REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4106 | 13 - Mapping and data quality | Australian, state and territory governments should ensure greater consistency and collaboration in the collation, storage, access and provision of data on the distribution and conservation status of Australian flora and fauna. |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4065 | 13 - Mapping and data quality | Australian, state and territory governments should continue to develop a greater capacity to collect and share standardised and comprehensive natural disaster impact data. |
REC317-4105 | 13 - Mapping and data quality | Australian, state and territory governments should agree to: |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4130 | 21 - Role of Commonwealth Government | The Australian Government should establish accountability and assurance mechanisms to promote continuous improvement and best practice in natural disaster arrangements. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4120 | 16 - Training and behaviour | Australian, state and territory governments should establish a national mechanism for sharing of trained and qualified recovery personnel and best practice during and following natural disasters. |
REC317-4060 | 13 - Mapping and data quality | Australian, state and territory governments should create common information platforms and share technologies to enable collaboration in the production, analysis, access, and exchange of information, data and knowledge about climate and disaster risks. |
REC317-4068 | 13 - Mapping and data quality | Australian, state and territory governments should establish a national register of fire and emergency services personnel, equipment and aerial assets. |
REC317-4109 | 13 - Mapping and data quality | Australian, state and territory governments should develop consistent processes for the classification, recording and sharing of fuel load data. |
REC317-4059 | 13 - Mapping and data quality | Australian, state and territory governments should prioritise the implementation of harmonised data governance and national data standards. |
Rec-ID | Code | Recommendation |
---|---|---|
REC266-1534 | 21 - Role of Commonwealth Government | The Australian National Audit Office (ANAO) recommends that the Attorney‐General’s Department significantly improve the administration of disaster relief and recovery funding by: |
REC266-1535 | 21 - Role of Commonwealth Government | To provide improved oversight and assurance in its administration of the Natural Disaster Relief and Recovery Arrangements, the Australian National Audit Office (ANAO) recommends that the Attorney‐General’s Department: |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1540 | 16 - Training and behaviour | Commanding Officer Defence Explosive Ordnance Training School, assisted by Joint Logistics Command Regional Explosive Ordnance Serices staff, conduct explosive ordnance accounting training for all instructional staff as a matter of priority and that such training be conducted for Defence Explosive Ordnance Training School staff on an annual basis. |
REC257-1536 | 16 - Training and behaviour | The Australian defence Force Explosive Ordnance Disposal course be reviewed by Manager Joint Training - Air Force, to ensure the assessments meet the learning outcomes specificed in the relevant Training Management Package. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
REC256-1576 | 21 - Role of Commonwealth Government | Within three years, the Australian Government should develop and implement a framework for untied grants for community recovery assistance to state and territory governments. This framework should take into account factors such as the type, location and scale of a disaster, and the number of people affected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2886 | 21 - Role of Commonwealth Government | Explore options to limit forecaster intervention in site-specific web forecasts. |
REC207-2896 | 21 - Role of Commonwealth Government | Lower yield options identified by the Bureau: |
REC207-2872 | 21 - Role of Commonwealth Government | Boost the number of frontline meteorologists to build response capacity in regional forecasting centres. |
REC207-2900 | 21 - Role of Commonwealth Government | Explore use of social media to enhance data gathering from authorised and informal sources and to disseminate weather information |
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
REC207-2895 | 21 - Role of Commonwealth Government | Fund delivery of improved seasonal forecasting services by: |
REC207-2899 | 21 - Role of Commonwealth Government | Improved seasonal forecasting capabilities: |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
REC207-2894 | 21 - Role of Commonwealth Government | Phase out seasonal prediction development and modelling and rely on products generated elsewhere |
REC207-2898 | 21 - Role of Commonwealth Government | Upgrade to the Bureau’s supercomputing capacity: |
REC207-2878 | 21 - Role of Commonwealth Government | Complete workforce planning project and succession plans as a matter of urgency. |
REC207-2891 | 21 - Role of Commonwealth Government | Cease or reduce the Ionospheric Prediction Service or offer it as a commercial service. |
REC207-2897 | 21 - Role of Commonwealth Government | Additional frontline meteorologists and specialised centres and systems: |
REC207-2876 | 21 - Role of Commonwealth Government | Focus the Bureau’s evolving environmental information role on natural hazards in the first instance. |
REC207-2887 | 21 - Role of Commonwealth Government | Centralise media services and establish protocols for media activity. |
REC207-2896 | 21 - Role of Commonwealth Government | Lower yield options identified by the Bureau: |
REC207-2873 | 21 - Role of Commonwealth Government | Boost the Bureau’s flood warning capacity by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2913 | 21 - Role of Commonwealth Government | In developing and improving its policies and practices for stakeholder engagement, NOPSA should ensure that: |
REC189-2910 | 21 - Role of Commonwealth Government | NOPSA should: |
REC189-2908 | 21 - Role of Commonwealth Government | To ensure that NOPSEMA is in a strong position to perform its functions effectively: |
REC189-2906 | 21 - Role of Commonwealth Government | In order to improve the effectiveness of National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), with similar benefits for State or Territory regulators, attention should be given to the following actions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3375 | 21 - Role of Commonwealth Government | For the purposes of that review, the Minister should issue a ‘show cause’ notice to PTTEPAA under s 276 of the OPGGS Act. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3351 | 21 - Role of Commonwealth Government | In the future, and in the interests of ensuring that all possible well control options are comprehensively pursued to exhaustion, decisions as to well control response options should be the result of collaboration between the regulator and the operator rather than leaving one party to make unilateral judgements as to the appropriateness of various well control operations. The regulator should provide transparent and contemporaneous explanations to the public of all well control options under consideration at any particular time. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3372 | 21 - Role of Commonwealth Government | OSCPs should be endorsed by AMSA prior to regulatory approval to ensure that they align with the National Plan. Once field operations commence, the capability of operators should be assessed against their plans, and exercises conducted to ensure the plans remain effective. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3349 | 21 - Role of Commonwealth Government | In the meantime, the Minister should: |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3371 | 21 - Role of Commonwealth Government | The Government should examine the scope for a single environment plan to meet the regulatory requirements of both the OPGGS Act and the EPBC Act. This could possibly be achieved by way of bilateral agreements and accreditation arrangements and/or legislative amendment. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3348 | 21 - Role of Commonwealth Government | Responsibility for well integrity should be moved to NOPSA (as also proposed by the Productivity Commission). |
REC177-3358 | 21 - Role of Commonwealth Government | The body established to undertake a central coordination and facilitation role in the event of any future blowout in Commonwealth waters should undertake to make all relevant information publically available from one, authoritative and easy to access source. |
REC177-3274 | 21 - Role of Commonwealth Government | The Minister should appoint a senior policy adviser to investigate and report on the best means to implement the recommendations contained in this Chapter 3 of this report. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3347 | 21 - Role of Commonwealth Government | The proposal of the Productivity Commission’s Research Report (Review of Regulatory Burden on the Upstream Petroleum (Oil and Gas) Sector, April 2009) to establish a NOPR should be pursued at a minimum. |
REC177-3357 | 21 - Role of Commonwealth Government | In any future similar blowout or offshore emergency situation, the Minister appoint (through either a NOPR or the relevant Department) a senior public servant to establish and oversight a central coordinating body that will facilitate interaction between regulators, industry, AMSA and the owner/operator. Primary responsibility for stopping a blowout should remain with the owner/operator but should be subject to direction from the central coordinating body in consultation with stakeholders (including the owner/operator). |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3376 | 21 - Role of Commonwealth Government | In carrying out a review of PTTEPAA’s permit and licence, the Minister should have regard to this Report, particularly (i) the adverse findings set out in this Chapter; and (ii) the extent to which PTTEPAA has implemented the Action Plan submitted to the Inquiry, or otherwise addressed the matters canvassed in this Report. |
REC177-3346 | 21 - Role of Commonwealth Government | A single, independent regulatory body should be created, looking after safety as a primary objective, well integrity and environmental approvals. Industry policy and resource development and promotion activities should reside in government departments and not with the regulatory agency. The regulatory agency should be empowered (if that is necessary) to pass relevant petroleum information to government departments to assist them to perform the policy roles. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC160-3041 | 21 - Role of Commonwealth Government | To improve the governance arrangements for business continuity management (BCM) in Centrelink ,the Australian National Audit Office (ANAO) |
REC160-3043 | 21 - Role of Commonwealth Government | The ANAO recommends that Centrelink develop and promulgate a business continuity plan (BCP) template and require business units to develop BCPs that identify: |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3143 | 21 - Role of Commonwealth Government | The role of the advisory Board, namely to give advice to Ministers and NOPSA when asked, should be made clear to Board members and all stakeholders. The Board and NOPSA should consider the need for a clear description of who does what based on the legislated responsibilities of the NOPSA CEO. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
REC148-3162 | 21 - Role of Commonwealth Government | That facilities for the unloading and transferring of horses at Tullamarine Airport in Melbourne be constructed urgently, upon advice of experts in biosecurity containment, to enable adequate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. |
REC148-3168 | 21 - Role of Commonwealth Government | That each government controlled and operated quarantine station have sufficient staff to carry out properly all activities and measures required by the current operating procedures dealing with the quarantine of horses. |
REC148-3161 | 21 - Role of Commonwealth Government | That the facilities for unloading and transferring of horses at Sydney (Kingsford Smith) Airport be upgraded without delay, following the advice of experts in biosecurity containment, so as to enable appropriate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. The facilities should include at least one padded box or stall sound-proofed to the extent that it is reasonable to do so. |
REC148-3166 | 21 - Role of Commonwealth Government | That, in the absence of other satisfactory government controlled and operated post-arrival quarantine stations becoming available before the options to renew the leases of Eastern Creek and Spotswood Quarantine Stations expire, those options be exercised. |
REC148-3152 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse Importation may be removed in the following circumstances only: |
REC148-3165 | 21 - Role of Commonwealth Government | That there continue to be in Australia government controlled and operated post-arrival quarantine stations for horses. |
REC148-3151 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse |
REC148-3164 | 21 - Role of Commonwealth Government | That there be similar facilities for the unloading and transfer of horses at any other airport in Australia that might receive horses imported from places other than New Zealand. |
REC148-3148 | 21 - Role of Commonwealth Government | That the Secretary of the Department of Agriculture, Fisheries and Forestry designate, without delay, a Senior Executive Service officer to be primarily responsible and accountable for the importation of horses into Australia and to that end to have the power to exercise all necessary authority. |
REC148-3163 | 21 - Role of Commonwealth Government | That there be provided without delay at Sydney (Kingsford Smith) and Tullamarine Airports facilities to enable people who might have had contact with imported horses to shower and change their clothes, under supervision, before leaving the airport. |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3187 | 16 - Training and behaviour | The ANAO recommends that, in order to maximise the benefit of emergency management training activities, EMA review periodically its approach to delivering individual training courses, to ensure the most appropriate delivery mechanism is used commensurate with training objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC134-3520 | 21 - Role of Commonwealth Government | To improve the management of the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing incorporate into its governance framework: |
Rec-ID | Code | Recommendation |
---|---|---|
REC118-3644 | 21 - Role of Commonwealth Government | That the Prime Minister’s Science, Engineering and Innovation Council requests that the Australian Government, through the Australian Emergency Management Committee, develops an effective pathway to incorporate hazard science into emergency management policy. |
REC118-3643 | 21 - Role of Commonwealth Government | Consolidate the Australian Government decision to establish an Australian Tsunami Warning System through a long-term government commitment to ensure a sustainable and effective national tsunami warning system beyond the current four-year initiative. |