Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4328 | 9 - Community education | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services establish a community education program by 1 November 2023 that complements the implementation of the Australian Warning System. An evaluation process should be incorporated into the program to determine effectiveness. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4339 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends that Queensland Fire and Emergency Services review and update the State Disaster Risk Report, including re-evaluating the risk of flooding by all types. Queensland Fire and Emergency Services should publish the updated State Disaster Risk Report by 1 November 2023. |
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4307 | 9 - Community education | Flood education: That, to build disaster resilience in future generations as floods and other natural disasters are a fact of Australian life, the Department of Education should design, implement and deliver an evidence-based, targeted education campaign (like sun exposure) in schools (new disaster curriculum). |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2489 | 9 - Community education | To enable the community to have a shared understanding of risks and enhance community engagement, flood scenarios in Emergency Action Plans be published, and in a format that can be utilised by public mapping systems. |
REC311-2503 | 9 - Community education | To enable the casual/itinerant worker and tourism sector, including those who do not have English as a first language, to make informed choices about disaster management, community engagement and communication strategies about Paradise Dam and floods in the Burnett river system be tailored to this sector. |
REC311-2502 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, Sunwater develop and deliver a sustainable long-term communication strategy on the community safety issues and |
REC311-2501 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, a joint Sunwater/council community engagement program be conducted to prepare the community downstream from Paradise Dam for events in the 2019/2020 storm and cyclone season, including the possibility of a Paradise Dam failure. |
REC311-2500 | 9 - Community education | To enable the community to make informed choices about disaster management, Bundaberg and North Burnett regional councils and Sunwater undertake a community-informed audible test of the Paradise Dam siren. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1256 | 9 - Community education | That SES and Tasmania Fire Service share resources and align their community education programs and adopt an all-hazards approach to awareness. |
REC297-1251 | 9 - Community education | That all councils include an easily identifiable website link for the public to locate their Municipal Emergency Management Plan and community safety information. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2381 | 21 - Role of Commonwealth Government | I recommend that ASIO liaise with the Fixated Threat Assessment Centre with a view to both agencies cooperating in the identification, assessment and management of fixated, radicalised individuals. |
REC292-2378 | 21 - Role of Commonwealth Government | I recommend that: the Commonwealth Attorney-General and ASIO confer with the Australian Psychological Society regarding the restrictions in clause A 5 2 of the Code of Ethics (2007) with respect to radicalisation, terrorism and politically motivated violence; and the Australian Psychological Society consider amending clause A 5 2 of the Code of Ethics (2007) to enable psychologists to report risks of a terrorist nature. |
REC292-2377 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth Attorney-General liaise with ASIO to develop a policy to ensure that where correspondence is received by a government agency, minister or public office holder, from a non government entity, and that correspondence is relevant to the security assessments of the author, the correspondence be referred to: ASIO; and a Fixated Threat Assessment Centre. |
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1524 | 9 - Community education | SunWater provide downstream residents with easily understood information regarding operation of the dam, and the impacts that various outflows may have for them, in accordance with mapping prepared for the Emergency Action Plan. This information should be complementary to any information from the Banana Shire Council. |
REC271-1523 | 9 - Community education | Banana Shire Council coordinates the development of a strategy to significantly enhance public education regarding local disaster management arrangements within the Banana Shire, focusing on key identified risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0811 | 9 - Community education | Monitor, investigate and address community response to flood warnings |
REC238-0810 | 9 - Community education | Undertake, coordinate and evaluate community education programs on flood risk and response. |
REC238-0809 | 9 - Community education | Ensure the SES has the long-term capacity to plan and exercise for the full range of flood events in the Hawkesbury-Nepean Valley |
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
REC238-0812 | 9 - Community education | Develop mechanisms and arrangements to promote and provide greater access to flood risk information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2813 | 38 - Agency/Department Reporting | To strengthen its oversight of Queensland reconstruction progress, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce: |
REC234-2810 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Australian Government Reconstruction Inspectorate and the National Disaster Recovery Taskforce seek to maximise the benefits from their value for money review activities by obtaining more timely and comprehensive information on project progress and completion from the Queensland Reconstruction Authority, to enable the preliminary value for money assessments to be finalised based on the scope and cost of works that were actually delivered (rather than estimates). |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2864 | 9 - Community education | Management of community expectations: continued community education. |
REC216-2863 | 9 - Community education | Management of community expectations: better understanding of what different groups within a community expect. |
REC216-2865 | 9 - Community education | Management of community expectations: further development of tools that would allow the community to more easily |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0680 | 9 - Community education | Queensland Urban Utilities, and other distributor-retailers and councils, that have identified a practice of stormwater drains being connected to sewerage infrastructure, should conduct a program of education to raise public awareness that this practice is illegal and impedes the operation of the sewerage infrastructure. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0615 | 9 - Community education | Flood maps, and property specific flooding information intended for use by the general public, should be readily interpretable and should, where necessary, be accompanied by a comprehensible explanatory note. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0614 | 9 - Community education | Councils and the Queensland Government should display on their websites all flood mapping they have commissioned or adopted. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0604 | 9 - Community education | By reference to the order of priority determined in accordance with recommendation 2.5, the Queensland Government and councils should together ensure that the council responsible for each urban area in Queensland has access to current flood study information. This will include determining: a. a process or processes by which the flood studies will be completed, including the involvement of the Queensland Government and relevant councils b. how, and from whom, the necessary technical and financial resources will be obtained c. a reasonable timeframe by which all flood studies required will be completed. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0603 | 9 - Community education | The Queensland Government, in consultation with councils, should determine which urban areas in Queensland do not have access to flood information from a current flood study. The Queensland Government should rank those areas in order of priority in accordance with their need for updated flood information by reference to factors including: a. population b. sophistication of land use planning and emergency management measures already in place in those areas c. currency of any flood risk information available to the council d. approximate frequency of damaging floods in the area according to the historical record |
REC210-0689 | 9 - Community education | Councils should conduct education campaigns directed to ensuring that all residents and property owners in areas identified as being at risk of backflow flooding are aware of the circumstances in which backflow flooding can occur, the hazard it presents and what should be done if it occurs. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0431 | 9 - Community education | the state allocate core funding for the ongoing delivery of the ‘FloodSafe’ program to flood prone communities across Victoria. |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0430 | 9 - Community education | the state undertake a community education program to inform households of their respective flood risk. This may include information on rate notices of heights of houses above flood level and educating people about flash flooding. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0483 | 9 - Community education | the state ensure: • where external assistance is provided to Victoria during emergencies, communities are advised of the specific purpose of that assistance, through media and other information channels; and • all agencies provide incident management personnel with information regarding the arrangements for tasking Australian Defence Force resources and that this advice is reinforced during emergencies where Australian Defence Force support is provided. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2946 | 21 - Role of Commonwealth Government | That a national agency sponsored by the Commonwealth Government be established to undertake national coordination of flood risk management and to operate the system of premium discounts and the flood risk reinsurance facility. The Agency would: |
REC187-2918 | 21 - Role of Commonwealth Government | That an agency sponsored by the Commonwealth Government be created to manage the national coordination of flood risk management and to operate a system of premium discounts and a flood risk reinsurance facility, supported by a funding guarantee from the Commonwealth. |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2997 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet and Victoria Police, in consultation with departments, should standardise reporting on training exercises conducted under Part 6 of the Act and the CIP framework to promote greater consistency and to enable better identification of lessons learned and continuous improvement. |
REC169-2989 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet should lead the development of a performance management framework for measuring, monitoring and reporting on the implementation of Part 6 of the Act and the CIP framework. The framework should include key indicators, targets and reporting arrangements for assessing the extent to which departments, agencies and industry have fulfilled their obligations, as well as measures for monitoring achievement of joint objectives. |
REC169-2998 | 38 - Agency/Department Reporting | Reports on the training exercises should be retained in an appropriately secured central repository so that consolidated results of the exercises can be drawn together effectively. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0074 | 9 - Community education | SERCon consider a review of existing community-based educational programs, with a view to informing the community |
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3634 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter- Terrorism Committee, pursue the adoption of a more strategic approach to determining the National Capability Development Exercise Programme so that: |
REC117-3641 | 38 - Agency/Department Reporting | The ANAO recommends that, to ensure the outcomes of evaluations are effectively used to enhance the national counter-terrorism arrangements, the Attorney-General’s Department and the Department of the Prime Minister and Cabinet take appropriate measures to ensure: |
REC117-3633 | 38 - Agency/Department Reporting | The ANAO recommends that, to provide better information to contribute to strategic assessments, decisions and reporting, the Attorney-General’s Department, with input and guidance from the Department of the Prime Minister and Cabinet: |
REC117-3639 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the National Counter-Terrorism Committee, strengthens the reporting on the National Capability Development Exercise Programme through: |
REC117-3638 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee: |
REC117-3637 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, pursue a more strategic and systematic approach to the measurement of performance via the National Capability Development Exercise Programme by: |
REC117-3636 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in conjunction with the National Counter-Terrorism Committee’s exercise management advisers, explore options for the incorporation of more contemporary and varied testing and training aids in the National Capability Development Exercise Programme. |