Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2383 | 15 - Inter-service cooperation | Tasmanian Fire Service (TFS), Tasmanian Parks and Wildlife Service (PWS) and Sustainable Timber Tasmania (STT) initiate a discussion among their Australasian peers about good practice around managing new fire starts in remote terrain, to include issues around identification, predictive analysis, risk management and suppression activities. The outcome should be a document which allows for benchmarking to accepted good practice across Australasia, from which Tasmanian fire agencies can develop protocols against which the management of future events can be tested. |
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
REC301-2388 | 15 - Inter-service cooperation | TFS, PWS and STT should establish a State Air Desk, to be staffed by specialist staff year-round, with responsibility for managing both preparatory and contractual issues out of season as well as aircraft management when fires or other emergency events are occurring. |
REC301-2386 | 15 - Inter-service cooperation | TFS, PWS and STT should work with government and each other to continue to pursue a whole-of-state fuel management and burning program that encompasses all land tenures, meets the range of outcomes required by the state (township protection, risk reduction and landscape-scale burns) and is inclusive of private landholders and local communities as well as all fire agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
REC297-1254 | 13 - Mapping and data quality | That Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1180 | 15 - Inter-service cooperation | The Tasmanian fire agencies consider the development of fire operational guidelines to avoid long-term environmental impacts such as: • • • strategies and tactics that will minimise the impact of fire management activities conditions under which earthmoving equipment and fire chemicals may be used information on seasonal conditions and the times of year when various strategies and tactics should be applied, and fuel management strategies. |
REC287-1179 | 15 - Inter-service cooperation | The Tasmanian fire agencies develop a joint multi-agency Fire Preparedness Matrix to guide decision-making in response to severe fire weather conditions or capacity issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1131 | 15 - Inter-service cooperation | That the Emergency Management Australia’s ‘Arrangements for Interstate Assistance (Fire and Emergency Services)’ be applied to all future requests for assistance by the SACFS, SAMFS and SASES. |
REC273-1132 | 15 - Inter-service cooperation | Noting the implementation of Common Incident Command and Control System (CICCS) in SA that fire and emergency services together with police (including through AFAC and ANZPAA), continue to liaise regarding the development of a national incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0863 | 34 - Local knowledge | That Tasmania Fire Service considers measures to bring local knowledge into Incident Management Team operations. |
REC247-0860 | 13 - Mapping and data quality | That Tasmania Fire Service establishes suitable systems and practices for recording fire management objectives and tactics. |
REC247-0948 | 15 - Inter-service cooperation | That the Department of Justice conduct an independent review to develop a suitable model for integrated and interoperable emergency management arrangements in Tasmania. |
REC247-0854 | 15 - Inter-service cooperation | That in multi-agency response and recovery operations, arrangements be made so it is unambiguous who is in charge of these operations. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0851 | 13 - Mapping and data quality | That if a sound business case is developed, the Emergency Information Management and Sharing Project be supported. |
REC247-0875 | 34 - Local knowledge | That Tasmania Fire Service reviews its integration of rural local knowledge and volunteer brigades into fire operations, develops and maintains appropriate strategies, and aims to be a best-practice fire service in this regard. |
REC247-0850 | 13 - Mapping and data quality | That police and other emergency service agencies establish and maintain effective recording systems for emergency operations. |
REC247-0865 | 34 - Local knowledge | That Tasmania Fire Service reviews its position on using local experienced officers on the fire ground in the command model in a structured and systemic way. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |