REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3273 | 26 - Research | Collate data and research the impact of bushfires upon communities, firefighters and animals (both native and domestic) to identify appropriate medium and long-term welfare and support requirements. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3267 | 16 - Training and behaviour | Invest in fireground leadership and incident management training for CFS, SES and MFS personnel to improve safety on the fireground. Invest in greater technological interoperability such as AVL, Thermal Imagery, Burnover Protection Systems (BOPS), lightning tracking and appropriate vehicle fleets for bushfire conditions including at the peri-urban interface. |
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1540 | 16 - Training and behaviour | Commanding Officer Defence Explosive Ordnance Training School, assisted by Joint Logistics Command Regional Explosive Ordnance Serices staff, conduct explosive ordnance accounting training for all instructional staff as a matter of priority and that such training be conducted for Defence Explosive Ordnance Training School staff on an annual basis. |
REC257-1536 | 16 - Training and behaviour | The Australian defence Force Explosive Ordnance Disposal course be reviewed by Manager Joint Training - Air Force, to ensure the assessments meet the learning outcomes specificed in the relevant Training Management Package. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3016 | 37 - Funding | ESWG recommends investigation of options to fund NGERAC’s on-going activities including through AEMO’s funding model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1775 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to identify the effects of continuous cropping, minimum tillage, direct drilling seeding practices and of the retention of cropping stubble, in respect of bushfire risk and prevention. |
REC153-1793 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the need to deliver to the Deputy State Coordinator timely, accurate and relevant information pertaining to an ongoing fire incident. |
REC153-1798 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1792 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the duties and responsibilities attaching to that position insofar as they apply to an ongoing fire incident, and in particular to recognise the need to conduct a risk assessment in relation to an incident and the need to scrutinise, evaluate and validate the strategies and Incident Action Plans of Incident Management Teams. |
REC153-1797 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1779 | 4 - Fire season preparation | That the South Australian Farmers’ Federation encourage its members and constituents to keep and maintain on rural land in proper working order machinery that is capable of removing, modifying or reducing cropping stubble at short notice in order to minimise or mitigate bushfire risk. |
REC153-1796 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in risk assessment. |
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
REC153-1795 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in risk assessment. |
REC153-1776 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to establish means by which risk of bushfires, as created by continuous cropping, minimum tillage, direct drilling seeding practices and the retention of cropping stubble across the landscape, can be minimised. |
REC153-1794 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of all Incident Management Team members, in particular but not limited to the Incident Controller and Planning Officer, of the need to conduct a full risk assessment that not only addresses operational risk, but the risk posed to the general public by an existing incident and at all times to consider and identify the ‘worst case scenario’ outcome. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC118-3642 | 26 - Research | Establish a Regional Centre of Excellence for Tsunamis to focus Australian and international science/research and collaboration on the challenge of understanding tsunamis and mitigating their consequences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2113 | 26 - Research | The Working Group recommends support for ongoing research into natural hazard risks and an improved understanding of emergency management capability. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2106 | 16 - Training and behaviour | The Working Group recommends that appropriate building/surveyor peak bodies be identified, and that discussions be held between the emergency management sector and those peak bodies at State/Territory and national level with a view to: |
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |