Rec-ID | Code | Recommendation |
---|---|---|
REC321-4203 | 9 - Community education | We recommend that DELWP provides advice to government, in consultation with Country Fire Authority, Fire Rescue Victoria and councils, on options to improve owner and occupier awareness of and accountability for bushfire management overlay planning controls (see Section 4.3). |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
REC316-4015 | 12 - EM agency and authority | The working group should report to SEMSOG on progress. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4039 | 12 - EM agency and authority | Establish a Communications Working Group (CWG) with representatives from across key Directorates (CMTEDD, ESA, ACT Policing, Health, CHS, EPSDD for example) to review the CCIP and to further identify how the CCIP can be best implemented and utilised. The CWG should report its progress though SEMSOG and coordinate with other WG’s. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4027 | 12 - EM agency and authority | All organisations who have a role in the ECC should review their existing arrangements to ensure there is a sufficient cohort of staff to maintain a presence in the ECC at a level and with an imprimatur sufficient to make decisions and allocate resources and have access to senior executive levels if needed. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
REC316-4026 | 12 - EM agency and authority | The role, level, requirements and expectations of an ECC LO be clarified in the Emergency Plan and ECC Ops Sub-plan. |
REC316-4036 | 12 - EM agency and authority | Government give consideration to investment in professional specialities such as fire behaviour analysts, airbase managers, aerial firefighting technical specialists etc for the RFS. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4022 | 12 - EM agency and authority | That when determining their Management Executive, at a minimum the EC should consider appointing Director-General JACS and the PIC as standing members. |
REC316-4031 | 12 - EM agency and authority | The ESA hold bi-lateral executive level meetings with the utility providers on a regular basis in consultation with other relevant Government stakeholders. |
REC316-4045 | 42 - Culture and Heritage | WHoG desktop exercise should be conducted to test and support relocation and evacuation planning. |
REC316-4016 | 12 - EM agency and authority | That the Emergency Plan be amended to include considerations for declaring a State of Alert or Emergency (and also wind back from these) and guidance as to what actions and decisions at a minimum should be taken as a consequence of such a declaration. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC275-1173 | 12 - EM agency and authority | IGEM recommends that fire agencies review their documentation systems and information recording processes to ensure that all operational activities are captured, and to maintain the accuracy and relevance of all developed products. This includes the need to ensure that all significant points of reference entered into mapping products are geo-coded to facilitate accurate transfer of information from one mapping product to another. |
REC275-1172 | 12 - EM agency and authority | IGEM recommends that fire agencies review their resource allocation recording mechanisms and systems to ensure that an accurate reflection of resources deployed to an incident at any given time can be ascertained |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1405 | 37 - Funding | That the Department of Justice & Regulation broadens Budget Paper 3 response time measures to more comprehensively cover emergency responses to fires, rescues and other emergencies. |
REC274-1411 | 12 - EM agency and authority | That the Country Fire Authority, Victoria State Emergency Service and Metropolitan Fire and Emergency Services Board improve controls over response time data collection and reporting. |
REC274-1410 | 12 - EM agency and authority | That the Department of Justice & Regulation applies a consistent approach to emergency response time measures including data capture, calculation and reporting. |
REC274-1409 | 12 - EM agency and authority | That the Department of Health & Human Services and Department of Justice & Regulation verify that response time data used in their reports on output performance measures is accurate and auditable. |
REC274-1407 | 12 - EM agency and authority | That the Department of Health & Human Services' and the Department of Justice & Regulation's public reporting of response time measures clearly attribute accountability for each phase of emergency response, including call-taking time involving the Emergency Services Telecommunications Authority. |
REC274-1406 | 12 - EM agency and authority | That the Department of Health & Human Services and Ambulance Victoria focus emergency response time reporting on highest priority cases. |
REC274-1413 | 12 - EM agency and authority | That Ambulance Victoria, Country Fire Authority, Metropolitan Fire and Emergency Services Board and Victoria State Emergency Service improve the transparency of public reporting on response times by including regional performance, times, trends and analysis of the factors affecting performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1099 | 12 - EM agency and authority | VicSES should: align ERAS-e profiles with its planning cycle |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC248-2582 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should provide one comprehensive source of information on leave |
REC248-2576 | 12 - EM agency and authority | Ambulance Victoria should review processes for managing personal unplanned leave evidence to reduce the risk that personal unplanned leave is incorrectly recorded |
REC248-2581 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should improve specialised human resources support to frontline managers |
REC248-2586 | 12 - EM agency and authority | Victoria Police should monitor the use of online tools for accessing unplanned leave data, to make sure that the tools are accessible and meet the needs of police managers |
REC248-2575 | 12 - EM agency and authority | Ambulance Victoria should review support for team managers who also perform paramedic duties and implement improvements to maximise team managers’ ability to perform their roles |
REC248-2580 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should provide operational commanders, senior station officers the personal unplanned leave of firefighters in their teams |
REC248-2585 | 12 - EM agency and authority | Victoria Police should improve the management of police members undergoing performance and discipline procedures |
REC248-2579 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should strengthen performance management of firefighter effectively manage personal unplanned leave |
REC248-2584 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should continue to strengthen human resource management processes and controls to reduce avoidable overtime costs. |
REC248-2578 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should review the impact of its enterprise agreements on the efficiency of frontline management, and on the implementation of audit recommendations, in preparation for enterprise agreement discussions in 2013 |
REC248-2583 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should review and strengthen controls over staff fulfilling their evidence to support personal unplanned leave |
REC248-2577 | 12 - EM agency and authority | Ambulance Victoria should closely monitor in rural regions the outcomes of its strategy to strengthen team management and adjust the strategy to address gaps or underperformance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1626 | 12 - EM agency and authority | The Emergency Services Agency and the Territory and Municipal Services Directorate should clarify the timing of the requirement for meeting firefighter fitness requirements, as set out in ACT Rural Fire Service operating procedures and the Territory and Municipal Directorate’s Enterprise Agreement, and give priority to meeting that requirement. |
REC228-1624 | 12 - EM agency and authority | The Emergency Services Agency should: |
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
REC228-1627 | 12 - EM agency and authority | The Emergency Services Agency (ACT Rural Fire Service headquarters) should implement a system to provide assurance to the Chief Officer of the ACT Rural Fire Service that personnel and equipment readiness meets requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2982 | 12 - EM agency and authority | The Department of Human Services should base targets for staff in emergency roles on regional needs and develop a staff deployment strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3054 | 12 - EM agency and authority | ACTAS should improve systems to manage its non-emergency transport services, provide training and guidance to staff on use of these systems, and implement a quality assurance process. |
REC159-3052 | 12 - EM agency and authority | ACTAS should develop and implement as a matter of priority, appropriate strategies to address declining response times. |
REC159-3049 | 12 - EM agency and authority | ACTAS should enhance its approach to demand modelling in order to better guide current and future ambulance resourcing by: |
REC159-3048 | 12 - EM agency and authority | ACTAS should enhance its approach to risk management by: |
REC159-3046 | 12 - EM agency and authority | ACT Ambulance Service (ACTAS) should revise its Business Plan to address key priorities and activities for each key service delivery function. This would include clearer expected outputs to be delivered annually and their prioritisation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1991 | 9 - Community education | That the Emergency Services Agency establish annual targets for the introduction of community education programs and provide resources to conduct regular independent assessments of the level of community preparedness engendered as a result of the programs |
REC126-1999 | 9 - Community education | That the Canberra Urban Development Working Group referred to in Mr Peter Dunn's letter consider the report prepared by Mr Leonard and note particularly that the community awareness information currently available to householders in connection with measures they can take to better protect their homes from bushfires does not refer to the potential of wooden fences, conifers and outbuildings to contribute greatly to fire spread, particularly in suburban areas. Also noteworthy is Mr Leonard's evidence that the linear sitting of homes on house blocks in Canberra seems to be an important factor contributing to house-to-house fire spread and that this should be avoided in future developments on the urban fringe |
REC126-1990 | 9 - Community education | That the Emergency Services Agency take measures to ensure that the community regularly receives up-to-date information on the risks of bushfires |
REC126-1996 | 9 - Community education | That the Emergency Services Agency develop a clear policy for disseminating information to the public and the media in times of emergency and that, as required, that policy incorporate advance door-knocking of homes in the area affected, as well as regular broadcasts by local radio and television stations and regular updates on the relevant website - be that Canberra Connect or a different ACT government website - as well as the Emergency Services Agency's website |
REC126-1963 | 12 - EM agency and authority | That priority be given to ensuring that the ACT has an adequate resource of remote area firefighting teams consisting of personnel with high levels of fitness and training in remote fire suppression |
REC126-1995 | 12 - EM agency and authority | That the Emergency Services Agency staff the Media Unit within its planning Section with profesisonal, experienced information officers skilled in dissemination of information and media management and liaison |
REC126-2005 | 9 - Community education | That community education programs include unambiguous information that at times of unusually high water demand there might be a drop in or loss of water pressure and it might be appropriate for residents who intend to remain and fight a fire to have auxilary water pumps or booster pumps |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1993 | 9 - Community education | That consulations and negotiations occur between the Emergncy Services Agency and the NSW Rural Fire Service to ensure that fire risk and safety messages to the community are coordinated. Maximum use should be made of television and radio announcements throughout the ACT and southern NSW, consistent with NSW timetables for targeted programs in conjunction with the United Firefighters Union ACT Branch and volunteer fire brigade representative. The Emergency Services Agency should consider using ACT Fire Brigade staff and ACT Rural Fire Service volunteers to talk to groups in the community on request, thus furthering face-to-face community education in high-risk suburban areas of the ACT |
REC126-2003 | 9 - Community education | That the community be made aware of the risk presented by heavy loads of garden fuels and certain types of vegetation around their houses and take active, regular measures to reduce that risk |
REC126-1949 | 12 - EM agency and authority | That the Emergency Services Agency be relocated into accommodation that is purpose-built and more sited to the agency’s operations than the current facility at Curtin |
REC126-1992 | 9 - Community education | That implementation of the Bushfire Wise Program continue and include a letterbox drop of the updated Bushfire Information Booklet |
REC126-2001 | 9 - Community education | That community education programs provide information about fire behaviour, urban design principles that contribute to a specific level of risk, and the benefits of fitting basic ember protection materials in areas at risk from bushfire |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3900 | 12 - EM agency and authority | That agencies integrate condition information into their asset management decision-making practices and use it as the basis for validating asset valuations and depreciation calculations. |
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3917 | 12 - EM agency and authority | That DPI improves monitoring and surveillance of high priority threats and improves the quality of information provided to the Commonwealth. |
REC112-3915 | 12 - EM agency and authority | That DPI makes arrangements to use contract labour for fruit fly trap monitoring and surveillance before the predicted fruit fly outbreak season. |
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |
REC112-3914 | 12 - EM agency and authority | That DPI develops a consistent approach to recording and enforcing breaches of the certification and verification system. |
REC112-3927 | 6 - Insurance and legal liability | That PSB and PIRVIC review their service agreement to ensure that PIRVIC is compensated for its costs in providing PSB with the specified level of service. |
REC112-3909 | 12 - EM agency and authority | That PSB’s enforcement procedures are consistent with those of the rest of the department. |
REC112-3923 | 12 - EM agency and authority | That DPI negotiates access, as and when required, to an AQIS PC4- accredited laboratory. |
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |