Rec-ID | Code | Recommendation |
---|---|---|
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4187 | 33 - Relief and recovery | Recovery governance: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils, relevant recovery organisations and communities to develop clear roles and responsibilities for: |
REC319-4195 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, leads the development of a comprehensive, person-centred, trauma-informed recovery financial assistance system that establishes: |
REC319-4188 | 12 - EM agency and authority | Recovery governance: The Inspector-General for Emergency Management recommends that the Victorian Government establish a permanent and comprehensive entity dedicated to recovery management with the authority, capability, capacity and resourcing to coordinate the planning and delivery of recovery functions for all emergencies. |
REC319-4196 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, works with the emergency management sector to develop a recovery funding model that enables: |
REC319-4189 | 33 - Relief and recovery | Donated good: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department: |
REC319-4198 | 33 - Relief and recovery | Relief and recovery capability: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions works with the entity referred to in Recommendation 13, or otherwise responsible government department and/or Municipal Association of Victoria, councils and local relief and recovery organisations to provide centralised capability development opportunities to increase local capability and capacity to plan and deliver on their relief and recovery responsibilities: |
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
REC319-4200 | 33 - Relief and recovery | Foundations of emergency management: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in consultation with the emergency management sector – establish policies and platforms to improve operational and personal information sharing between relief and recovery organisations. These policies and platforms should enable: |
REC319-4191 | 12 - EM agency and authority | Relief governance: The Inspector General for Emergency Management recommends that Emergency Management Victoria lead the development of relief arrangements to achieve greater clarity of roles, reporting and accountability in relief across state, regional and incident tiers. These arrangements should: |
REC319-4192 | 12 - EM agency and authority | Relief governance: The Inspector-General for Emergency Management recommends that the Emergency Management Commissioner strengthen the State Emergency Management Plan and supporting operational arrangements in accordance with his legislative obligations to ensure the roles and responsibilities of the State Emergency Relief Coordinator and the State Relief and Recovery Team are clear. These documents should enable: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
REC318-4173 | 32 - Doctrine, standards, and reform | The Inspector-General for Emergency Management recommends that in conjunction with Inquiry Recommendation 2, the State establish or assign responsibility to a single body or entity to lead and coordinate the implementation of evidence-based fuel management policy, practice and assurance and reporting on activities on both public and private land in Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4035 | 32 - Doctrine, standards, and reform | Review, refine and implement the joint ESA/EPSDD Arrangement for Fire Management in the ACT with the previous recommendation in mind. |
REC316-4015 | 12 - EM agency and authority | The working group should report to SEMSOG on progress. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4025 | 32 - Doctrine, standards, and reform | The Emergency Plan and ECC Ops Plan be amended to better articulate the delivery of emergency management vs the delivery of the emergency plan. The Plan should facilitate principles for emergency management and clear role delineations whilst allowing flexibility in how the mechanisms are structured. |
REC316-4031 | 12 - EM agency and authority | The ESA hold bi-lateral executive level meetings with the utility providers on a regular basis in consultation with other relevant Government stakeholders. |
REC316-4044 | 11 - Evacuation and shelters | A Relocation and Evacuation working group be established from stakeholder organisations to consider and develop an Evacuation and Relocations Sub- Plan. The Sub-Plan should consider the lessons learned this year and address principles, lead agency, WHoG coordination, trigger points etc. This could be the same working group formed for reviewing the Emergencies Act, Plan and sub-plans. |
REC316-4024 | 32 - Doctrine, standards, and reform | The Government consider amendments to the Emergencies Act to include provision for a Deputy ESA Commissioner. |
REC316-4052 | 32 - Doctrine, standards, and reform | The ACT Emergencies Act 2004 be amended to clarify that the powers of the EC encompass the power to direct agencies and directorates to share personal information for the preservation of life and protection of Canberrans. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4039 | 12 - EM agency and authority | Establish a Communications Working Group (CWG) with representatives from across key Directorates (CMTEDD, ESA, ACT Policing, Health, CHS, EPSDD for example) to review the CCIP and to further identify how the CCIP can be best implemented and utilised. The CWG should report its progress though SEMSOG and coordinate with other WG’s. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4022 | 12 - EM agency and authority | That when determining their Management Executive, at a minimum the EC should consider appointing Director-General JACS and the PIC as standing members. |
REC316-4051 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended so that the powers, including delegations, available to an EC be granted on their appointment and remain in place under the same section of the Act for the duration of their appointment rather than being drawn from different sections of the Act that are dependent on the existing alert state for the specified event. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4021 | 32 - Doctrine, standards, and reform | The Emergency Plan be amended to better reflect the intent of the Emergencies Act in the establishment of a Management Executive, separate to SEMSOG, on the appointment of an EC. It should describe the role of SEMSOG and the Management Executive as distinct in the emergency management architecture. |
REC316-4050 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the provision for a Deputy Emergency Controller to be appointed, independent of the initial appointment of an EC. The powers and functions of this appointment to be contingent on the absence of the EC. |
REC316-4027 | 12 - EM agency and authority | All organisations who have a role in the ECC should review their existing arrangements to ensure there is a sufficient cohort of staff to maintain a presence in the ECC at a level and with an imprimatur sufficient to make decisions and allocate resources and have access to senior executive levels if needed. |
REC316-4036 | 12 - EM agency and authority | Government give consideration to investment in professional specialities such as fire behaviour analysts, airbase managers, aerial firefighting technical specialists etc for the RFS. |
REC316-4016 | 12 - EM agency and authority | That the Emergency Plan be amended to include considerations for declaring a State of Alert or Emergency (and also wind back from these) and guidance as to what actions and decisions at a minimum should be taken as a consequence of such a declaration. |
REC316-4049 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the appointment of the EC to be made for a discretionary time period of up to 28 days with the requirement for a legislated review of the appointment to be removed. Alternatively, a period of review should fall within the Chief Ministers discretion for up to seven (7) days following appointment. |
REC316-4026 | 12 - EM agency and authority | The role, level, requirements and expectations of an ECC LO be clarified in the Emergency Plan and ECC Ops Sub-plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2406 | 12 - EM agency and authority | Retain the Regional Bushfires Committees as regional planning and consultative bodies tasked with monitoring, reviewing and making recommendations on fire management in a Fire Control Region. |
REC304-2412 | 12 - EM agency and authority | Maintain independence of volunteer brigades as community-based organisations and clarify the status and role of volunteers within the chain of command. |
REC304-2417 | 32 - Doctrine, standards, and reform | Amend the Act title to ‘Bushfires Management Act’. |
REC304-2405 | 24 - Govt responsibility | Retain the Bushfires Council as a Ministerial advisory body. |
REC304-2411 | 12 - EM agency and authority | Create new seasonal paid positions to coordinate and support groups of volunteer brigades. |
REC304-2415 | 32 - Doctrine, standards, and reform | Define formal bushfire management regimes for areas with different bushfire management requirements and define bushfire management responsibilities in those areas. One category will provide for areas that warrant provision of a wildfire response capacity, another will allow for the declaration of temporary fire management arrangements for the duration of identified high-risk circumstances. |
REC304-2410 | 12 - EM agency and authority | Authorise Bushfires NT to establish volunteer bushfire brigades and to give authority to volunteer firefighters to take part in fire suppression and mitigation operations. |
REC304-2414 | 12 - EM agency and authority | Clarify and streamline the allocation of powers to Bushfires NT staff and volunteers involved in bushfire management operations, using a system of delegation through a chain of command similar to the arrangements described in the NT Fire and Emergency Act. |
REC304-2421 | 32 - Doctrine, standards, and reform | Include a detailed description of the role, responsibility and accountability of |
REC304-2409 | 32 - Doctrine, standards, and reform | Formalise and clearly define the powers and duties of Bushfires NT personnel, including volunteers, thereby clarifying Bushfires NT’s role in bushfire management in the Northern Territory. |
REC304-2414 | 12 - EM agency and authority | Clarify and streamline the allocation of powers to Bushfires NT staff and volunteers involved in bushfire management operations, using a system of delegation through a chain of command similar to the arrangements described in the NT Fire and Emergency Act. |
REC304-2420 | 32 - Doctrine, standards, and reform | Enshrine the broader fire management principles, including coordination, strategic planning, mitigation, monitoring and control within the Act. |
REC304-2408 | 32 - Doctrine, standards, and reform | Introduce clear Terms of Reference for the Bushfires Council and Regional Bushfires Committees, and introduce a requirement for the Minister to consider advice and recommendations from the Council. |
REC304-2413 | 12 - EM agency and authority | Authorise the Director of Bushfires NT to intervene in volunteer brigade affairs where necessary to maintain an effective fire management capacity in a brigade area. |
REC304-2418 | 32 - Doctrine, standards, and reform | Amend the object to provide for ‘The mitigation, management, and suppression of bushfires’. Definitions of these terms should be included in the Act, and should include clarification that bushfire suppression can include emergency response activities in certain circumstances |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC275-1173 | 12 - EM agency and authority | IGEM recommends that fire agencies review their documentation systems and information recording processes to ensure that all operational activities are captured, and to maintain the accuracy and relevance of all developed products. This includes the need to ensure that all significant points of reference entered into mapping products are geo-coded to facilitate accurate transfer of information from one mapping product to another. |
REC275-1172 | 12 - EM agency and authority | IGEM recommends that fire agencies review their resource allocation recording mechanisms and systems to ensure that an accurate reflection of resources deployed to an incident at any given time can be ascertained |
REC275-1174 | 32 - Doctrine, standards, and reform | IGEM recommends that fire agencies consider an earlier classification of Level 3 incident for fires that present significant complexity such as was evident in the Wye River – Jamieson Track event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1079 | 32 - Doctrine, standards, and reform | The State review and revise the Bushfre Smoke Protocol and the PM Health Protection Protocol, to: 2.5 • ensure both protocols are consistent with each other; and • ensure both protocols include assessment methods and trigger points for specifc responses. |
REC264-1078 | 32 - Doctrine, standards, and reform | The State review and revise the community carbon monoxide response protocol and the firefghter carbon monoxide response protocol, to: |
REC264-1077 | 32 - Doctrine, standards, and reform | The State take the lead in advocating for a national compliance standard for PM |
REC264-1088 | 32 - Doctrine, standards, and reform | GDF Suez adopt and apply the firefghter carbon monoxide response protocol. |
REC264-1075 | 32 - Doctrine, standards, and reform | The State: • bring forward the commencement date of s.16 of the Mineral Resources (Sustainable Development) Amendment Act 2014 (Vic), to facilitate the requirement that approved work plans specifcally address fre prevention, mitigation and suppression; and • acquire the expertise necessary to monitor and enforce compliance with fre risk measures adopted by the Victorian coal mining industry under both the mine licensing and occupational health and safety regimes. |
REC264-1084 | 32 - Doctrine, standards, and reform | GDF Suez revise its Emergency Response Plan, to: • require an increased state of readiness on days of Total Fire Ban; • require pre-establishment of an Emergency Command Centre; • require pre-positioning of an accredited Incident Controller as Emergency Commander; and • require any persons nominated as Emergency Commander to have incident controller accreditation and profciency in the use of the Australasian Inter-service Incident Management System. |
REC264-1074 | 32 - Doctrine, standards, and reform | The State enact legislation, to: • require Integrated Fire Management Planning; and • authorise the Emergency Management Commissioner to develop and implement regional and municipal fire management plans. |
REC264-1080 | 32 - Doctrine, standards, and reform | The State develop and widely disseminate an integrated State Smoke Guide, to: • incorporate the proposed State Smoke Plan for the management of public health impacts from large scale, extended smoke events; • include updated Bushfre Smoke, carbon monoxide and PM protocols; and 2.5 • provide practical advice and support materials to employers, communities and individuals on how to minimise the harmful effects of smoke. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1613 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should continue to work with National Land managers and develop a National Land bushfire management framework to address bushfire risks on National Land. |
REC228-1627 | 12 - EM agency and authority | The Emergency Services Agency (ACT Rural Fire Service headquarters) should implement a system to provide assurance to the Chief Officer of the ACT Rural Fire Service that personnel and equipment readiness meets requirements. |
REC228-1606 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should comply with the Emergencies Act 2004 requirements for the Strategic Bushfire Management Plan by including in this Plan an explicit statement of all resources needed to meet the objectives of the Plan. |
REC228-1612 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should develop a strategy for monitoring the development and implementation of all Government land managers’ operational plans. |
REC228-1626 | 12 - EM agency and authority | The Emergency Services Agency and the Territory and Municipal Services Directorate should clarify the timing of the requirement for meeting firefighter fitness requirements, as set out in ACT Rural Fire Service operating procedures and the Territory and Municipal Directorate’s Enterprise Agreement, and give priority to meeting that requirement. |
REC228-1605 | 24 - Govt responsibility | The Justice and Community Safety Directorate should continue to review its strategic and accountability indicators and the Territory and Municipal Services Directorate should commence a review of its strategic and accountability indicators. The directorates should consult to develop complementary measures which better assess their bushfire management activities. |
REC228-1611 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should specify preparation and approval requirements for bushfire operational plans, particularly those for lands in the Bushfire Abatement Zone. |
REC228-1624 | 12 - EM agency and authority | The Emergency Services Agency should: |
REC228-1610 | 24 - Govt responsibility | The Emergency Services Agency should annually review fire management zones and the Territory and Municipal Services Directorate should subsequently update the Regional Fire Management Plans. |
REC228-1621 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should improve its management of the Community Fire Unit Program by: |
REC228-1608 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should review the operations of the Strategic Bushfire Management Plan Implementation Working Group to determine if it is the most appropriate mechanism for ‘monitoring the scope and effectiveness’ of the Strategic Bushfire Management Plan. If it is retained, ways to improve its effectiveness should be identified and implemented. |
REC228-1618 | 24 - Govt responsibility | The Emergency Services Agency, the Environment and Sustainable Development Directorate and the Territory and Municipal Services Directorate should strengthen across-Government delivery of major projects in the Strategic Bushfire Management Plan and Regional Fire Management Plans by collectively: |
REC228-1607 | 32 - Doctrine, standards, and reform | The Justice and Community Safety Directorate, in managing future amendments to the Emergencies Act 2004, should propose amendments which require the Emergency Services Agency to maintain information on privately-owned assets of public interest that are vulnerable to bushfire without the need to include this information in the Strategic Bushfire Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1663 | 12 - EM agency and authority | Review Bushfires CRC initiatives as the basis for the implementation of a recruitment drive in the Territory. |
REC209-1678 | 32 - Doctrine, standards, and reform | That the Bushfires Act and Regulations be reviewed and modernised after the implementation of the recommendations of this review. |
REC209-1660 | 24 - Govt responsibility | Better alignment between divisions within DNRETAS be achieved through the development of an integrated strategy that addresses the combined objectives of weed management, land management, carbon farming and biodiversity management using fire across the Territory. |
REC209-1670 | 32 - Doctrine, standards, and reform | Bushfires NT create a bushfire management strategy and emergency response procedures framework including the criteria that define the escalation and response requirements for all incidents up to and including the establishment of an EOC, applicable for all regions across the Territory. |
REC209-1659 | 32 - Doctrine, standards, and reform | Regional Fire Management Plans be reviewed for all regions prior to the start of each fire season. |
REC209-1668 | 12 - EM agency and authority | Maintain DNRETAS as the lead agency for all aspects of Bushfires NT’s role and maintain Bushfires NT as the lead organisation for both fire prevention and fire fighting operations in its specified districts and zones. |
REC209-1654 | 24 - Govt responsibility | That the Director Bushfires NT NOT be appointed as a member of Council. |
REC209-1665 | 12 - EM agency and authority | Develop a long term forecast of volunteer requirements, by region, and then review the adequacy of volunteer operational grants, equipment and facilities to meet this forecast. |
REC209-1649 | 12 - EM agency and authority | Regular rotation of staff across other regions of the Territory to increase knowledge, skills and expertise that can be called upon to increase response effectiveness. |
REC209-1664 | 12 - EM agency and authority | Review Bushfires NT brigade boundaries to increase the catchment for possible volunteers and maximise the availability and allocation of equipment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0235 | 12 - EM agency and authority | Consider the ‘secondment’ of staff into Information Section roles during the fire season along the lines of the seasonal Project Fire Fighters model |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0320 | 12 - EM agency and authority | The Fire Services continue working towards a common and integrated information and communication platform to improve interoperability at state, regional and local levels. |
REC195-0313 | 32 - Doctrine, standards, and reform | The Fire Services expedite programmed work on joint operational command and control, including standards, procedures and training |
REC195-0312 | 32 - Doctrine, standards, and reform | The Fire Services Commissioner ensures that joint fireground command and control, integration and escalation procedures are developed, particularly for ‘fastrunning’ fires |
REC195-0311 | 32 - Doctrine, standards, and reform | The Fire Services ensure that agency specific operational procedures fully align with the arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0163 | 32 - Doctrine, standards, and reform | The State consider amending the Emergency Management Act 1986 to introduce a graded scale of emergency declarations short of a state of disaster. |
REC181-0171 | 17 - Assets and technology | The State, in conjunction with Emergency Management Australia and the Department of Defence, develop an agreement that allows Commonwealth aerial resources that are suitable for firefighting and support activities to be incorporated in preparedness plans and used on days of high fire risk. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0162 | 32 - Doctrine, standards, and reform | The State consider either amending the Emergency Management Act 1986 or adopting a standing practice to require the Minister for Police and Emergency Services or the Chief Commissioner of Police to consult the Premier about the possibility of declaring a state of disaster for all of or any part of Victoria whenever the Minister or the Chief Commissioner of Police becomes aware of circumstances that make it a reasonable possibility that the criteria for making such a declaration will be satisfied. |
REC181-0213 | 32 - Doctrine, standards, and reform | The State enact legislation designed to achieve two specific ends: ■ appoint a Fire Commissioner as an independent statutory officer responsible to the Minister for Police and Emergency Services and as the senior operational firefighter in Victoria; ■ make the Chief Fire Officer of the Department of Sustainability and Environment a statutory appointment. The Fire Commissioner should have responsibility for the following: ■ promoting and directing reform aimed at increasing the operational capability, interoperability and resilience of Victoria’s fire services; ■ developing and building operational capacity to prepare for the days of highest bushfire risk and exercising control over level 3 fires as the permanent State Controller; ■ providing to government periodic advice on the metropolitan fire district boundary on the basis of triggers, frequency and criteria approved by government; ■ representing Victorian interests on operational matters in national committees. |
REC181-0170 | 17 - Assets and technology | The Country Fire Authority and the Department of Sustainability and Environment amend their policies on aerial preparedness and standby arrangements, their dispatch protocols and the management of aircraft in order to do the following: ■ require that at locations that attract the risk assessment or preparedness level A on code red days all personnel needed for air operations must be on standby by 10.00 am; ■ establish a system that enables the dispatch of aircraft to fires in high-risk areas without requiring a request from an Incident Controller or the State Duty Officer. |
REC181-0161 | 32 - Doctrine, standards, and reform | The State consider amending the Emergency Management Act 1986 and the Emergency Management Manual Victoria in order to achieve the following: ■ remove the title of Coordinator in Chief of Emergency Management from the Minister for Police and Emergency Services; ■ clarify the function and powers of the Minister; ■ designate the Chief Commissioner of Police as Coordinator in Chief of Emergency Management, who would have primary responsibility for keeping the Minister informed during an emergency. |
REC181-0164 | 32 - Doctrine, standards, and reform | The Victorian fire agencies amend the AIIMS framework before the 2010–11 fire season in order to do the following: ■ designate the Information Unit as a separate section reporting directly to the Incident Controller and require that the Information Unit contain a dedicated Public Information Officer whenever a full incident management team is required; ■ specify a set of functions in relation to which the Deputy Incident Controller for a level 3 incident will have oversight, which may be adjustable for a particular incident by agreement between the Incident Controller and the Deputy Incident Controller; ■ ensure that an individual with local knowledge is incorporated in an incident management team |
REC181-0209 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment amend the Code of Practice for Fire Management on Public Land in order to achieve the following: ■ provide a clear statement of objectives, expressed as measurable outcomes; ■ include an explicit risk-analysis model for more objective and transparent resolution of competing objectives, where human life is the highest priority; ■ specify the characteristics of fire management zones—including burn size, percentage area burnt within the prescribed burn, and residual fuel loading; ■ adopt the use of the term ‘bushfire’ rather than ‘wildfire’. |
REC181-0158 | 32 - Doctrine, standards, and reform | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require the following: ■ that at locations that attract preparedness levels A or B there be a full incident management team under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of code red fire danger and a core incident management team (eight personnel) under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of extreme fire danger; ■ that at locations that attract preparedness levels A or B there be a full incident management team under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of code red fire danger and a core incident management team (eight personnel) under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of extreme fire danger. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3473 | 24 - Govt responsibility | That the Victorian Government expedite the implementation of its 2006 election commitment to provide four wheel drive clubs with access to management vehicle only tracks. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3482 | 32 - Doctrine, standards, and reform | That the Victorian Government, and responsible agencies, expedite the implementation of the Integrated Fire Management Planning framework. |
REC155-3479 | 32 - Doctrine, standards, and reform | That a process of year round community engagement in the preparation of Fire Operations Plans be established. In addition a record of year round community engagement, as contained in the Gippsland Fire Operations Plan, should be a requirement of all Fire Operations Plans. |
REC155-3474 | 24 - Govt responsibility | That the Victorian Government consider all available means, consistent with conservation values, for substantially increasing the access of apiarists to the public land estate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3592 | 32 - Doctrine, standards, and reform | Clarifying protocols for activating VBIL beyond normal working hours and for 24 hour activations |
REC132-3591 | 32 - Doctrine, standards, and reform | Joint development of templates for provision of core incident information by regional Incident Management Teams to CFA and DSE emergency coordination centres as basis for updates to the VBIL and other authorised information recipients |
REC132-3596 | 12 - EM agency and authority | CSC investigating possible change of location when contract for current location at Wendouree expires in 2008. |
REC132-3595 | 32 - Doctrine, standards, and reform | Development of framework document investigating future direction of VBIL including its role during incidents and its role in the transition from bushfire preparation to incident to bushfire recovery phases |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1964 | 32 - Doctrine, standards, and reform | That all firefighting agencies adopt a policy and practice that all fires in remote areas of the ACT be responded to as quickly as possible, with vigorous and sustained efforts made to suppress the fires and not leave them unattended – especially at night – unless there are compelling reasons relating to firefighter safety or lack of resources |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1946 | 32 - Doctrine, standards, and reform | That the ACT Government consider amending the Coroners Act 1997 to include what were ss. 56(1)(d) and 56(2)(c) of the 1956 Coroners Act |
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1963 | 12 - EM agency and authority | That priority be given to ensuring that the ACT has an adequate resource of remote area firefighting teams consisting of personnel with high levels of fitness and training in remote fire suppression |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-1945 | 32 - Doctrine, standards, and reform | That s. 47 of the ACT Coroners Act 1997 be expanded to explicitly state that an inquest and the inquiry are not adversarial in nature and are solely inquisitorial, with a view to establishing the truth |
REC126-1978 | 32 - Doctrine, standards, and reform | That it be a matter of policy and practice that the relevant land management agency is responsible for the initial response to any fire or fires on the land under its care or management – within the overall operational response of the ACT Rural Fire Service |
REC126-1995 | 12 - EM agency and authority | That the Emergency Services Agency staff the Media Unit within its planning Section with profesisonal, experienced information officers skilled in dissemination of information and media management and liaison |
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
REC126-1966 | 32 - Doctrine, standards, and reform | That the Emergency Services Agency investigate and implement arrangements that will provide the capacity to use fire retardant in remote areas |
REC126-1944 | 32 - Doctrine, standards, and reform | That s. 59 of the ACT Coroners ACT 1997 be amended by deleting the words ‘by instrument’ in s. 59(1) and by deleting the words ‘by his or her instrument of appointment’ in s. 59(2)(b) |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-1989 | 32 - Doctrine, standards, and reform | That formal protocols be developed and agreed with NSW authorities, so that a concerted effort that combines the resources of both NSW and the ACT can be brought to bear in the future - without impediment caused by lines on a map that make the ACT an island within the state of NSW |
REC126-1962 | 32 - Doctrine, standards, and reform | That version 2 of the Strategic Bushfire Management Plan be completed and introduced without delay |
REC126-1965 | 32 - Doctrine, standards, and reform | That helicopters be used wherever possible to facilitate the rapid deployment of remote area firefighting crews |
REC126-1943 | 32 - Doctrine, standards, and reform | That the ACT’s Director of Public Prosecutions Act 1990 be amended by repealing s. 6(d) of the Act |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1949 | 12 - EM agency and authority | That the Emergency Services Agency be relocated into accommodation that is purpose-built and more sited to the agency’s operations than the current facility at Curtin |
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1964 | 32 - Doctrine, standards, and reform | That remote area firefighting resources be deployed to a fire in a remote area as a matter of priority and in preference to the deployment of large tankers |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3886 | 32 - Doctrine, standards, and reform | Clarify, strengthen and document roles, responsibilities and accountabilities of DSE and its partner organisations in the prescribed burning program: |
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
REC124-3887 | 32 - Doctrine, standards, and reform | Give priority to the establishment of risk management processes across all stages of prescribed burning within the Department’s broader risk management strategy: |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2252 | 32 - Doctrine, standards, and reform | That existing DSE and CFA regional co-ordination arrangements be reviewed and any changes, such as the continued use of Integrated Multi-Agency Co-ordination Centres, be reflected in the Victorian emergency management arrangements. |
REC104-2309 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to include a provision that, on the recommendation of the Minister for Police and Emergency Services as Co-ordinator-in-Chief of Emergency Management, or of another Minister, the Premier establish a Ministerial Task Force to oversee recovery in situations of extreme natural disaster or other emergency events. |
REC104-2227 | 32 - Doctrine, standards, and reform | That the Municipal Fire Management Plan amendment includes appropriate provisions for the audit of the plans including: |
REC104-2257 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to require the development of agreements that describe joint operational arrangements between emergency response agencies. |
REC104-2314 | 33 - Relief and recovery | That DHS, in conjunction with Local Government, Government departments and the nongovernment sector, modify recovery planning at all levels to include a case management approach supported by an appropriate information system to be activated at the time of an emergency. |
REC104-2236 | 32 - Doctrine, standards, and reform | That the Statewide Fire Control Priorities: |
REC104-2286 | 17 - Assets and technology | That CFA, having regard to terrain, continue to review the mix of firefighting appliances currently in service. In particular, consideration should be given to the number and distribution of smaller ‘slip-on’ type equipment. |
REC104-2326 | 12 - EM agency and authority | That, as a matter of urgency, CFA and DSE: |
REC104-2199 | 32 - Doctrine, standards, and reform | That evidence of the rekindling or otherwise of spring prescribed burns in forests be assembled and a model constructed and tested to see whether or not some days in spring could be used for prescribed burning in certain circumstances and places, especially in Zone 1. |
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2307 | 33 - Relief and recovery | That the Victorian Government recommend to the Commonwealth Government that it reviews eligibility for those without employment who may or may not be engaged in an emergency response, and are unable to access the appropriate infrastructure to register for financial assistance. |
REC104-2226 | 32 - Doctrine, standards, and reform | That the new Municipal Fire Management Plan is informed by the policy directions of the subcommittee of the Victoria Emergency Management Council. |
REC104-2256 | 24 - Govt responsibility | That the State Emergency Operations Centre develop and maintain strong and close links with the State Emergency Response Coordination Centre, if collocation is not possible. |
REC104-2313 | 33 - Relief and recovery | That Government review the emergency relief and financial assistance policy, and develop and communicate a predictable, consistent and equitable policy designed to assist the community to recover from emergencies, including natural disasters. |
REC104-2234 | 12 - EM agency and authority | That the fire agencies develop contingency plans in relation to access to water for firefighting, including where appropriate, the use of static, large volume water tanks. |
REC104-2285 | 32 - Doctrine, standards, and reform | That, as a matter of urgency and in consultation with stakeholders, CFA and DSE develop and communicate clear guidelines on how and when privately owned firefighting equipment should be integrated into the fire response. |
REC104-2324 | 32 - Doctrine, standards, and reform | That this group reports to the Minister for Police and Emergency Services on proposed legislative amendments to the Emergency Management Act 1986, the Country Fire Authority Act 1958 and any associated legislation by June 2004. |
REC104-2198 | 32 - Doctrine, standards, and reform | That an explicit formulation of the interactions between terrain, fuel, ignition pattern, time of day and weather be created to better define those days suited to prescribed burning. |
REC104-2248 | 12 - EM agency and authority | That Incident Control Centres and Municipal Emergency Co-ordination Centres be collocated, wherever practicable. |
REC104-2306 | 33 - Relief and recovery | That VicRoads and Municipal Councils review procedures and processes to ensure that the identification and delivery of remedial works on State and Council roads following emergency events are as efficient as possible. |
REC104-2334 | 12 - EM agency and authority | That the Fire Management Branch of DSE be prescribed as an ‘emergency service agency’ for the purposes of s21C (1)(a) of the Emergency Management Act 1986. |
REC104-2225 | 24 - Govt responsibility | That the Victoria Emergency Management Council establish a sub-committee by June 2004 to ensure an all-agency and appropriate industries’ policy framework is developed and agreed in respect to the planning for fire prevention, mitigation and suppression. |
REC104-2255 | 24 - Govt responsibility | That the options of collocating the State Emergency Response Coordination Centre with the new State Emergency Operations Centre |
REC104-2312 | 33 - Relief and recovery | That all agencies engaged in recovery participate in community briefings prior to and during emergency events, to ensure recovery issues are reinforced and communities are informed of the processes established to assist individuals – including matters that are not the responsibility of Victoria, such as Centrelink payments. |
REC104-2232 | 24 - Govt responsibility | That Government in the development of its statewide water policy includes appropriate consideration of access to water for firefighting. |
REC104-2278 | 32 - Doctrine, standards, and reform | That DSE and CFA review the standards and protocols for documentation, including mapping, provided to fire line managers as part of their briefing notes, to ensure these are concise and appropriate. |
REC104-2321 | 24 - Govt responsibility | That Government confirms that the Model of Fire Cover/Fire Safety Victoria strategy should be a seamless model for the whole of the State and include both private and public land. |
REC104-2196 | 32 - Doctrine, standards, and reform | That, as a result of this monitoring, weather conditions for the safe conduct of burning in such operations should be defined. |
REC104-2247 | 24 - Govt responsibility | That an appropriately resourced, national aerial firefighting strategy is urgently required, and that the Victorian Government make representations to the Commonwealth to support the Australasian Fire Authorities Council recommendations |
REC104-2305 | 33 - Relief and recovery | That DPI actively promote as widely as possible within the community, the agricultural recovery service available during emergencies to ensure that all farmers are aware of the services provided. |
REC104-2331 | 24 - Govt responsibility | That a State Emergency Operations Centre be established to replace the existing separate fire agency centres. This could, if necessary, be initially confined to being a State Fire Operations Centre as recommended in Chapter 18, Part D. |
REC104-2224 | 32 - Doctrine, standards, and reform | That the Country Fire Authority Act 1958 be amended to: |
REC104-2254 | 24 - Govt responsibility | That a single state-of-the-art all hazards State Emergency Operations Centre be established for Victoria. This could, if necessary, be implemented in stages, initially incorporating DSE, CFA, MFESB and the State Aircraft Unit. |
REC104-2311 | 32 - Doctrine, standards, and reform | That all Departments, statutory authorities, utility providers and Local Governments be made aware of the need to develop contingency plans for recovery activities, and that such plans, and the associated public education and information strategies, are included in the Municipal Emergency Management Plans. |
REC104-2230 | 24 - Govt responsibility | That DSE investigates whether such agreements should exist with other government Departments and agencies, particularly those with officers located in rural Victoria who may be involved in fire response and support operations in the future, based on their expertise and experience. |
REC104-2276 | 32 - Doctrine, standards, and reform | That CFA and DSE jointly develop procedures to ensure that a more consistent strategic approach can be maintained at shift and tour of duty changes. |
REC104-2316 | 33 - Relief and recovery | That the State Emergency Recovery Committee explore opportunities to establish a 'one-stop shop’ approach wherever practicable following emergencies, including a single telephone number to connect a person to all agencies involved in the recovery process. |
REC104-2192 | 24 - Govt responsibility | That, according to available scientific evidence, a decision regarding cattle grazing in the High Country should not be based on the argument that ‘grazing prevents blazing.’ |
REC104-2239 | 24 - Govt responsibility | That any local level agreements developed to address geographically specific risks or issues must be consistent with State-level arrangements. |
REC104-2303 | 24 - Govt responsibility | That Interstate Agreements prepared by the fire agencies be reviewed to include protocols for the joint release of consistent and appropriate information relating to fires burning across State borders. |
REC104-2330 | 32 - Doctrine, standards, and reform | That this unified system include recommendations for the appointment of one person or agency to be responsible for overall control of fire suppression activity in country Victoria, including for any legislative reform considered necessary. |
REC104-2219 | 32 - Doctrine, standards, and reform | That, following the review of Forest Industry Brigades, the Country Fire Authority Act 1958 be amended to ensure that the Forest Industry Brigades, which are acting in an approved manner, have the same powers and rights as other Brigades when attending fires on public land or interstate. |
REC104-2253 | 32 - Doctrine, standards, and reform | That Victoria Police, CFA and DSE review the relationship between fire service regional co-ordination arrangements and Divisional Emergency Response Plans and that any changes be formalised in the emergency management arrangements. |
REC104-2310 | 33 - Relief and recovery | That recovery is recognised as commencing at the same time as response and that recovery planning and delivery is an integral part of the operations of the Municipal Emergency Co-ordination Centres. |
REC104-2229 | 32 - Doctrine, standards, and reform | That DSE and the Department of Primary Industries formalise an agreement by the 2003-2004 fire season documenting the policies, procedures and financial arrangements relating to the availability of Department of Primary Industries staff to be trained and released for fire prevention and suppression activities on public land. |
REC104-2261 | 32 - Doctrine, standards, and reform | That the emergency management arrangements be amended to require Police Divisional Emergency Response Coordinators, in consultation with other response agencies, to establish and document procedures and structures at regional level in order to ensure there is: |
REC104-2315 | 24 - Govt responsibility | That the Privacy Commissioner be asked for advice in the development of this model. |
REC104-2237 | 12 - EM agency and authority | That CFA continues to work with its Brigades to complete the integration of AIIMS-ICS with the Group Structure for full implementation by the 2004-2005 fire season. |
REC104-2288 | 32 - Doctrine, standards, and reform | That CFA develop protocols to integrate Ultra High Frequency and Citizen Band radios into their communication structures. |
REC104-2329 | 32 - Doctrine, standards, and reform | That CFA, DSE, MFESB and Victoria Police jointly develop a unified command and control system that better integrates with the State's emergency management arrangements, and that this be endorsed by the Victoria Emergency Management Council by July 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3949 | 17 - Assets and technology | It is recommended that the A.R.P. dams or earth tanks be kept filled during possible danger periods. |
REC016_3946 | 12 - EM agency and authority | It is recommended that it [The Fire Brigade] endeavour and be encouraged to add to its reserve of members, and that the reserves be fully and efficiently trained. Should fire on a wide, unbroken front attack the town, the brigade, if limited to its present numbers, could not be expected to be able to save the town. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3956 | 24 - Govt responsibility | It is strongly recommended that no public department of possible combination of public departments interested in forests should be permitted to gain control of this authority. |
REC015_3955 | 12 - EM agency and authority | The institution of a State Fire Authority is recommended. |
REC015_3961 | 12 - EM agency and authority | It is recommended that each forestry officer should be stationed in one district for as long a time as is practicable consistent with justice to the officer. |
REC015_3954 | 24 - Govt responsibility | It is recommended that each public department or body which may now or hereafter control forest areas be allowed to pursue its own policy of fire prevention and suppression. As each such body is responsible directly or indirectly to Parliament it must be allowed to carry its responsibility in its own manner. It is strongly recommended that no such department be given authority over any other body in matters relating to fire prevention or suppression. If it is ultimately shown that a department is unfit to discharge the duty involved other measures may be taken. |
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |
REC015_3958 | 12 - EM agency and authority | It is recommended that all members of the police force, members of brigades, municipal engineers and forest officers should be appointed as wardens. |
REC015_3957 | 12 - EM agency and authority | It is recommended that the functions of this authority should be primarily those of defining a general policy of prevention and suppression of bush fires and protection of life and property; of organizing and recruiting local brigades; of maintaining discipline of local brigades and over local fire authorities; and of acting independently, with or without such advice as it may care to take. |