Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4214 | 1 - Land-use and building regs | We recommend that DELWP determines which elements of different regional planning approaches are the most effective and implements these across the state. |
REC321-4215 | 1 - Land-use and building regs | We recommend that DELWP develops more holistic bushfire-management planning that focuses on the best mix of risk treatments rather than planned burning alone. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
REC321-4211 | 1 - Land-use and building regs | We recommend that CFA (in consultation with FRV) improves planning on private land to ensure risk assessments and plans are conducted consistently across public and private land to address state-wide bushfire risk based on where and how they can most effectively reduce risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4197 | 36 - Volunteers | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department develop and resource an ongoing strategy to coordinate spontaneous volunteers that can be activated before, during or after emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1345 | 36 - Volunteers | That issues of animal welfare be given a higher practical priority in the planned burning process on the ground, including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0475 | 16 - Training and behaviour | the Department of Planning and Community Development review the volunteer register and examine additional options to support councils in volunteer management, including the development of tools and staffing support. |
REC199-0422 | 36 - Volunteers | the state establish a process for volunteer community member accreditation to allow volunteers to provide flood information to the control agency during a flood event. This process should establish a base competency standard and provide appropriate emergency management and Australasian Inter-service Incident Management System training to accredited community volunteers. |
REC199-0427 | 35 - Business and Industry in relation to industry | the state require dam owners and operators provide regular situational reports to the relevant control agency where dam issues may impact incident management. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0426 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform people situated downstream of water storages if the owners/operators become aware of an immediate threat arising from the dam to the safety of those people. The owner/operators should provide this information as soon as the owner/operators become aware of the threat. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0463 | 16 - Training and behaviour | the state: • ensure an appropriate regime of regular emergency management training and exercising is introduced. This must be ‘all hazards’ and multi-agency focused and include all relevant stakeholders • designate an accountable officer to hold ongoing responsibility for conducting such exercises; and • designate the Emergency Services Commissioner as holding ongoing responsibility for auditing and reviewing this training and exercising. |
REC199-0415 | 16 - Training and behaviour | the state ensure that all personnel who are likely to become involved in incident management teams for floods receive basic flood awareness training prior to such involvement. |
REC199-0425 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform the control agency and the Bureau of Meteorology about the management and operation of dams and weirs consistent with the flood warning requirements of the relevant river systems, including providing telemetry at sites as necessary. This may require the state proactively liaising with other states to ensure equivalent obligations are placed on interstate dam operators where the dam may impact Victorian communities. |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0462 | 16 - Training and behaviour | the state introduce a joint emergency management leadership training program that will deliver critical core competencies for all levels of management of major emergencies. Future appointments to senior operational emergency management positions should require successful accreditation at the appropriate level. |
REC199-0414 | 16 - Training and behaviour | the state ensure that all personnel who, because of their particular flood expertise, are likely to be potential participants in an Incident Control Centre are familiar with the requirements of the Australasian Inter-service Incident Management System structure |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0424 | 35 - Business and Industry in relation to industry | the state require dam owners and operators to review storage operating manuals to incorporate lessons from the 2010–11 floods and make this information publicly available. The manuals should include a clear policy on dam surcharging and pre-release. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0448 | 16 - Training and behaviour | the state ensure that sector wide familiarity and understanding of the various systems for incident management is developed and maintained. Primarily, this should be achieved through multi-agency emergency management training and exercising involving usage of the various agency incident management systems. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0233 | 16 - Training and behaviour | Further train Incident Controllers in the management of the Information Section and its roles. |
REC196-0232 | 16 - Training and behaviour | Increase the regularity of training for ICC Information Section staff and encourage pre-season drilling and trials in the use of OSOM and Emergency Alert particularly under critical capacity conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0329 | 21 - Role of Commonwealth Government | The Fire Services Commissioner requests the Federal Government to revise the National SEWS Guidelines |
REC195-0314 | 16 - Training and behaviour | The Fire Services enhance and increase joint training and exercise programs at all levels of command and control, including the State Control Centre. (These programs need to enable volunteer participation.) |
REC195-0326 | 16 - Training and behaviour | The Fire Services recognise the specialised role of Information Sections and enhance training and resources accordingly. |
REC195-0310 | 16 - Training and behaviour | The Fire Services Commissioner ensures that there is a comprehensive understanding of the State Command and Control Arrangements for Bushfires in Victoria across the Fire Services. |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0190 | 1 - Land-use and building regs | The Country Fire Authority amend its guidelines for assessing permit applications for dwellings, nondwellings and subdivisions in the Bushfire-prone Overlay in order to accommodate the amendments to the Wildfire Management Overlay that are implemented as a result of recommendation 39 and make the guidelines available to municipal councils and the public. The revised guidelines should do the following: ■ substantially restrict new developments and subdivisions in those areas of highest risk in the Bushfire-prone Overlay; ■ set out the CFA’s guidelines for assessing permit applications for dwellings, non-dwellings and subdivisions—including the minimum defendable space requirements for different risk levels; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ emphasise the need for enduring permit conditions—in particular, conditions for the creation and maintenance of minimum defendable space to be maintained for the life of the development. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0198 | 1 - Land-use and building regs | The Australian Building Codes Board do the following: ■ amend the performance requirements in the Building Code of Australia to ensure that they incorporate reducing the risk of ignition from ember attack; ■ work with Standards Australia to effect expeditious continuing review and development of AS 3959, Construction of Buildings in Bushfire-prone Areas, and other bushfire-related standards referred to in the Building Code of Australia; ■ negotiate with Standards Australia and SAI Global Ltd an arrangement for free online access to AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, the other Australian standards referred to in AS 3959-2009, and any other bushfire-related Australian standards referred to in the Building Code of Australia; ■ amend the Building Code of Australia to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ include in the Building Code of Australia bushfire construction provisions for non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0189 | 1 - Land-use and building regs | The State amend the Victoria Planning Provisions relating to bushfire to ensure that the provisions give priority to the protection of human life, adopt a clear objective of substantially restricting development in the areas of highest bushfire risk—giving due consideration to biodiversity conservation—and provide clear guidance for decision makers. The amendments should take account of the conclusions reached by the Commission and do the following: ■ outline the State’s objectives for managing bushfire risk through land-use planning in an amended state planning policy for bushfire, as set out in clause 15.07 of the Victoria Planning Provisions; ■ allow municipal councils to include a minimum lot size for use of land for a dwelling, both with and without a permit, in a schedule to each of the Rural Living Zone, Green Wedge Zone, Green Wedge A Zone, Rural Conservation Zone, Farming Zone and Rural Activity Zone; ■ amend clause 44.06 of the Victoria Planning Provisions to provide a comprehensive Bushfire-prone Overlay provision. |
REC181-0197 | 1 - Land-use and building regs | Standards Australia do the following: ■ amend the objective of AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, to ensure that it incorporates reducing the risk of ignition from ember attack; ■ review, and amend as appropriate, the testing methods prescribed in its standards for Tests on Elements of Construction for Buildings Exposed to Simulated Bushfire Attack (AS 1530.8.1 and AS 1530.8.2) to ensure that, so far as is possible, the methods provide a reliable predictor of the performance of construction elements under bushfire conditions. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0205 | 1 - Land-use and building regs | The State initiate the development of education and training options to improve understanding of bushfire risk management in the building and planning regimes by: ■ providing regular training and guidance material to planning and building practitioners; ■ providing regular training and guidance material to planning and building practitioners. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0188 | 1 - Land-use and building regs | The State implement a regional settlement policy that: ■ takes account of the management of bushfire risk, including that associated with small, undeveloped rural lots; ■ includes a process for responding to bushfire risk at the planning stage for new urban developments in regional cities, the process being similar to that used for new developments in Melbourne’s Urban Growth Zone. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0196 | 1 - Land-use and building regs | The State develop and implement a retreat and resettlement strategy for existing developments in areas of unacceptably high bushfire risk, including a scheme for non-compulsory acquisition by the State of land in these areas. |
REC181-0203 | 1 - Land-use and building regs | The State amend s. 32 of the Sale of Land Act 1962 to require that a vendor’s statement include whether the land is in a designated Bushfire-prone Area, a statement about the standard (if any) to which the dwelling was constructed, the bushfire attack level assessment at the time of construction (where relevant) and a current bushfire attack level assessment of the site of the dwelling. |
REC181-0175 | 16 - Training and behaviour | The Country Fire Authority and the Department of Sustainability and Environment require without exception that all relevant staff be trained in the need for Incident Controller approval to be obtained before a back-burn is lit. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0200 | 1 - Land-use and building regs | Standards Australia move expeditiously to develop a standard for bushfire sprinklers and sprayers. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0186 | 21 - Role of Commonwealth Government | The Commonwealth, states and territories continue to pursue the National Action Plan to Reduce Bushfire Arson in Australia, giving priority to producing a nationally consistent framework for data collection and evaluating current and proposed programs in order to identify and share best-practice approaches. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0191 | 1 - Land-use and building regs | The State: ■ amend the Victoria Planning Provisions to require that, when assessing a permit to remove native vegetation around an existing dwelling, the responsible authority and the Department of Sustainability and Environment, as referral authority, take into account fire hazard and give weight to fire protection purposes; ■ develop guidelines for determining the maximum level of native vegetation removal for bushfire risk mitigation, beyond which level the application would be rejected. |
REC181-0199 | 1 - Land-use and building regs | The State modify its adoption of the Building Code of Australia for the following purposes: ■ to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ to apply bushfire construction provisions to non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities; ■ other than in exceptional circumstances, to apply a minimum AS 3959-2009 construction level of BAL-12.5 to all new buildings and extensions in bushfire-prone areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3493 | 35 - Business and Industry in relation to industry | The electricity distribution businesses and retailers work with the Department of Human Services and hospitals to review the registration, notification and removal process for those on life support machinery. |
REC156-3502 | 35 - Business and Industry in relation to industry | The Emergency Services Telecommunications Authority in partnership with Telstra should develop testing regimes that will ensure the integrity of the call queue arrangements and correct configuration of the Recorded Voice Announcements. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3496 | 21 - Role of Commonwealth Government | The Bureau of Meteorology contact list for severe weather warning be strategically managed in consultation with Emergency Service Organisations, to identify critical contacts. The Bureau of Meteorology must ensure the detail for these critical contacts remains up to date. |
REC156-3495 | 16 - Training and behaviour | The Department of Primary Industries should work through the appropriate Ministerial Councils to seek alignment of competency standards for line workers across jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3893 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures that stakeholders (and especially local councils) are fully consulted before and during the development of drainage strategies and plans. These plans should consider councils’ drainage systems. |
REC125-3892 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures stakeholder expectations are fully considered when setting flood risk reduction targets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
REC124-3890 | 16 - Training and behaviour | Update education and training programs relating to prescribed burning to reflect revised organisational priorities including year round (365 day) fire management program: |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2260 | 16 - Training and behaviour | That VICSES, with the support of the CFA, includes basic fire safety training as one of the competencies for the VICSES Volunteers. |
REC104-2328 | 36 - Volunteers | That CFA, VICSES and other volunteer-based emergency service organisations develop proposals in support of the strategies for sustainable volunteerism, and that the State Government advocate these initiatives to the Federal Government. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2259 | 16 - Training and behaviour | That the MFESB continue to give priority to appropriate bushfire training for its firefighters. |
REC104-2327 | 16 - Training and behaviour | That all fire agencies include a formal mentoring scheme as part of their workforce development programs; and that consideration be given to the use of suitably competent and experienced individuals (such as retired staff), to act as coaches or mentors with inexperienced Incident Controllers. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2221 | 35 - Business and Industry in relation to industry | That CFA and the Plantation Industry jointly develop and agree on Fire Prevention Guidelines for Plantations by June 2004, to be then promoted and distributed by the Industry. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2264 | 16 - Training and behaviour | That CFA and DSE provide media training to all Level 2 and Level 3 Incident Controllers. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2250 | 41 - Emergency Management exercises | That DSE and CFA work in cooperation with the Municipal Emergency Response Coordinators to develop and conduct joint exercises that practise the skills and test procedures for operations of the Municipal Emergency Coordination Centre, Municipal Recovery Centre and Incident Control Centres. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2263 | 16 - Training and behaviour | That the person appointed by DSE or CFA as Incident Controller for any incident should have formal qualifications and accreditation in the Incident Control System, be fully aware of the Victorian emergency management arrangements and have access to local fire prevention and response planning, including the Municipal Fire Management Plan |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2249 | 16 - Training and behaviour | That DSE and CFA ensure that: |
REC104-2294 | 16 - Training and behaviour | That training and competency programs for Incident Controllers should include aircraft firefighting capability training. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2335 | 41 - Emergency Management exercises | That the fire agencies develop a program to significantly increase the amount of joint training and exercises undertaken. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2235 | 16 - Training and behaviour | That DSE and CFA review selection and training programs for Incident Controllers and Incident Management Team members to ensure that they include all necessary competencies in recognition that technical skills are only one component of the required attributes. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
REC016_3948 | 16 - Training and behaviour | It is recommended that workers and volunteers generally be instructed in accordance with a pre-arranged plan, as to what they should do in future times of emergency. Since the fighting of fires is for the greater part a matter of voluntary action, some estimate could perhaps be made, after investigation, of the numbers of men in each department who would be willing to volunteer. It would be necessary that each department should become a component part of an over-riding scheme and that it and its members should be fully instructed in the matter of whistle or siren warnings, places of assembly, reception of messages from the director of proceedings, use of equipment, and the various details which would necessarily be parts of an effective scheme. The training need not be onerous. If given once or twice at the beginning of possible danger periods, it would make for some degree of order and efficiency instead of a probable state of confusion. |
REC016_3945 | 16 - Training and behaviour | It is recommended that a large proportion of men employed in and about the open-cut be systematically trained in the use of equipment and in the tactical disposition of it. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3962 | 35 - Business and Industry in relation to industry | It is recommended that the matter be submitted to experts, of which there are many in the Public Service; and that such experts determine the best manner of construction. |