REC317-4124 | 6 - Insurance and legal liability | In reviewing the Disaster Recovery Funding Arrangements, Australian, state and territory governments should examine the small disaster criterion, and financial thresholds generally. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4113 | 6 - Insurance and legal liability | The insurance industry, as represented by the Insurance Council of Australia, working with state and territory governments and other relevant stakeholders, should produce and communicate to consumers clear guidance on individual-level natural hazard risk mitigation actions insurers will recognise in setting insurance premiums. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4075 | 6 - Insurance and legal liability | The Australian Government should afford appropriate legal protections from civil and criminal liability to Australian Defence Force members when conducting activities under an authorisation to prepare for, respond to and recover from natural disasters. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3264 | 6 - Insurance and legal liability | Consider removing stamp duty from home insurance to encourage a wider section of the community to take out insurance. South Australian government agencies should share their risk modelling data with the Insurance Council of Australia. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2507 | 35 - Business and Industry in relation to industry | Developing, approving and implementing disaster recovery plans for all key business systems. |
REC313-2515 | 35 - Business and Industry in relation to industry | Conducting a risk assessment of disaster recovery plans for key business systems. |
REC313-2511 | 35 - Business and Industry in relation to industry | Scheduling disaster recovery tests for key business systems regularly, in line with their importance. |
REC313-2510 | 35 - Business and Industry in relation to industry | Defining recovery time objectives and recovery point objectives for key business systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1274 | 35 - Business and Industry in relation to industry | That relevant agencies, such as the Department of State Development, SA Police and emergency services, collaborate to establish an education campaign to encourage businesses in South Australia to develop Business Continuity Plans which, among other potential hazards such as flood and fire, also take into account the potential impact of an extended power outage. |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
REC273-1132 | 15 - Inter-service cooperation | Noting the implementation of Common Incident Command and Control System (CICCS) in SA that fire and emergency services together with police (including through AFAC and ANZPAA), continue to liaise regarding the development of a national incident management. |
REC273-1131 | 15 - Inter-service cooperation | That the Emergency Management Australia’s ‘Arrangements for Interstate Assistance (Fire and Emergency Services)’ be applied to all future requests for assistance by the SACFS, SAMFS and SASES. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2616 | 6 - Insurance and legal liability | That once the review of the Emergency Management Act has been finalised, any reference to the liability of councils should be mirrored in both the EM Act and the F&ES Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0843 | 6 - Insurance and legal liability | That the Government work with the Local Government Association to resolve questions of liability by volunteers who work for Councils, as raised with the Select Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2642 | 6 - Insurance and legal liability | That with regard to volunteer community safety and emergency service organisations that do not own land where their facilities exist: |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1595 | 35 - Business and Industry in relation to industry | Department of Broadband, Communications and the Digital Economy to work with the Trusted Information Sharing Network’s Communications Sector Group to develop general telecommunications continuity advice for businesses and individuals to assist in developing continuity plans. |
REC233-1601 | 35 - Business and Industry in relation to industry | Community service providers consider in their business continuity planning how they could assist with facilitating access to telecommunications services for the public during mass outages. |
REC233-1594 | 35 - Business and Industry in relation to industry | When businesses review their business continuity plans they should take into account the prospect of a major telecommunications outage that affects both mobile and fixed voice and data services. |
REC233-1600 | 35 - Business and Industry in relation to industry | Community service providers consider, in consultation with relevant government authorities, reviewing their current privacy practices concerning personal information about vulnerable persons to ensure they are able to appropriately share information during major disruptive incidents. |
REC233-1593 | 35 - Business and Industry in relation to industry | Telstra and other service providers to consider improving processes to assist customers with setting up temporary call diversions during future outages. |
REC233-1599 | 35 - Business and Industry in relation to industry | Providers of personal alert devices consider telecommunications outages in their service continuity plans and provide clear advice to their customers regarding their options during a telecommunications service outage. |
REC233-1591 | 35 - Business and Industry in relation to industry | While noting the importance of voice communications, telecommunications providers should consider as part of their mass outage business continuity planning, options for the provision of interim mobile broadband services for the community e.g. local wireless broadband access hubs (i.e. Wi-Fi). |
REC233-1598 | 35 - Business and Industry in relation to industry | Community service providers consider developing information and advice regarding telecommunications outages for clients managed remotely using telecommunication services, including personal alert devices. |
REC233-1597 | 35 - Business and Industry in relation to industry | Community service providers consider updating their business continuity plans to take into account the possibility of a major telecommunications outage involving both fixed and mobile voice and data services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2844 | 15 - Inter-service cooperation | The committee recommends that Australian governments specifically address issues of compatibility and capacity to facilitate the most effective interoperability of emergency service organisations and their key personnel, especially for fire services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2922 | 6 - Insurance and legal liability | That all home building insurance policies include flood cover. |
REC187-2938 | 6 - Insurance and legal liability | That for home building insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000. For properties with a value greater than $500,000 policyholders then pay the full cost of the portion of risk exceeding $500,000. |
REC187-2955 | 6 - Insurance and legal liability | That, in endorsing the Government proposal for a Key Facts Statement, the Key Facts Statement list replacement cover and all natural disaster events, identified as ‘standard cover’ in the Insurance Contracts Regulations 1985. That insurers issue a Key Facts Statement to policy holders with all new policies written and all policy renewals on an annual basis. |
REC187-2927 | 6 - Insurance and legal liability | The levels of the discounts and the phasing out periods be reviewed from time to time. |
REC187-2943 | 6 - Insurance and legal liability | That the Commonwealth Government guarantee payment of claims from the reinsurance pool by ensuring that, whenever a funding shortfall occurs in the pool through claims exceeding the funds held in the pool, the Commonwealth would meet the shortfall. |
REC187-2960 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the Code of Practice to impose a four month time limit (subject to exceptional circumstances) to make a determination as to liability and the nature of the loss or damage with respect to a claim. That, should a claimant not receive a determination within the four month period, the claim be automatically escalated to an internal dispute resolution complaint and the insurer notify the Code Compliance Committee of the breach of the Code. |
REC187-2932 | 6 - Insurance and legal liability | That all home contents insurance policies include flood cover. |
REC187-2949 | 6 - Insurance and legal liability | That all home, contents and home unit insurance policies cover the policyholder for storm surge, tsunami and landslide, where the storm surge, tsunami or landslide is the result of another event that is covered under the policy and regardless of whether the insured property directly suffers damage from the underlying insured event. |
REC187-2965 | 6 - Insurance and legal liability | That ASIC conduct a review of the General Insurance Code of Practice three years after the amendments recommended to the Code in this Review are implemented, in order to assess the effectiveness of the Code with a view to determining whether an ASIC Regulatory Guide for claims handling should then be introduced. |
REC187-2921 | 6 - Insurance and legal liability | The Commonwealth Government guarantee the payment of claims by ensuring that, whenever a funding shortfall occurs in the reinsurance facility through claims exceeding the funds held in the facility, the Commonwealth would meet the shortfall and the Commonwealth would seek reimbursement of a portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2937 | 6 - Insurance and legal liability | That flood premium discounts be delivered through a model that requires insurers to retain and price a portion of the risk with the remainder to be ceded to the reinsurance facility at a discounted reinsurance premium. |
REC187-2954 | 6 - Insurance and legal liability | That subsection 35(2) of the Insurance Contracts Act 1984 be amended so that policyholders are not deemed to be clearly informed of a deviation from ‘standard cover’ by simply being provided a copy of the insurance policy or product disclosure statement. |
REC187-2926 | 6 - Insurance and legal liability | That flood premium discounts be provided for home building insurance for eligible homes: |
REC187-2942 | 6 - Insurance and legal liability | That a flood risk reinsurance facility, or reinsurance pool, be established which would have two primary functions: |
REC187-2959 | 6 - Insurance and legal liability | That every APRA-authorised general insurer adopt and comply with the General Insurance Code of Practice. |
REC187-2931 | 6 - Insurance and legal liability | That the definition of a home for the purposes of flood cover and flood premium discounts be any building for which a homeowner purchases a home insurance policy. |
REC187-2948 | 6 - Insurance and legal liability | That: |
REC187-2964 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice such that the General Insurance Code Compliance Committee: |
REC187-2920 | 6 - Insurance and legal liability | That a system of premium discounts be introduced in order that most purchasers of home insurance, home contents and home unit insurance policies in areas subject to flood risk be eligible for discounts against the full cost of flood insurance. |
REC187-2936 | 6 - Insurance and legal liability | That the questions of flood cover as standard in small business policies and access to discounted premiums for small business policyholders should be revisited once the recommended arrangements for homes, home units and home contents are in place. |
REC187-2953 | 6 - Insurance and legal liability | That all home building insurance policies providing sum insured cover be modified by the end of 2014 so as to include replacement value cover in the event of total loss of the home. That during the transition period insurers consider how the design features of home building replacement value policies should respond following a natural disaster, including the conditions under which cash settlements are to be offered and finalised. |
REC187-2925 | 6 - Insurance and legal liability | That the following five principles underpin the design of a system of premium discounts: |
REC187-2941 | 6 - Insurance and legal liability | That homes at high and extreme risk of flood be provided with discounts initially and that they be assessed regularly for mitigation work already undertaken and the potential for further mitigation. |
REC187-2958 | 6 - Insurance and legal liability | That, in order to give general insurance policyholders the same legal remedies as other consumers, unfair contract terms laws be applied to general insurance. |
REC187-2930 | 6 - Insurance and legal liability | That flood premium discounts be provided, in the same manner as for homes, to the bodies corporate of eligible properties, and on the same basis as for detached homes. |
REC187-2947 | 6 - Insurance and legal liability | That the Agency charge insurers a small administrative fee for each policy ceded to the reinsurance facility. |
REC187-2963 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice to require that: |
REC187-2919 | 6 - Insurance and legal liability | That all home insurance, home contents and home unit insurance policies include flood cover. |
REC187-2935 | 6 - Insurance and legal liability | That flood premium discounts not be provided to small businesses and that the reinsurance facility not offer reinsurance for small businesses. |
REC187-2952 | 6 - Insurance and legal liability | That lending institutions remind mortgagors annually of their obligations to hold home insurance and of the risks of under-insurance in order to minimise non-insurance and under-insurance of homes. |
REC187-2968 | 6 - Insurance and legal liability | That the Government give priority to introducing legislation necessary to ensure that all home, contents and home unit insurance policies include flood cover and to establish a new national agency for flood risk management and flood reinsurance purposes. |
REC187-2924 | 6 - Insurance and legal liability | That whenever flood cover is included in home building insurance policies: |
REC187-2940 | 6 - Insurance and legal liability | That for home contents insurance policies, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $100,000. For contents with a value greater than $100,000 policyholders then pay the full cost of the portion of risk exceeding $100,000. |
REC187-2957 | 6 - Insurance and legal liability | That the Commonwealth Government introduce a standard definition of flood in the form proposed in the ‘Reforming flood insurance: Clearing the waters’ consultation paper. |
REC187-2929 | 6 - Insurance and legal liability | That all home unit insurance policies include flood cover, in the same manner as for homes. |
REC187-2945 | 6 - Insurance and legal liability | That to facilitate flood risk information being made publicly available, Commonwealth, State and Territory governments grant indemnities to the providers of flood risk information if the information is obtained and provided in good faith and in the absence of any gross negligence. |
REC187-2962 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend clause 4.5 of the General Insurance Code of Practice to extend the time within which claimants in natural disasters have the right to make further claims or lodge reviews after the finalisation of an initial claim to seven months from the date of the relevant natural disaster, regardless of when the initial claim was finalised. |
REC187-2934 | 6 - Insurance and legal liability | That all insurers offering small business insurance be obliged to include flood cover on an opt-out basis, instead of an opt-in/opt-out basis as at present, in all of their small business package policies. |
REC187-2951 | 6 - Insurance and legal liability | That access to insurance be enhanced through the development of alternative payment options, in particular: |
REC187-2967 | 6 - Insurance and legal liability | That the current formula for the cost of rebuilding of State and Territory assets under the Natural Disaster Relief and Recovery Arrangements be changed to expenditure before any insurance recoveries by the State or Territory rather than net of any insurance recoveries. |
REC187-2923 | 6 - Insurance and legal liability | That home building and home contents insurance should not be made compulsory. |
REC187-2939 | 6 - Insurance and legal liability | That for body corporate insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000 times the number of units. For properties with a value greater than $500,000 times the number of units policyholders then pay the full cost of the portion of risk exceeding $500,000 times the number of units. |
REC187-2956 | 6 - Insurance and legal liability | That a ‘health warning’ be provided by insurers to the purchasers of home and contents policies that do not include full flood cover or full replacement cover. The health warning should be provided: |
REC187-2928 | 6 - Insurance and legal liability | That there be limitations on the size of the discount available to high-value homes. |
REC187-2944 | 6 - Insurance and legal liability | That the Commonwealth seek reimbursement of some portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2961 | 6 - Insurance and legal liability | That the Insurance Council of Australia repeal clauses 4.3 and 4.4 of the General Insurance Code of Practice, so that claims arising from natural disasters are subject to the same minimum standards as other claims — including the four month time limit for a determination on liability and the nature of the loss/damage with respect to the claim. |
REC187-2933 | 6 - Insurance and legal liability | That discounts be provided, in the same manner as for homes, to home contents insurance policies for eligible properties. |
REC187-2950 | 6 - Insurance and legal liability | That the Commonwealth engage with the insurance industry and the States and Territories in planning for the future coordination of charitable and government payments to individuals to assist with recovery after future natural disasters. |
REC187-2966 | 6 - Insurance and legal liability | That the Commonwealth and State governments provide funding for legal advice and assistance with insurance disputes following natural disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC185-1933 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Treasury clarify what is meant by the term 'cost-effective' as it relates to the 2011 NDRRA Determination and the scrutiny of the states' and territories' insurance arrangements. |
REC185-1932 | 6 - Insurance and legal liability | The committee recommends that a particular focus of the Natural Disasters Insurance Review into the adequacy of current insurance arrangements should be on whether the international insurance market offers reinsurance for the states' and territories' road networks. |
REC185-1930 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Government consult with state and territory governments to ensure that the states' and territories' captive insurance and reinsurance arrangements are reported transparently and on a comparable basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3310 | 6 - Insurance and legal liability | Consideration should be given to ways to ensure that contractors who are involved in barrier installation (such as cementing companies) have a direct interest in the performance of works to a proper standard. In particular, consideration should be given to (i) preventing contractors from avoiding the economic consequences of negligent installation of barriers; and/or (ii) imposing specific legislative standards of workmanship on contractors with respect to well control (similar to those which presently apply to licensees). |
REC177-3369 | 6 - Insurance and legal liability | The obligation of companies involved in an incident to meet the full costs of monitoring and remediation should be made a condition of approval of proposals under the EPBC Act and OPGGS Act. Suitable arrangements (insurance or otherwise) need to be in place to ensure that companies have this capacity. |
REC177-3365 | 6 - Insurance and legal liability | The National Plan should specify that the cost of responding to an oil spill, or other damage to the offshore marine environment, will be totally met by the owner/operator. This would be consistent with the Inquiry’s recommendation for legislative changes to the regulatory framework concerning owner/operators meeting the cost of monitoring and remediation of environmental damage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3010 | 35 - Business and Industry in relation to industry | Energy Security Working Group (ESWG) recommends consideration be given to government and industry working together to understand that investment opportunities in the energy sector are realised in a timely fashion to better manage potential longer term supply shortfalls. |
REC162-3015 | 35 - Business and Industry in relation to industry | ESWG recommends National Gas Emergency Response Advisory Committee maintain its industry, jurisdiction and consumer representation noting the importance of input from each of these groups in developing its advice. |
REC162-3021 | 35 - Business and Industry in relation to industry | ESWG notes that existing and future contracts and the impending introduction of the Short Term Trading Market will be the primary mechanisms for addressing future gas supply shortfalls. |
REC162-3014 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to leveraging AEMO’s expanded responsibilities in gas markets by undertaking the role of the National Gas Emergency Response Advisory Committee (NGERAC) Secretariat while the Commonwealth continue as Chair, with the Chair’s position to be reviewed once the short term trading market (STTM) commences in June 2010. ESWG also recommends that the review be undertaken by NGERAC jurisdictional members. |
REC162-3020 | 35 - Business and Industry in relation to industry | ESWG recommends that as far as reasonably practical, arrangements for load shedding be as transparent as possible to give consumers confidence in the process. |
REC162-3013 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to consolidating gas and electricity network status and emergency information on one webpage for central communication. |
REC162-3019 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to the spokesperson role AEMO can undertake during an electricity and/or gas supply shortfall in its covered markets and relevant jurisdictional emergencies, noting that AEMO has clear responsibility for the bulk supply of electricity as outlined in the Power System Emergency Management Plan and the Victorian wholesale gas market, and that for multi-jurisdiction gas supply emergencies, any AEMO spokesperson role would be to reflect NGERAC’s advice. |
REC162-3012 | 35 - Business and Industry in relation to industry | ESWG recommends reviewing AEMO’s Gas Bulletin Board (GBB) to ensure it is effectively communicating all publicly available information to market participants to assist in monitoring daily gas supplies, and any changes to the GBB rules required to improve information and awareness of any potential shortages that will assist the market to make the necessary investments and/or adjustments in maintenance. |
REC162-3018 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of a review of communication protocols with the aim of achieving high level policy consistency of communication across jurisdictions to the maximum extent possible. |
REC162-3011 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to expanding the role of AEMO in providing market information on gas by: |
REC162-3017 | 35 - Business and Industry in relation to industry | ESWG notes NGERAC already informally advises ministers on the possible effects of gas emergencies on electricity supplies. ESWG recommends formalising this role by acknowledging it in NGERAC’s MOU. ESWG also recommends an editorial review of NGERAC’s MOU to ensure accuracy and consistency. |
REC162-3022 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of how to ensure good communication and flow of information between the liquid fuels and other energy sectors. One approach that may be considered is that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
REC153-1804 | 35 - Business and Industry in relation to industry | That the Chief Officer and the Editors of all newspapers and other media outlets develop a Memorandum of Understanding that ensures that all CFS press releases concerning total fire ban days and ongoing bushfire incidents are published in full. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3401 | 15 - Inter-service cooperation | The streamlining correspondence to Emergency Service Agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3212 | 6 - Insurance and legal liability | The Committee recommends that the Australian Government request the Productivity Commission to undertake an inquiry into the projected impacts of climate change and related insurance matters, with a particular focus on: |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3635 | 15 - Inter-service cooperation | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, seek to create systematic mechanisms for better targeting and evaluating inter- agency coordination within the National Capability Development Exercise Programme and continuous improvement cycle. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2098 | 15 - Inter-service cooperation | The Working Group recommends that Emergency Management Australia (EMA) facilitate national discussions into the capability of States/Territories to ensure thorough collaborative systems and plans for inter-jurisdictional resource interoperability exist, and where this has not already occurred at State/Territory level and appropriate agencies, committees or government departments can be identified, they should be tasked with progressing specific issues in the following areas: |
REC116-2121 | 35 - Business and Industry in relation to industry | The Working Group recommends that the Australian Government investigate, in consultation with the finance and banking sector, the development of arrangements to ensure that essential transactions can continue in the event of a catastrophic failure of the banking system that includes access to cash. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2102 | 35 - Business and Industry in relation to industry | The Working Group recommends that jurisdictions identify appropriate commercial organisations/bodies able to ensure maintenance of supply of food items and packaged water to commercial outlets in times of disaster. |
REC116-2101 | 35 - Business and Industry in relation to industry | The Working Group recommends that each jurisdiction; |
REC116-2119 | 6 - Insurance and legal liability | The Working Group recommends that the National Recovery Coordinators Group approach the Investment and Financial Services Association Limited, with a view to identifying the most appropriate way of engaging the life insurance industry in the recovery process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2183 | 6 - Insurance and legal liability | Further to recommendation 21 in Chapter 4, the Committee recommends that the Commonwealth seeks to ensure that the proposed Council of Australian Governments review of the bushfire management, initiate |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2175 | 6 - Insurance and legal liability | The Committee recommends that insurance companies ensure that potential and existing policyholders are aware of the need to regularly review their insurance policies to prevent undervaluing. This could be done through renewal notices and quarterly reminders. This should include a list of bushfire risk reduction measures that policyholders can implement to decrease the cost of their premium. |
REC098-2172 | 6 - Insurance and legal liability | The Committee recommends that taxes on insurance premiums be calculated only on the premium in order to eliminate the current cascading cost. |
REC098-2157 | 6 - Insurance and legal liability | The Committee recommends that the Commonwealth Government work with Australasian Fire Authorities Council to review the insurance cover provided to volunteer fire fighters in all states and territories and ensure that cover is adequate for loss of life or injury and related loss of income and property lost in the line of duty. |
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |