REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
Rec-ID | Code | Recommendation | |
---|---|---|---|
REC323-4279 | 37 - Funding |
|
|
REC323-4280 | 37 - Funding | That the NSW Government work with local governments to identify alternative routes to vulnerable roads, and that the NSW and Australian Governments fund the construction of these important routes to improve evacuation and access options in times of disaster. |
|
REC323-4261 | 37 - Funding | That the NSW Government advocate through the National Cabinet to widen eligibility under the Disaster Funding Recovery Arrangements to allow local councils to build back better. |
|
REC323-4281 | 37 - Funding | That the NSW Government allocate funding to the improvement of the Pitt Town Evacuation Route and other key possible evacuation routes in Sydney's northwest. |
|
REC323-4270 | 37 - Funding | That the NSW Government consider entering into a service agreement with an organisation that has the resources and capacity to manage donations and activate quickly during natural disasters. |
|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
|
REC323-4272 | 37 - Funding | That the NSW Government ensure that flood affected individuals can continue to access financial assistance for as long as there is demonstrated need. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2560 | 29 - Operational Health and Safety | The Civil Aviation Safety Authority devolve to Designated Aviation Medical Examiners the ability to renew aviation medical certificates (for Classes 1, 2, and 3) where the applicant meets the required standard at the time of the medical examination. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2791 | 37 - Funding | The committee recommends that the government develop a process by which the ATSB can request access to supplementary funding via the minister. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1845 | 37 - Funding | The state government should provide core, ongoing funding to the responsible authority for the FloodSafe community education program. Funding should be provided for education about prevention, response and recovery phases and include information on rates notices about the height of particular floods. |
REC217-1842 | 37 - Funding | The state government review the current funding approach used for the operation, maintenance and upgrade of river gauges, with a view to improving the river gauge network. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1814 | 37 - Funding | The funding model for works on levees and their ongoing maintenance be revised, to be primarily based on the beneficiary pays principle. The state government should give consideration to wholly funding, or contributing to, the initial upgrade of high priority levees to an agreed standard. The construction of any new public levees will be the subject of a cost‐benefit analysis to be undertaken by DSE and the public authority, and be supported by a floodplain management study. Levees deemed low priority will be wholly the responsibility of the beneficiaries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0418 | 7 - Inter-agency communication | the state develop an efficient process to ensure that, during flood events, temporary construction of flood mitigation works, such as levees, is controlled so as not to unacceptably impact on flood intelligence. |
REC199-0458 | 7 - Inter-agency communication | the state ensure: • a common, functional and accessible system be introduced to enable effective Municipal Emergency Coordination Centre and Incident Control Centre communications • a regime of regular Municipal Emergency Coordination Centre exercising is introduced with oversight by an appropriate independent body. Such exercising should include testing of systems utilised for Incident Control Centre and Municipal Emergency Coordination Centre communications • those required to perform Emergency Management Liaison Officer roles have undertaken appropriate training; and • resource requesting arrangements are clarified and documented so that control and coordination functions do not overlap. |
REC199-0449 | 7 - Inter-agency communication | the state ensure that interoperable information management practices are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0447 | 7 - Inter-agency communication | the state ensure that common and interoperable resource management systems are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0446 | 7 - Inter-agency communication | the state commit to securing effective multi-agency interoperable communications as a high level priority and that all future communications projects and upgrades incorporate compliance provisions mandating interoperability requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2912 | 29 - Operational Health and Safety | The review team recommend that the safety case system be strengthened by including provisions for a design notification scheme along the lines of that under the British Offshore Safety Case Regulations. |
REC189-2911 | 29 - Operational Health and Safety | The review team recommend that: |
REC189-2907 | 29 - Operational Health and Safety | a) For the purposes of designing and implementing its regulatory activities, National Offshore Petroleum Safety Authority (NOPSA) should continue to identify priority hazards and risks and their underlying causes, in consultation with the NOPSA Advisory Board and stakeholders (see Theme 9, Stakeholder engagement). |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3135 | 29 - Operational Health and Safety | The initial acceptance of a new facility Safety Case should be in conjunction with inspection of a facility upon commencement of operations. |
REC149-3128 | 29 - Operational Health and Safety | National Offshore Petroleum Safety Authority (NOPSA) should develop guidelines in consultation with stakeholders to provide clarity and consistency to the process which ultimately will result in better safety outcomes. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3147 | 29 - Operational Health and Safety | As all stakeholders have responsibility for safe outcomes, decisions regarding target subjects for safety promotion need to have the support of all stakeholders including NOPSA and the workforce. Industry, which ultimately has the responsibility for managing risk as well as funding the promotion, should take a leadership role in implementation. |
REC149-3144 | 29 - Operational Health and Safety | The Safety Case proponent should be allowed some flexibility to involve appropriate experience matched with the proposed workforce competencies to enable the Safety Case to be developed with value adding processes. Subsequent to the hiring of the workforce Final Government Response Offshore Petroleum Safety Regulation Inquiry and 2008 Review of NOPSA Operational Activities and preferably before the commencement of operations a review of the Safety Case should take place with the new workforce to ensure they understand the accepted Safety Case, its risks and Safety Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3737 | 29 - Operational Health and Safety | There must be a minimum of two independent methods of self-initiated emergency escape for passengers from all trains at all times. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3682 | 29 - Operational Health and Safety | All new rolling stock should be designed to be compatible with at least level 2 automatic train protection discussed in chapter 7 of this report. |
REC121-3743 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must have the external emergency door release clearly marked with the words “Emergency Door Release”. |
REC121-3711 | 29 - Operational Health and Safety | The ITSRR should establish an electronic document control system to enable effective and reliable information to be gathered for monitoring the safety of the New South Wales rail system. |
REC121-3755 | 29 - Operational Health and Safety | The RailCorp Board should require a full review of the safety competence of RailCorp managers to ensure that each has the ability to bring about those safety reforms recommended in this report which are applicable to his or her position. |
REC121-3735 | 29 - Operational Health and Safety | Risk assessments of occupational health and safety issues by RailCorp should include an analysis of broader public safety risks and not be confined to narrow occupational health and safety issues. |
REC121-3681 | 29 - Operational Health and Safety | RailCorp should progressively implement, within a reasonable time, level 2 automatic train protection with the features identified in chapter 8 of this report. |
REC121-3741 | 29 - Operational Health and Safety | The operation of the train doors should have an override facility whereby the train driver or the guard can override an internal passenger emergency door release system if the door release is interfered with when there is no emergency. There should be an alarm, together with an intercom, in the train guard’s compartment so that, if a passenger attempts to initiate an emergency door release, there is an appropriate delay during which time an alarm sounds in the train guard’s compartment and the guard can then, after first attempting to speak via the intercom to the person concerned, if necessary, override the door release, and make an appropriate announcement over the intercom system in the train. |
REC121-3709 | 29 - Operational Health and Safety | RailCorp should provide access to electronic versions of safety documentation for all operational staff at their workplace. |
REC121-3754 | 29 - Operational Health and Safety | The RailCorp Board should ensure that RailCorp has an adequate and integrated safety management system, including adequate systems for risk assessment, clearly defined safety responsibilities and accountabilities for persons holding management positions, and specific performance criteria against which evaluations can be made of safety performance and accountability for safety performance of all managers. |
REC121-3734 | 29 - Operational Health and Safety | RailCorp should integrate its management of occupational health and safety into its overall safety management. |
REC121-3680 | 29 - Operational Health and Safety | All trains must be fitted with a minimum of two independent engineering defences to minimise the risk of derailment or collision in the event of train driver incapacitation. |
REC121-3740 | 29 - Operational Health and Safety | The internal passenger emergency door release should be fitted with a facility which prevents it from operating unless the train is stationary. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3707 | 29 - Operational Health and Safety | The safety document management system should provide for the distribution of electronic versions of safety documentation to relevant staff. |
REC121-3749 | 29 - Operational Health and Safety | All new rolling stock must be designed with an area of the roof through which emergency services personnel can access a rail car without encountering wiring or other equipment. That access point must be clearly marked with words such as “emergency services cut here”. |
REC121-3733 | 29 - Operational Health and Safety | RailCorp’s approach to occupational health and safety should be proactive and involve the systematic analysis of all current hazards, risks and controls and an assessment of their adequacy to reduce the risk of injury to, or death of, employees to an acceptable level. |
REC121-3739 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must be fitted with external emergency door releases which do not require any special key or other equipment to operate. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3706 | 29 - Operational Health and Safety | RailCorp should establish a comprehensive safety document management system. |
REC121-3748 | 29 - Operational Health and Safety | All new rail cars must have appropriate signage and lighting identifying escape routes in the case of emergency. |
REC121-3732 | 29 - Operational Health and Safety | If ITSRR accepts such a plan as an appropriate response to the existing weak safety culture, ITSRR should approve it and monitor the effectiveness of the plan. |
REC121-3764 | 29 - Operational Health and Safety | The ITSRR should not grant accreditation to any rail organisation unless it has an integrated safety management system in accordance with any safety management system regulation and the guidelines published from time to time by ITSRR. |
REC121-3738 | 29 - Operational Health and Safety | All passenger trains must be fitted with an internal passenger emergency door release. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3702 | 29 - Operational Health and Safety | Random alcohol testing should be continued. |
REC121-3747 | 29 - Operational Health and Safety | All trains should have windows available through which passengers can escape. |
REC121-3731 | 29 - Operational Health and Safety | RailCorp should develop a plan to be submitted to ITSRR to address the deficiencies in the safety culture of RailCorp, including: |
REC121-3759 | 29 - Operational Health and Safety | A Safety Reform Program Director (hereafter referred to as SRPD), reporting directly to the Chief Executive of RailCorp, should be retained to manage, as head of a Safety Reform Program Office, any safety reform program being undertaken by RailCorp. The SRPD should work with the Chief Executive and senior management to ensure the implementation of an integrated safety management system and the cultural change required. The SRPD must have qualifications suitable for recognition by the Australian Institute of Project Management as a master program director. He or she should report to and be under the control of the Chief Executive, to ensure that the accountability of the Chief Executive is not reduced. The SRPD should co-ordinate and integrate any existing rail safety reform programs and, in consultation with and with the authority of the Chief Executive he or she should: |