Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4013 | 19 - Offences | Infringement of the regulations by either party should be followed by a summary form of justice, instituted before two Magistrates. |
REC002-4002 | 19 - Offences | Where safety-lamps are necessary - gas being present for (say) one month after being found in dangerous quantity - they should be securely locked by a man duly appointed, and tampering with them must be punishable by a simple and inexpensive process of law. |
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0681 | 19 - Offences | Councils and distributor-retailers should agree to protocols for the exchange of information about suspected illegal connections, the steps being taken to investigate them or the basis for concluding that no investigation is required, and the results of any investigations or enforcement actions. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3454 | 24 - Govt responsibility | That the Department of Transport ensures that key stakeholders are engaged during the implementation of the approved Review recommendations. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
REC158-3448 | 24 - Govt responsibility | That the Director of Marine Safety works with the Australian Maritime Safety Authority to ensure that State and port emergency arrangements interface appropriately with the National Maritime Emergency Response Arrangements. |
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
REC158-3433 | 24 - Govt responsibility | That Harbour Masters are employed by a government body and remain geographically located at the port. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3664 | 20 - Role of police | The location of the command post for site control at the scene of any rail accident should be identified by NSW Police by a distinctive flashing light. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3998 | 19 - Offences | That a by-law be made forbidding, under a heavy penalty, any persons travelling in such trains to throw lighted tobacco, cigars, cigarettes, pipe ashes, matches, or other inflammable matter on the railway line or right-of-way, or in any part of a railway carriage except the receptacles duly provided for the purpose. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |