REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0788 | 25 - Inquiry, audit, lessons management and after action review | TFS seek to address the following outstanding items from the recommendations of the Victorian Bushfires Royal Commission. § 45 out of 53 Community Bushfire Response Plans for “at risk” communities have been finalized. The remaining eight should be completed as a priority action. § That TFS progress the development of Community Bushfire Mitigation Plans for the 53 at risk communities, possibly as an action for reactivated Fire Management Area Committees. § TFS, together with other ESOs and local government, should develop a common comprehensive approach to the option of planned evacuation from dangerous or potentially dangerous areas to safer areas and eventual return. § TFS should include factors for consideration for evacuation during a bushfire into their training doctrine for Incident Controllers. § The IAP Template and its application be reinforced as an important operational requirement for IMT’s during the 2013-14 pre-season briefing program. 10 § That TFS review their use of IRMS to ascertain if either its full potential is not being realized through a lack of operator training or it is in fact not providing the required functionality and there is a need to research an improved resource management system which enhances interoperability. § The TFS Publication: Guidelines for Development in Bushfire Prone Areas of Tasmania http://www.fire.tas.gov.au/userfiles/stuartp/file/Publications/BushDeve… s2012.pdf requires an update to reflect the provisions of Planning Directive #5 Bushfire-Prone Areas Code. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0222 | 22 - Role of local Gvt | The Local Government Association of Tasmania advocate, coordinate and support local councils’ input of bushfire risk assets data into the Bushfire Risk Assessment Model. |
REC193-0226 | 22 - Role of local Gvt | Local government councils should: strongly encourage owners to make improvements to construction or increase buffers in order to meet minimum safety standards implement programs to audit impacted properties and issue abatement notices where necessary monitor and maintain their reserves to ensure that adequate buffers to neighbouring buildings exist. |
REC193-0225 | 22 - Role of local Gvt | Local government councils should move promptly to: adopt the Tasmania Fire Service Guidelines for Development in Bushfire Prone Areas of Tasmania give effect to the Department of Primary Industries, Parks, Water and Environment Neighbouring Developments and Fire Management Policy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0202 | 22 - Role of local Gvt | The State develop and implement, in consultation with local government, a mechanism for sign-off by municipal councils of any permit conditions imposed under the Bushfire-prone Overlay and the regular assessment of landowners’ compliance with conditions. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0195 | 22 - Role of local Gvt | The State press municipal councils—in particular, Murrindindi Shire Council—to urgently adopt a bushfire policy in their Local Planning Policy Framework and incorporate bushfire risk management in their planning policies and strategies for rebuilding communities such as Marysville, Kinglake and others affected by the January–February 2009 fires. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0181 | 22 - Role of local Gvt | Municipal councils include in their municipal fire prevention plans for areas of high bushfire risk provision for the identification of hazard trees and for notifying the responsible entities with a view to having the situation redressed. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0153 | 22 - Role of local Gvt | The State establish mechanisms for helping municipal councils to undertake local planning that tailors bushfire safety options to the needs of individual communities. In doing this planning, councils should: ■ urgently develop for communities at risk of bushfire local plans that contain contingency options such as evacuation and shelter; ■ document in municipal emergency management plans and other relevant plans facilities where vulnerable people are likely to be situated—for example, aged care facilities, hospitals, schools and child care centres; ■ compile and maintain a list of vulnerable residents who need tailored advice of a recommendation to evacuate and provide this list to local police and anyone else with pre-arranged responsibility for helping vulnerable residents evacuate. |
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC180-2973 | 22 - Role of local Gvt | Local Government Victoria should, further to its work on strengthening the oversight role of audit committees, assist councils to develop good practice approaches to implementing, overseeing and continuously improving business continuity management. |
REC180-2972 | 22 - Role of local Gvt | Councils should strengthen their continuous improvement frameworks by: |
REC180-2971 | 22 - Role of local Gvt | Councils should improve the structure, format and content of their business continuity plans to provide greater clarity on roles and responsibilities for emergencies, more specificity on continuity and recovery responses, and better integration with other council disaster recovery and emergency plans. |
REC180-2970 | 22 - Role of local Gvt | Councils should improve assessments of business continuity risks by: |
REC180-2969 | 22 - Role of local Gvt | Councils should strengthen governance arrangements for business continuity by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3978 | 4 - Fire season preparation | Where possible to build stone or brick fireplaces for the use of travellers, teamsters, and drovers on the camping areas that are mostly used and where there is a risk of fire. |
REC013_3967 | 22 - Role of local Gvt | Each Shire Council shall divide the lands within their respective shires into suitable areas for the formation of Bush Fire Brigades as requested. |
REC013_3976 | 4 - Fire season preparation | To burn camping areas at suitable water and camping reserves. |
REC013_3968 | 22 - Role of local Gvt | Any number of persons, wishing to form a Bush Fire Brigade, may, by a majority vote of the ratepayers in the particular area, requisition the Shire Council to proclaim such area a Bush Fire Brigade area, and the Council may then impose, with the concurrence of a majority of such ratepayers, a special levy for the purpose of equipping such brigades and carrying out its neccessary functions. |