Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2388 | 15 - Inter-service cooperation | TFS, PWS and STT should establish a State Air Desk, to be staffed by specialist staff year-round, with responsibility for managing both preparatory and contractual issues out of season as well as aircraft management when fires or other emergency events are occurring. |
REC301-2386 | 15 - Inter-service cooperation | TFS, PWS and STT should work with government and each other to continue to pursue a whole-of-state fuel management and burning program that encompasses all land tenures, meets the range of outcomes required by the state (township protection, risk reduction and landscape-scale burns) and is inclusive of private landholders and local communities as well as all fire agencies. |
REC301-2383 | 15 - Inter-service cooperation | Tasmanian Fire Service (TFS), Tasmanian Parks and Wildlife Service (PWS) and Sustainable Timber Tasmania (STT) initiate a discussion among their Australasian peers about good practice around managing new fire starts in remote terrain, to include issues around identification, predictive analysis, risk management and suppression activities. The outcome should be a document which allows for benchmarking to accepted good practice across Australasia, from which Tasmanian fire agencies can develop protocols against which the management of future events can be tested. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
REC297-1254 | 13 - Mapping and data quality | That Government: |
REC297-1267 | 8 - Communications and warnings | That emergency management authorities react with heightened awareness and action when BoM issues flood watches and related warnings. |
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1266 | 8 - Communications and warnings | That Government supports the anticipated SES State Flood Warning proposals aimed at improving public warnings and communication, and that the proposed warning system is consistent with the National Frameworks. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
REC291-1244 | 11 - Evacuation and shelters | The Department of Fire and Emergency Services to work with the Department of Planning and Local Governments to adopt a policy which enables Local Governments to identify, register and communicate, ‘Places of Bushfire Last Resort’ in settlements and townsites where the life risk from bushfire is very high or greater. |
REC291-1243 | 8 - Communications and warnings | The Department of Fire and Emergency Services to investigate and adopt a system that will allow the public to opt in, monitor and receive, through a ‘push mechanism’, bushfire and other emergency warnings, maps and information using a wide variety of devices including personal hand held smart devices. |
REC291-1242 | 15 - Inter-service cooperation | The Departments of Fire and Emergency Services and Parks and Wildlife to investigate and adopt an emergency services resource management system that will enable the registration, tasking, tracking, management and coordination of emergency management personnel, vehicles, plant and aircraft. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1180 | 15 - Inter-service cooperation | The Tasmanian fire agencies consider the development of fire operational guidelines to avoid long-term environmental impacts such as: • • • strategies and tactics that will minimise the impact of fire management activities conditions under which earthmoving equipment and fire chemicals may be used information on seasonal conditions and the times of year when various strategies and tactics should be applied, and fuel management strategies. |
REC287-1179 | 15 - Inter-service cooperation | The Tasmanian fire agencies develop a joint multi-agency Fire Preparedness Matrix to guide decision-making in response to severe fire weather conditions or capacity issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0920 | 8 - Communications and warnings | That Tasmania Fire Service reviews its approach to communicating with communities threatened by bushfire and consider the matters referred to in this Report. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0890 | 11 - Evacuation and shelters | That decisions to open Community Fire Refuges and evacuation centres be coordinated with Tasmania Police. |
REC247-0946 | 20 - Role of police | That Tasmania Police establishes a section within its structure with responsibility for developing and maintaining contemporary expertise in emergency management, progressing innovation, assisting organisational change initiatives and supporting its responsibilities in state emergency management arrangements. |
REC247-0849 | 26 - Research | That Tasmania Fire Service supports the relevant authorities to continue developing methodologies to forecast and simulate fire risk. |
REC247-0867 | 7 - Inter-agency communication | That Tasmania Fire Service reviews the communication systems used for all emergency management operations, ensures operators are qualified, and ensures there is appropriate accountability. |
REC247-0900 | 8 - Communications and warnings | That a public information plan be developed as a part of the State Special Emergency Plan–Recovery, for implementation in the immediate recovery phase. |
REC247-0855 | 17 - Assets and technology | That a structure and facilities be established for the State Controller or other person managing multi-agency response and recovery operations. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0860 | 13 - Mapping and data quality | That Tasmania Fire Service establishes suitable systems and practices for recording fire management objectives and tactics. |
REC247-0889 | 11 - Evacuation and shelters | That Tasmania Police be identified as the lead agency on evacuations. |
REC247-0919 | 8 - Communications and warnings | That Tasmania Fire Service and Tasmania Police review their use of modern forms of communication with the community, including social media, and commit resources to fully use this capability where appropriate. |
REC247-0945 | 20 - Role of police | That Tasmania Police conducts a review to ensure emergency management is treated as a priority and a core function throughout the organisation, including the development of contemporary capabilities, and is supported by an appropriate culture. |
REC247-0866 | 26 - Research | That fire agencies continue to develop their predictive modelling capability for use in actively managing fires. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0854 | 15 - Inter-service cooperation | That in multi-agency response and recovery operations, arrangements be made so it is unambiguous who is in charge of these operations. |
REC247-0880 | 17 - Assets and technology | That bushfire agencies develop, implement and maintain air operations procedures. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0859 | 7 - Inter-agency communication | That police and other emergency services examine options for achieving radio interoperability between them in the absence of an integrated radio system. |
REC247-0888 | 11 - Evacuation and shelters | That arrangements are made and appropriate pre-planning occurs to effectively implement the policy on evacuation. |
REC247-0918 | 8 - Communications and warnings | That the State Emergency Management Committee makes arrangements to actively manage the use of social media in the community during an emergency, to avoid negative consequences for emergency operations. |
REC247-0942 | 1 - Land-use and building regs | That the Government makes land use planning and building construction to prevent and mitigate bushfire risk a high priority and establishes a means to progress improvements in this area, such as a designated body or group, as soon as possible. |
REC247-0865 | 34 - Local knowledge | That Tasmania Fire Service reviews its position on using local experienced officers on the fire ground in the command model in a structured and systemic way. |
REC247-0894 | 17 - Assets and technology | That the police and other emergency service organisations discuss their resource issues for emergency operations with the Government. |
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
REC247-0879 | 17 - Assets and technology | That bushfire agencies develop procedures for the automatic activation of aircraft to fires at pre-determined trigger points on high fire risk days. |
REC247-0905 | 8 - Communications and warnings | That the Government consider whether it should discuss options for greater mobile phone coverage and redundancy in areas of high risk in emergency situations where there are presently telecommunications limits. |
REC247-0858 | 7 - Inter-agency communication | That all agencies and the Government support moving to an integrated communications technology for police and the emergency services. |
REC247-0887 | 11 - Evacuation and shelters | That qualifying the evacuation authority in section 47 of the Fire Service Act 1979 be considered — by exempting those people with a pecuniary interest in a property from a directed evacuation where it is reasonable for them to remain. |
REC247-0917 | 8 - Communications and warnings | That the State Emergency Management Committee makes timely decisions and resource commitments on the appropriate use of social media in emergency management. |
REC247-0922 | 8 - Communications and warnings | That Tasmania Fire Service develops a research base from which to inform the design of communication campaigns for communities threatened by bushfire. |
REC247-0863 | 34 - Local knowledge | That Tasmania Fire Service considers measures to bring local knowledge into Incident Management Team operations. |
REC247-0893 | 17 - Assets and technology | That further options to appropriately supplement the resources available for emergency management operations be examined. |
REC247-0948 | 15 - Inter-service cooperation | That the Department of Justice conduct an independent review to develop a suitable model for integrated and interoperable emergency management arrangements in Tasmania. |
REC247-0851 | 13 - Mapping and data quality | That if a sound business case is developed, the Emergency Information Management and Sharing Project be supported. |
REC247-0878 | 17 - Assets and technology | That bushfire agencies evaluate the use and effectiveness of fixed wing water bombing aircraft. |
REC247-0902 | 7 - Inter-agency communication | That evacuation centres and other centres have a standard operating procedure for communications. |
REC247-0857 | 2 - Emergency powers | That the Tasmania Emergency Management Plan enable, and all organisations with a role in emergency management activate, emergency plans at lower threshold events to practice their arrangements and achieve a ‘hot start’ in escalating events. |
REC247-0886 | 11 - Evacuation and shelters | That a state-level policy on evacuations be developed in the emergency management plans, including specific requirements for vulnerable people and guidelines for its implementation. |
REC247-0916 | 8 - Communications and warnings | That Tasmania Fire Service ensures that the priority on warning communities at risk of active bushfires is not confined to when bushfires are burning out of control. |
REC247-0921 | 26 - Research | That Tasmania Fire Service promotes a structured approach to research across Australia, to provide a shared understanding and the capacity to benchmark and judge performance. |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0892 | 17 - Assets and technology | That a review be conducted of the resource capacity and capability to provide effective and efficient emergency operations, including approved improvements. |
REC247-0947 | 20 - Role of police | That Tasmania Police develops and implements a program for examining emergency management arrangements and facilities in Australia. |
REC247-0850 | 13 - Mapping and data quality | That police and other emergency service agencies establish and maintain effective recording systems for emergency operations. |
REC247-0875 | 34 - Local knowledge | That Tasmania Fire Service reviews its integration of rural local knowledge and volunteer brigades into fire operations, develops and maintains appropriate strategies, and aims to be a best-practice fire service in this regard. |
REC247-0901 | 11 - Evacuation and shelters | That evacuation centres and other centres have plans and arrangements for electrical power redundancy. |
REC247-0856 | 2 - Emergency powers | That the Government reconsider the current position on emergency declarations in the Emergency Management Act 2006 and the Act is amended to provide: • a graduated scale of emergency declarations; • the ability to make a declaration when an emergency has occurred, is occurring or is about to occur; • the ability for the State Controller (or whatever the person in overall control of response and recovery operations is called) to make one or more declarations; • a declaration to enable access to all emergency powers. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0915 | 8 - Communications and warnings | That Tasmania Fire Service actively uses predictive modelling to design emergency communications for communities threatened by bushfire, unless there is a compelling reason for not doing so. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2748 | 20 - Role of police | That the Queensland Police Service considers adopting the broader use of ANPR in line with other Australian jurisdictions in consultation with the Privacy Commissioner. |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2762 | 15 - Inter-service cooperation | That the Chief Executive Officer Portfolio Business in consultation with the Police Commissioner and the Commissioner Fire & Emergency Services should provide the direction for future information and communication technology strategies and acquisitions. |
REC239-2703 | 15 - Inter-service cooperation | That the protocols developed by the Queensland Police Service and SES for operations define the respective roles and responsibilities as well as recognise the varying capabilities of SES units across the State. |
REC239-2747 | 20 - Role of police | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative automated number plate recognition models should form part of the design architecture. |
REC239-2761 | 15 - Inter-service cooperation | That systems development in the Queensland Police Service capitalises on the advances made by the Queensland Fire and Rescue Service in recent years. |
REC239-2694 | 15 - Inter-service cooperation | That Queensland enters into a similar arrangement with Bureau of Meteorology to have an experienced forecaster seconded to Kedron State Disaster Coordination Centre for at least the duration of fire and storm seasons. |
REC239-2726 | 20 - Role of police | That the Queensland Fire and Rescue Service enters into discussion with the Queensland Police Service regarding the possibility for the Queensland Police Service to assist with prosecutions that may arise out of fire safety matters. |
REC239-2757 | 20 - Role of police | That the Queensland Police Service executive team reassesses its preparedness to collaborate with other agencies to deliver a whole of Government approach to delivering community safety. |
REC239-2690 | 8 - Communications and warnings | That the Chief Executive Officer Portfolio Business and Commissioners establish a high level working group with the ABC and commercial media to identify and implement an improved information flow to the community on disasters. |
REC239-2781 | 34 - Local knowledge | That the current provisions enabling there to be a Ministerial Direction be maintained and actioned as the Minister sees fit. |
REC239-2723 | 1 - Land-use and building regs | That the Queensland Fire and Rescue Service examine alternative contractual arrangements with building owners which would reduce the need for physical attendance at alarm activations. |
REC239-2752 | 20 - Role of police | That the roll-out of the Queensland Police Service digital technology should take into consideration adopting and facilitating new processes including the police response to domestic violence. |
REC239-2689 | 20 - Role of police | That, where appropriate, the Commissioner of Police appoints appropriately trained and experienced public service officers to appropriate roles in the disaster management system to support District Disaster Coordinators in their vital roles. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2750 | 20 - Role of police | That the Queensland Police Service: |
REC239-2667 | 15 - Inter-service cooperation | That Queensland Corrective Service, the Queensland Police Service and Queensland Health should work together to develop a position that enables prisoners to have timely access to their prescribed medication despite travel between facilities and without the need for costly re-prescription. |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0519 | 34 - Local knowledge | The Department of Environment and Conservation review its practices and procedures in the undertaking of prescribed burns so as to fully utilise the skills available to it in a seamless way including but not limited to: · volunteer bushfire brigades, especially in regard to use as a source of local advice; and · staff of the Fire and Emergency Services Authority of Western Australia. |
REC223-0517 | 26 - Research | The Department of Environment and Conservation be supported to conduct further research into the fuel management of coastal heath in the south west of Western Australia exploring alternatives to burning as well as best practice for burning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0628 | 1 - Land-use and building regs | The Queensland Government should draft model flood planning controls, using a similar format and structure to that in the Queensland Planning Provisions, that councils can adapt for local conditions. The Queensland Government should require these controls to be reflected in new planning schemes. This may be achieved by including the controls in either: • a state planning policy dealing with flood, with an accompanying amendment to the Sustainable Planning Act 2009, or • the Queensland Planning Provisions. The Queensland Government should consult councils to determine which of the two state planning instruments is the more appropriate to include the model flood planning controls. |
REC210-0649 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters. |
REC210-0675 | 1 - Land-use and building regs | The Queensland Government should consider including in the criteria in the Queensland Plumbing and Wastewater Code a requirement that the risk of leakage from private on-site sewerage systems during floods be minimised. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0612 | 1 - Land-use and building regs | For non-urban areas or areas where limited development is expected to occur councils should consider, on a risk basis, what level of information about flood risk is required for the area, and undertake the highest ranked of the following options which is appropriate to that need and within the capacities (financial and technical) of the council: a. a map showing ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. a map showing the extent of floods of a range of likelihoods (at least three) c. a flood map based on historic flood levels that have been subjected to a flood frequency analysis to estimate the annual exceedance probability of the selected historical flood d. a historic flood map without flood frequency analysis e. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay as a way to determine those areas for which further flood studies are required, or f. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay (preferably refined using local flood information) as a trigger for development assessment. |
REC210-0635 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to expressly provide either a power to remake or a power to extend a temporary local planning instrument containing interim flood regulation for a further limited period. The power to remake or extend should: a. permit the modification of the temporary local planning instrument to the extent required to ensure its provisions remain relevant, having regard to any requirement that may have been introduced or any information that may have become available while the original temporary local planning instrument was in force b. be contingent on the Minister’s being satisfied that the circumstances listed in section 105 of the Sustainable Planning Act continue to exist and that there are proper grounds for the failure to make a permanent scheme amendment while the original temporary local planning instrument was in force. |
REC210-0658 | 1 - Land-use and building regs | The Queensland Government should consult with councils to determine an effective method for the regulation of the construction of levees in Queensland. In particular, the Queensland Government should consider: • requiring a development permit for the construction of a levee by designating levees as assessable development in the Sustainable Planning Regulation 2009, or • requiring, by way of a state planning policy or mandatory provision in the Queensland Planning Provisions, that councils nominate the construction of a levee as assessable development in their planning schemes. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0622 | 1 - Land-use and building regs | If, as part of a state interest review process, the Department of Local Government and Planning decides that no condition should be imposed requiring a council’s proposed planning scheme to incorporate the effect of the Department of Community Safety’s comments about State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide, it should advise the Department of Community Safety of the reasons for its decision. |
REC210-0640 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0694 | 1 - Land-use and building regs | The Queensland Government should consider whether there should be a legislative requirement that customer dedicated assets be built at or above the applicable defined flood level and if so, the Queensland Government should consider which legislation should contain such a requirement. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0627 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to require that consideration be given to the risk of flooding in the preparation or revision of a regional plan. |
REC210-0647 | 1 - Land-use and building regs | The Department of Environment and Resource Management should ensure that, when applications for a material change of use for an environmentally relevant activity are approved by the department, the details of those activities, including their nature and location, are provided to the council within whose area the activity will be conducted. |
REC210-0674 | 1 - Land-use and building regs | The Queensland Government should consider amending the ‘Limitation’ section of the proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, to allow for the possible application of ‘acceptable solution A1’ to a building located on a lot if: • it is reasonable to expect the part of the lot on which the building work is proposed to be subjected to a maximum velocity of less than 1.5 metres per second, or • the part of the lot on which the building work is proposed is located in an inactive flow or backwater area. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0611 | 1 - Land-use and building regs | For urban areas or areas where development is expected to occur: a. councils with the requisite resources should develop a flood map which shows ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. councils without the requisite resources to produce a flood behaviour map should develop a flood map which shows the extent of floods of a range of likelihoods (at least three). |
REC210-0634 | 1 - Land-use and building regs | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include in their planning schemes a planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as a part of the development application, or • for development proposed on land where potential for flooding is unknown requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information to allow an assessment of the flood risk. |
REC210-0657 | 1 - Land-use and building regs | Levees should be regulated. |
REC210-0682 | 1 - Land-use and building regs | The Department of Environment and Resource Management should review the Queensland Urban Drainage Manual to determine whether it requires updating or improvement, in particular, to reflect the current law and to take into account insights gained from the 2010/2011 floods. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0621 | 1 - Land-use and building regs | The Queensland Government should: a. narrow the definition of ‘development commitment’ in State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide to ensure more development applications are assessed for compatibility with flood, and b. investigate whether the compensation provisions of the Sustainable Planning Act 2009 act as a deterrent to the inclusion of flood controls in a planning scheme and consider whether they ought be amended. |
REC210-0639 | 1 - Land-use and building regs | The Queensland Government should consider extending the application of a state planning policy dealing with flood to the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood. |
REC210-0662 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0691 | 1 - Land-use and building regs | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0626 | 1 - Land-use and building regs | Councils should consider using the limited development (constrained land) zone in their planning schemes for areas that have a very high flood risk. |
REC210-0646 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend the template assessment report used to assess applications for a material change of use for environmentally relevant activities so that it prompts departmental officers to give specific consideration, as part of the assessment process, to the risk of flooding at the site where the activity is proposed to occur. |
REC210-0673 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirements about utilities and sanitary drains (Performance Requirement P2 and P3) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0633 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as part of the development application, or • for development proposed on land where the potential for flooding is unknown, requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information, to allow an assessment of the flood risk. |
REC210-0656 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Regulation 2009 so that operational work or plumbing or drainage work (including maintenance and repair work) carried out by or on behalf of a public sector entity authorised under a state law to carry out the work is not exempt development under the Sustainable Planning Act 2009 if the development has the potential to reduce floodplain storage. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0617 | 1 - Land-use and building regs | The Queensland Government should consider implementing a mechanism by which prospective purchasers of property are alerted to the issue of flood risk. To that end, the Queensland Government should consider consulting the Real Estate Institute of Queensland and the Law Society of Queensland as to the appropriateness of amending standard contract conditions so as to include a ‘subject to flood search’ condition, or other means of achieving the same objective. |
REC210-0638 | 1 - Land-use and building regs | The Coordinator-General should amend the guideline for preparing an ‘initial advice statement’ for a significant project under the State Development and Public Works Organisation Act 1971 so that it specifically requires an applicant to consider and provide information about the project’s flood risk. |
REC210-0661 | 1 - Land-use and building regs | There should be a common set of considerations in the decision whether to approve an application to build a levee, including: • the impacts of the proposed levee on the catchment as a whole • the benefits of the proposed levee to the individual or entity applying to build the levee and to any nearby community as a whole • any adverse impacts on other landholders, including the risk of levee failure • the implications of the proposed levee for land planning and emergency management procedures • whether any structural, land planning or emergency management measures can be taken to mitigate the adverse impacts of the proposed levee. |
REC210-0690 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0625 | 1 - Land-use and building regs | The Queensland Government should change Temporary State Planning Policy 2/11: Planning for stronger more resilient floodplains to remove the possibility of councils’ using the interim floodplain assessment overlay mapping and Model Code as part of a permanent amendment to their existing planning scheme or as part of a new planning scheme. |
REC210-0645 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend its information sheet about applications for a material change of use for environmentally relevant activities so that applicants are prompted to include information (if any) about the risk of flooding at the site where the activity is proposed to occur. |
REC210-0672 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirement relating to building design and construction (Performance Requirement P1) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot, and • either: – declared a velocity to be the expected maximum velocity of flood water for the area in which the lot is located, or – designated the area in which the lot is located an inactive flow or backwater area. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0631 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0654 | 1 - Land-use and building regs | The Queensland Government should consider drafting assessment criteria to be included in the model flood planning controls which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the applicable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms) • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0677 | 1 - Land-use and building regs | Authorities responsible for the management of sewerage infrastructure should conduct a review of their existing infrastructure to identify electrical infrastructure that may be vulnerable to inundation and perform risk and cost/benefit assessments to determine if it should be relocated to a higher level. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0616 | 1 - Land-use and building regs | Councils that do not currently do so should consider offering an online database which allows the public to conduct a search on a parcel of land to find development approvals relevant to that parcel of land. |
REC210-0637 | 1 - Land-use and building regs | The Queensland Government should consider amending the Urban Land Development Authority Act 2007, the South Bank Corporation Act 1989, the State Development and Public Works Organisation Act 1971 insofar as it governs state development areas, and other legislation which establishes alternative planning systems that operate independently of the Sustainable Planning Act 2009, to require that: • any planning scheme, interim or otherwise, appropriately reflects any state planning policy with respect to flood • flood risk be considered in the assessment of any development application. |
REC210-0660 | 1 - Land-use and building regs | There should be a consistent process for the determination of applications to build levees. That process should include: • consulting landholders who may be affected by the proposed levee • obtaining or commissioning appropriate hydrological and hydraulic studies to assess the impacts of the proposed levee. |
REC210-0685 | 1 - Land-use and building regs | In assessing and determining development applications for material change of use in areas susceptible to flood, councils should consider whether the new developments locate essential services infrastructure above basement level, or, alternatively, whether essential services infrastructure located at basement level can be constructed so that it can continue to function during a flood. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0624 | 1 - Land-use and building regs | The Queensland Government should ensure that the circumstances in which the Department of Community Safety is to consult the Department of Environment and Resource Management about a planning scheme’s flood modelling and flood mapping are clear. |
REC210-0644 | 1 - Land-use and building regs | The Queensland Government should ensure that the criteria under the Environmental Protection Act 1994 that apply to the assessment of development applications for material change of use for environmentally relevant activities include consideration of the risk of flooding at the site on which the activity is proposed to occur. |
REC210-0666 | 1 - Land-use and building regs | The Queensland Government should draft a model planning scheme policy to be included in the model flood planning controls that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0629 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a requirement that councils have a flood overlay map in their planning schemes. The map should identify the areas of the council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0652 | 1 - Land-use and building regs | The Queensland Government should review the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003 to consider whether the design and construction standards should be made more stringent than the existing standards. |
REC210-0676 | 1 - Land-use and building regs | Authorities responsible for the construction of sewerage infrastructure should, when embarking on new works, undertake risk and cost/benefit assessments to determine the level at which electrical infrastructure that may be vulnerable to inundation should be placed. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0613 | 1 - Land-use and building regs | Councils should ensure that areas for which there has been no assessment of the likelihood of flooding are indicated on a map and that, as part of the development assessment process for these, there is at least some enquiry into whether a site proposed for development could be subject to flooding. |
REC210-0636 | 1 - Land-use and building regs | The Queensland Government should consider allowing councils to amend a planning scheme to update existing flood mapping information by way of the minor amendment process, provided that adequate public consultation has occurred. |
REC210-0659 | 1 - Land-use and building regs | The Queensland Government should consult with councils to formulate a definition of ‘levee’ to identify what should be regulated. |
REC210-0684 | 1 - Land-use and building regs | Councils should consider amending their planning schemes to include provisions directed to consideration of the flood resilience of basements as a factor in determining the appropriateness of a material change of use. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0623 | 1 - Land-use and building regs | The Department of Community Safety should put in place administrative arrangements which ensure it can readily ascertain whether its comments are being reflected in council planning schemes. If the Department of Community Safety becomes aware that its comments are not being adequately addressed, it should take steps to follow this up with the Department of Local Government and Planning. |
REC210-0642 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require the impact of flood on commercial property to be minimised. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0697 | 1 - Land-use and building regs | Queensland Rail and QR National should continue to investigate opportunities for increasing the flood resilience of their networks, including raising the height of critical equipment. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0250 | 8 - Communications and warnings | Initial StateAlert messages should provide timely broad advice to a wide audience authorised by the SDD, while subsequent messages may provide more detail. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
REC201-0260 | 15 - Inter-service cooperation | There are a range of opportunities identified from reviewing the three fires that will improve coordination between FESA and DEC, requiring limited resources, potentially generating some efficiencies and reflecting a joint, tenure blind approach to fire management in WA. The MIR acknowledges the progress made through the IBMC in these matters and notes these measures will require ongoing strong leadership. These include: · Clarification and consistent application of the Zone 2 and 2A mobilisation protocols; · Duplicating available information on websites; · Establishing a single State air desk and cross-utilising Air Attack Supervisors; · Completing common training for the conduct of public meetings;· Coordinating IMT training and exercises; · Operating joint IMT‘s during interface fires; FESA utilising the DEC mobile ICC when suitable ICPs are not available; · FESA engaging in daily weather teleconferences with DEC; Engaging a permanent BoM officer to support a common FESA and DEC SOC; · Developing a common ‗Tool Box‘ of forms and operational procedures for fire response; · Developing common jurisdictional arrangements to accommodate interstate support; · Developing a joint FESA/DEC SOC at the new (FESA) Emergency Services facility at Cockburn; · Adopting common and transparent Level 3 IC accreditation · Using a single mapping capability across both agencies and · Using common naming conventions for fires. |
REC201-0252 | 7 - Inter-agency communication | FESA must actively manage the transition to WAERN and provide alternative means for regional crews to communicate when in areas where WAERN is not operated. |
REC201-0259 | 11 - Evacuation and shelters | FESA seek legal and policing advice regarding the policy to leave residents who chose not to evacuate in a declared ‗dangerous area‘ after a bushfire. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0370 | 8 - Communications and warnings | The Fire and Emergency Services Authority and the ABC commence a thorough review of emergency warning messages. This review should give consideration to: The content, structure and presentation of emergency warning messages Media access to the Incident Management Team and State Operations Centre. This review should be expanded to include other media organisations should they demonstrate a willingness and capacity to contribute. 20 |
REC200-1713 | 7 - Inter-agency communication | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0359 | 13 - Mapping and data quality | The State Government ensure that the continued development of the Fire and Emergency Service Authority’s Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1697 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-1711 | 8 - Communications and warnings | FESA develop in partnership with other emergency service agencies develop a 'one source: one message' multi layered system similar to that recommended by the Victoria Bushfire royal Commission. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-0358 | 13 - Mapping and data quality | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. The system should enable public access to allow members of the community to access information about the fuel load in a given locality. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1690 | 8 - Communications and warnings | The Fire and Emergency Services Authority work in partnership with Main Roads Western Australia and local governments to develop and implement a comprehensive strategy for the use of mobile variable message boards to alert the community to the declaration of a total fire ban and what it means. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-1710 | 8 - Communications and warnings | The Fire and Emergency Services Authority and the ABC commence a thorough review of emergency warning messages. This review should give consideration to: |
REC200-0338 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0374 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-0357 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-0386 | 15 - Inter-service cooperation | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. This should include field exercises which test: Evacuation centres Critical infrastructure (including at the local level) Traffic management, including road blocks. Consideration should also be given to involving the community in exercising (see Recommendation 7) and using prescribed burns as exercises (see Recommendation 14) More detailed planning for exercises should be included in a revised WESTPLANBUSHFIRE to be endorsed by the State Emergency Management Committee. |
REC200-1689 | 8 - Communications and warnings | The Fire and Emergency Services Authority consider alternative wording to Total Fire Ban that ensures people gain a more complete understanding of what actions are prohibited. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-1708 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0372 | 7 - Inter-agency communication | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0355 | 13 - Mapping and data quality | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-0381 | 2 - Emergency powers | The State Government amend section 50 of the Emergency Management Act 2005 to allow the Chair of the State Emergency Coordination Group to declare an emergency situation. |
REC200-1680 | 15 - Inter-service cooperation | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0371 | 8 - Communications and warnings | FESA develop in partnership with other emergency service agencies a ‘one source: one message’ multi layered system similar to that recommended by the Victoria Bushfire royal Commission. |
REC200-1714 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-0352 | 13 - Mapping and data quality | The Fire and Emergency Services Authority and local governments ensure that the ability to: measure and map fuel loads maintain fuel load databases draw up prescriptions for, and oversee controlled burns are included as key competencies in any future recruitment of Chief Bushfire Control Officers and Community and Emergency Services Managers. |
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-1679 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
REC183-0116 | 15 - Inter-service cooperation | Triggers and a process for transfer of command and control from DEC to FESA should be developed and documented. |
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0118 | 15 - Inter-service cooperation | A Memorandum of Understanding signed by the Chief Executives of DEC and FESA would be a valuable statement of joint commitment between the two agencies. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
REC183-0117 | 15 - Inter-service cooperation | The Interagency Bushfire Management Committee and its sub-committees are the logical central platform for developing and strengthening future joint bushfire strategies and common systems of work between bushfire management agencies in Western Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0124 | 15 - Inter-service cooperation | FESA and DEC take a whole of capability approach to joint operations, including developing joint doctrine that provides a common and articulated understanding of roles and responsibilities, resources and capabilities |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
REC182-0129 | 15 - Inter-service cooperation | FESA maintains inter-agency relationships and arrangements, and develops formalised arrangements across the entire emergency management cycle for joint activities such as training, exercises and procedure development. |
REC182-0125 | 15 - Inter-service cooperation | FESA, in partnership with other agencies and the community, develops Western Australia’s urban interface fire fighting capability and capacity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0086 | 2 - Emergency powers | Suggested escalation trigger points be discussed with District Disaster Coordinators and Local Disaster Coordinators, and if considered practical and useful, be incorporated in Local, District and State Disaster Management Plans. |
REC165-0085 | 20 - Role of police | The Commissioner of Police, through a dedicated Assistant Commissioner (supported by a cohort of Assistant Commissioners to ensure adequate coverage), be assigned responsibility for overall control of each natural Disaster Management event in Queensland as the preferred arrangement. |
REC165-0096 | 15 - Inter-service cooperation | The Department of Community Safety and Councils develop MOUs to reflect the genuine partnership that exists in present arrangements including an emphasis on the use of the agreed State disaster arrangements to task and deploy SES units following State/Local consultation. |
REC165-0081 | 2 - Emergency powers | District and State levels utilise the current Act to make pre-emptive declarations of a disaster event (likely disasters) so as to be proactive in leading and controlling disaster events. All levels of the system should immediately notify other levels if they activate the Disaster Management arrangements. The Public Safety Preservation Act 1986 be amended to provide powers for Police Officers to provide an immediate response in the event of a rapid onset disaster event such as a landslide. |
REC165-0095 | 11 - Evacuation and shelters | Planning and consultation be undertaken by EMQ with all levels of the Disaster Management system to ensure that necessary risk-based disaster evacuation plans are prepared at Local, District and State levels, supported by necessary community education and preparedness programs. |
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
REC165-0087 | 8 - Communications and warnings | The SDMG commission the Department of Community Safety and seek the necessary funding to develop and enhance the Statewide Disaster Management information and communications system building on alternatives already in place and in consultation with all levels of Government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
REC019-4151 | 26 - Research | The Forests Department carry out more research into both the technical and practical side of fire control as a necessary accompaniment to the expenditure of money on other forest works and that forest fire control officers be sent overseas at intervals to gain information regarding the latest developments in this work. |
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
REC019-4156 | 26 - Research | A fire control research advisory committee be formed to co-operate with the Forests Department in carrying out scientific research into fire control. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |