Portfolio Business establishes a set of performance indicators to provide a transparent process for government to monitor its performance. |
REC239-2773 | 38 - Agency/Department Reporting | That should the Mobile Strategy in its current form be approved by government the CEO Portfolio Business and the Deputy Commissioner Operations: |
REC239-2729 | 16 - Training and behaviour | That the Queensland Fire and Rescue Service work to change the culture of entitlement so that firefighters recognise firefighting is only one of a range of skills they bring to their core role of emergency management. |
REC239-2750 | 20 - Role of police | That the Queensland Police Service: |
REC239-2674 | 38 - Agency/Department Reporting | That Queensland Corrective Service continues to develop its proposed recidivism index as a priority, including place and program based measures. |
REC239-2772 | 38 - Agency/Department Reporting | That the roll-out of the mobile service program business case mentioned earlier |
REC239-2726 | 20 - Role of police | That the Queensland Fire and Rescue Service enters into discussion with the Queensland Police Service regarding the possibility for the Queensland Police Service to assist with prosecutions that may arise out of fire safety matters. |
REC239-2748 | 20 - Role of police | That the Queensland Police Service considers adopting the broader use of ANPR in line with other Australian jurisdictions in consultation with the Privacy Commissioner. |
REC239-2673 | 38 - Agency/Department Reporting | That Queensland Corrective Service, in consultation with key partners in the criminal justice and social services sectors, develops specific performance indicators focused on efficiencies and customer/stakeholder outcomes across the criminal justice system. |
REC239-2771 | 38 - Agency/Department Reporting | That the Queensland Police Service Commissioner addresses the situation regarding statistical reporting. The Commissioner, in collaboration with the Chief Executive Officer Portfolio Business and the Queensland Fire and Rescue Service Commissioner should also examine the opportunity to acquire the services of a qualified and experienced Chief Information Officer or Chief Digital Officer in line with other Queensland and Australian government agencies. |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2747 | 20 - Role of police | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative automated number plate recognition models should form part of the design architecture. |
REC239-2671 | 16 - Training and behaviour | That all Queensland Corrective Service provision of training should be contestable. |
REC239-2767 | 38 - Agency/Department Reporting | Recommendation: That the CEO Portfolio Business collaborates with the two portfolio Commissioners to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
REC207-2881 | 17 - Assets and technology | Extend ICT governance arrangements to all applications and subject in-house development to rigorous approval processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3290 | 38 - Agency/Department Reporting | The successful installation of every barrier should be the subject of written verification within and between licensees and rig operators; and should be the subject of explicit reporting to the relevant regulator(s). |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3287 | 38 - Agency/Department Reporting | Licensees should be subject to an express obligation to inform regulators of problems which arise in the course of installing barriers, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0085 | 20 - Role of police | The Commissioner of Police, through a dedicated Assistant Commissioner (supported by a cohort of Assistant Commissioners to ensure adequate coverage), be assigned responsibility for overall control of each natural Disaster Management event in Queensland as the preferred arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
REC140-3574 | 38 - Agency/Department Reporting | Formation of a subcommittee of the DHHS Tasmanian Medical Retrieval Services Committee to identify risk exposures, system problems and potential solutions. The subcommittee should review data, problem cases, system issues and generate a risk register. Meetings should occur at least quarterly. |
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
REC140-3555 | 16 - Training and behaviour | The Tasmanian Ambulance Service Clinical Advisory Committee review helicopter and fixed wing Flight Paramedic training and consider extending the scope of practice to embrace the role of retrieval paramedic in the Doctor/Paramedic retrieval team setting. |