REC325-4335 | 16 - Training and behaviour | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services update and deliver training on the workflow reviewed (as per Recommendation 3) of the current Emergency Alert system to all persons responsible at a local, district and state level by 1 November 2022. Training should address system constraints and system complexities in addition to the process of requesting, composing (including Clear Explicit Translatable Language [CETL]), authorising and issuing Emergency Alerts. |
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2469 | 12 - EM agency and authority | Entities with disaster management responsibilities need to integrate the eight priorities identified within the Emergency Management Sector Adaptation Plan for Climate Change into their disaster management planning cycle. |
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2474 | 16 - Training and behaviour | The provision of system-wide tools, education, guidance and testing for requests for assistance is strengthened to enhance understanding and outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC293-1336 | 32 - Doctrine, standards, and reform | The chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services, implement the Mackay Disaster District capability improvement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1417 | 32 - Doctrine, standards, and reform | That the following disaster management doctrine are reviewed and reissued to ensure consistency and improved guidance to local government: |
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
REC272-1421 | 16 - Training and behaviour | In conjunction with the Queensland Fire and Emergency Services review of guidelines, the Public Safety Business Agency should consider reviewing the cyclone shelter management training package to include guidance to the shelter management team on their roles and responsibilities, and powers available under legislation and how these may be exercised. |
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1532 | 32 - Doctrine, standards, and reform | The evacuation sub-plan component of the Local Disaster Managment Plan should be reviewed, including any identified triggers for activation. Ideally, the plan should be tested in a live, multi-agency exercise prior to next summer. |
REC271-1531 | 32 - Doctrine, standards, and reform | Banana Shire Council completes business continuity planning as a matter of priority, including documentation and testing of the plan. |
REC271-1530 | 16 - Training and behaviour | Local Disaster Coordination Centre capability and capacity should be reviewed to ensure adequate staffing arrangements are in place to fill key positions, and that operational protocols are known and practiced across all functions to provide redundancy. Assistance for review and necessary training should be sought from key Local Disaster Management Group member agencies. |
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC269-1168 | 32 - Doctrine, standards, and reform | The Local and District Disaster Management Guidelines are reviewed to align with the Standard for Disaster Management in Queensland. |
REC269-1167 | 32 - Doctrine, standards, and reform | That Queensland’s disaster management arrangements are reviewed to enhance integration. Specifically: · to address the disparity between functions and structure of local government and disaster groups · to integrate hazard specific agency planning at all levels of the arrangements (This may include legislative, policy and procedural considerations). |
REC269-1171 | 32 - Doctrine, standards, and reform | State agencies with disaster management roles and responsibilities assess their performance by including a disaster management performance measure in chief executive officers’ performance agreements. This measure should reinforce an obligation for agencies to participate in the arrangements at all levels. |
REC269-1170 | 32 - Doctrine, standards, and reform | Responsibilities of functional lead agencies and hazard-specific primary agencies are clearly articulated in state level doctrine, including the Queensland State Disaster Management Plan. |
REC269-1169 | 32 - Doctrine, standards, and reform | An integrated risk-based approach to disaster management planning for Queensland is developed that is consistent with the Standard for Disaster Management in Queensland and applicable at all levels of the arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1428 | 16 - Training and behaviour | The Warning and Alert Systems training (including the use of Emergency Alert and the requirements of the guidelines) is delivered to: |
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2651 | 13 - Mapping and data quality | That the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomesThat the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2670 | 12 - EM agency and authority | That prisoner transport and non-managerial roles within watch-houses should be a priority for contestability. |
REC239-2704 | 32 - Doctrine, standards, and reform | That the current SES memoranda of agreement between the Department of Community Safety and local governments be revised to include a clear statement as to the command and control arrangements between State and respective local governments. These arrangements should also be reflected in the local disaster management plans. |
REC239-2730 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service actively progress initiatives for flexible employment including: |
REC239-2751 | 12 - EM agency and authority | That collaboration on new initiatives such as the co-responder model in Cairns continue and if successful, initiatives should be considered for state wide or service wide adoption. |
REC239-2680 | 12 - EM agency and authority | That the fire service takes a broader view of its role as an emergency management organisation. |
REC239-2713 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the Deputy Commissioner of Regional Operations (Department of Fire and Emergency Services): |
REC239-2736 | 36 - Volunteers | That training for volunteers be reviewed to determine which courses require national standardisation. Organisational training should then address the remaining training needs. The review should take into account the risk exposure to government agencies if changes are to be made. |
REC239-2760 | 12 - EM agency and authority | That a suitably qualified Chief Information Officer with whole of portfolio responsibility is appointed to oversight corporate support and capability development |
REC239-2658 | 12 - EM agency and authority | That the Queensland Ambulance Service maintains its own identity to: |
REC239-2693 | 32 - Doctrine, standards, and reform | That the presence of police in State Disaster Coordination Centre response teams is mandated and formalised through documented standard operating procedures. |
REC239-2718 | 32 - Doctrine, standards, and reform | That the Department of Fire and Emergency Services be created through the renaming and amendment to the existing Fire and Rescue Service Act 1990 including: |
REC239-2741 | 16 - Training and behaviour | That the annual training calendar identify course, training location and the coordinating authority. |
REC239-2669 | 12 - EM agency and authority | That specific business cases should be developed for contestability of correctional services in Queensland, including: |
REC239-2702 | 32 - Doctrine, standards, and reform | That the Queensland Police Service and SES develop clear operational protocols to ensure that SES assistance is not exploited. |
REC239-2729 | 16 - Training and behaviour | That the Queensland Fire and Rescue Service work to change the culture of entitlement so that firefighters recognise firefighting is only one of a range of skills they bring to their core role of emergency management. |
REC239-2746 | 36 - Volunteers | That volunteers should be engaged to assist in determining what constitutes ‘fit for task’ and how that should be implemented. |
REC239-2677 | 12 - EM agency and authority | That biometric tools be leveraged for other demands (e.g. bail reporting). |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2735 | 32 - Doctrine, standards, and reform | That the new Department of Fire and Emergency Services develop a common doctrine to protect people from fire and emergencies. |
REC239-2756 | 32 - Doctrine, standards, and reform | That the Chief Executive Officer Portfolio Business consider ‘big data’ problems and solutions in line with the outcome of the efficiency review into the Queensland Police Service and ensure alignment with whole of government solutions. |
REC239-2656 | 12 - EM agency and authority | That the Queensland Ambulance Service is maintained as a state-wide service into the future. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2717 | 32 - Doctrine, standards, and reform | That the ‘Functions of Chief Executive’ under the Disaster Management Act 2003 are amended to remove those functions that will become the role of the proposed Inspector General of Emergency Management. |
REC239-2740 | 16 - Training and behaviour | That impediments to the publication of an annual training calendar of core skills be removed. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2668 | 32 - Doctrine, standards, and reform | That as part of reviewing its legislation, Queensland Corrective Service should ensure that amendments be made to ensure a stronger onus is placed upon a more efficient process to receive prisoners with a view to reducing the time spent in police watch houses. |
REC239-2698 | 12 - EM agency and authority | That the Deputy Commissioner, Operations (of the proposed new Department of Fire and Emergency Services) should be responsible for ensuring the readiness of the disaster operations system, including the State Disaster Coordination Centre, enabling seamless transition to police control when required. |
REC239-2728 | 32 - Doctrine, standards, and reform | That the Fire and Rescue Act 1990 be amended so that Commissioner’s position is not limited to a “person with professional experience in fire prevention and fire fighting”. |
REC239-2745 | 12 - EM agency and authority | That the Emergency Service Cadet Program take a full spectrum approach to emergency services |
REC239-2676 | 32 - Doctrine, standards, and reform | That any changed arrangements to the operations of Queensland Corrective Service ensure anti-corruption, prisoner management, and accountability processes are defined and established. |
REC239-2707 | 12 - EM agency and authority | That the Inspector General Emergency Management ensures that improvement strategies identified are acted upon and improvement strategies embedded within agencies as standard practice. |
REC239-2734 | 12 - EM agency and authority | That a new Deputy Commissioner position be created to manage volunteer emergency services including the Rural Fire Service and the State Emergency Service. |
REC239-2755 | 32 - Doctrine, standards, and reform | That the Queensland Police Service bring this practice to the attention of the Privacy Commissioner and discuss a new service wide policy on the retention of data to ensure that their officers are not acting in breach of the law. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
REC239-2716 | 12 - EM agency and authority | That the remainder of the current Emergency Management structure transition to the Commissioner, Fire and Emergency Services for further consideration regarding the most appropriate reporting alignment giving due consideration to existing capacity. This should be done in consultation with the Commissioner, the Queensland Police Service to ensure proper collaboration with the Queensland Police Service Disaster Management Unit staff. |
REC239-2739 | 36 - Volunteers | That the Queensland Police Service and the Department of Community Safety develop intuitive, easily accessible systems that reduce the administrative burden on volunteers and their time. Greater exploitation of technology to deliver intuitive, simple and practical systems is required. |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2666 | 32 - Doctrine, standards, and reform | That a system should be designed so that the prisoner and the prisoner’s prescribed drugs are treated as one and therefore travel together through the system for whatever purpose. |
REC239-2697 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit work with emergency management staff in the new portfolio to produce the State disaster management plan. |
REC239-2722 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service should introduce alternative means of response to automatic alarms such as small first response investigative crews e.g. two fire–fighters in a sedan (not responding under lights and siren). |
REC239-2744 | 12 - EM agency and authority | That the revitalised PCYC Emergency Service Cadet Program continue to be supported by government. |
REC239-2672 | 12 - EM agency and authority | That Queensland Corrective Service conduct business analysis and planning to clearly identify its customers and its contribution to the Government’s priorities |
REC239-2706 | 12 - EM agency and authority | The establishment, management, support and education of the State Emergency Service (SES) become the responsibility of a Deputy Commissioner, Fire and Emergency Services and this person should also be responsible for Rural Fire Service Queensland. |
REC239-2733 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service reduce the number of communication centres to two, with one being a primary site and the other site providing redundancy and business continuity functionality. |
REC239-2754 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business should overhaul portfolio information and communication technology and appoint a Chief Information Officer with appropriate qualifications and significant industry experience as a first priority. |
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
REC239-2715 | 12 - EM agency and authority | That the Disaster Management Standards Branch element of Standards Improvement, transition to the Inspector General Emergency Management. |
REC239-2738 | 36 - Volunteers | That the current employer and family recognition practices be reviewed with a view to meet the needs of volunteers, their families and their employers. |
REC239-2766 | 12 - EM agency and authority | Recommendation: |
REC239-2665 | 12 - EM agency and authority | That planning, especially for infrastructure, must take into account the service delivery model (e.g. the fact that prisoners have high level health needs). |
REC239-2696 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit be given responsibility for production of the State disaster management plan for the State Disaster Management Group’s approval. |
REC239-2720 | 12 - EM agency and authority | That a reduced regional model for fire and emergency services be generally aligned to that of the Queensland Police Service with a district structure that accords with disaster districts. |
REC239-2743 | 12 - EM agency and authority | That where practicable, the consideration for new or enhanced facilities include an assessment of the viability of creating a Rural Fire Service /SES common user facility. |
REC239-2671 | 16 - Training and behaviour | That all Queensland Corrective Service provision of training should be contestable. |
REC239-2705 | 32 - Doctrine, standards, and reform | That the Inspector General Emergency Management assess the effectiveness of plans and policy in relation to SES deployment and command and control. |
REC239-2731 | 12 - EM agency and authority | That the CEO Portfolio Business and the Commissioner Queensland Fire and Rescue Service find a more appropriate method of accounting for part time and volunteer staff when considering the support required to raise, train and sustain this very large part of the workforce. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2714 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the position of Deputy Commissioner Rural Fire Service Queensland and State Emergency Services: |
REC239-2737 | 29 - Operational Health and Safety | That the workplace health and safety reporting system be reviewed to facilitate ease of reporting. |
REC239-2765 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business promote innovation and drive cultural change in terms of business practice. |
REC239-2663 | 12 - EM agency and authority | That the Commissioner of Queensland Corrective Service report directly to the Director-General the Department of Justice and Attorney-General. |
REC239-2695 | 32 - Doctrine, standards, and reform | That the Disaster Management Act 2003 be amended to: |
REC239-2719 | 12 - EM agency and authority | That the current Queensland Fire and Rescue Service model of functional management be expanded, shifting line management responsibility for community safety operations and professional development from Regional Assistant Commissioners to the State Commanders. Regional Assistant Commissioners become responsible for operations and coordination of departmental support within geographic locations and report to the Deputy Commissioner operations. |
REC239-2742 | 12 - EM agency and authority | That the recommendations of The Malone Review in relation to Criminal History checks, so far as supported, by the Review team in this report be progressed inclusive of SES issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0724 | 28 - Personal responsibility | Councils should consider making available to business owners locality specific information that would assist them to develop evacuation plans for commercial premises, for example, any evacuation sub-plan created under Emergency Management Queensland’s disaster evacuation guidelines. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0723 | 28 - Personal responsibility | Councils should support and encourage business owners to develop private flood evacuation plans by providing the following to business owners in areas known to be affected by flood: • information about the benefits of evacuation plans • contact details of relevant council and emergency service personnel for inclusion in evacuation plans. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
REC210-0679 | 28 - Personal responsibility | If the Queensland Development Code is amended to include provisions requiring homeowners to install sewage reflux valves, the Queensland Government should develop and make available to homeowners appropriate guidance material to assist them in meeting their responsibilities to maintain reflux valves. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1924 | 32 - Doctrine, standards, and reform | That the Queensland Reconstruction Authority review and approve the draft organisational policies and procedures, in the areas of human resources, finance, communications and information technology. |
REC190-1925 | 32 - Doctrine, standards, and reform | That the Queensland Reconstruction Authority develop and implement policies and procedures to ensure the adequate management and security of public records in accordance with the Public Records Act 2009. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0088 | 32 - Doctrine, standards, and reform | The State Disaster Management Act be strengthened by a description of the phases of Disaster Management with emphasis on the key elements within each phase including the recovery phase; Lead Agencies and nominated leaders in each area of Queensland for each of the four key elements of recovery be identified and provided with the appropriate training and familiarisation of their role to ensure the adequacy of planning at District and Local level throughout Queensland; Lead Agencies be responsible for maintaining strong relationships with counterparts at the Federal Government level to ensure necessary Federal support for State and Local recovery initiatives after disaster events; Response arrangements remain in place until the State Controller is satisfied that recovery leadership arrangements are in place at Local, District and State levels; Recovery leadership and support from State level remain in place until local recovery is substantially completed. |
REC165-0094 | 32 - Doctrine, standards, and reform | The Act be amended to make it clear that Disaster Controllers/Coordinators at all levels are to be authorised public officials with the necessary training and authority to properly discharge the role and provide an effective direct line of support, coordination and control of disaster events. The Act and State Plan provide guidance about appropriate role and functions of elected representatives during all disaster event phases. The Major Incidents Group and State Security Committee be merged to become the State Disaster and Security Council with role as suggested in this report. |
REC165-0078 | 32 - Doctrine, standards, and reform | The basic tenet of a local community response as the foundation of Queensland's Disaster Management framework, with a clear description of the relationships between the levels and description of the phases of Disaster Management, needs to be more strongly emphasised in the "objects" of the legislation and "how objects are to be achieved". |
REC165-0084 | 32 - Doctrine, standards, and reform | The State Disaster Management Group focus on Disaster Management strategy and policy with sub-committees or appropriate levels in the Disaster Management system assigned detailed disaster planning or risk management assessment roles. New group members be provided with an induction briefing about the State's Disaster Management arrangements by the Executive Officer prior to attending their first meeting. |
REC165-0093 | 32 - Doctrine, standards, and reform | The Department of Community Safety (through EMQ) be assigned in the Act with the responsibility to develop, maintain, monitor and continuously improve the State's Disaster Management arrangements and systems. The Executive Director, EMQ, be a member of SDMG with the Director-General, Department of Community Safety. The position of Executive Officer, SDMG, be assigned appropriate support roles to SDMG. An officer other than the Executive Director, EMQ, or the State Controller of a disaster event, perform the role of Executive Officer to the SDMG. A dedicated Assistant Commissioner of Police be assigned the role of control, coordination and overall responsibility for Queensland's response to disaster events other than those subject to National Plans and Agreements. |
REC165-0083 | 32 - Doctrine, standards, and reform | The Chairperson of SDMG (where leadership is not already defined in relevant National Plans) nominate a senior officer to assume overall responsibility for control and coordination of each disaster event to ensure a decisive and effective response. At Local level the Act provide for the CEO in consultation with the LDMC to appoint a public official/s with required training and competence as Local Controller. |
REC165-0092 | 32 - Doctrine, standards, and reform | Executive Officers to DDCs be serving Police Officers. Regional and Area officers of EMQ be members of Local and District Disaster Management Groups to enable them to fulfil their Statewide support and governance roles. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0091 | 32 - Doctrine, standards, and reform | EMQ resources be directed to continually improving, monitoring and regularly evaluating the State's Disaster Management system with a priority focus on providing support to Local Government levels including interlinking exercises involving District and State arrangements. |
REC165-0080 | 32 - Doctrine, standards, and reform | The State Disaster Management Plan incorporate linkages with all Lead Agencies and officers in control of National Plan or Agreement response. All of these Plans and Agreements should have a formal requirement to ensure officers in charge work within the State's Disaster Management framework to deliver Disaster Management responses. |
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0099 | 32 - Doctrine, standards, and reform | The suggested summary of legislative changes guide the legislative response to the report incorporating consultation with key stakeholders at State, District and Local levels. |
REC165-0079 | 32 - Doctrine, standards, and reform | The Act be amended (Sections 45, 46, 47) to enable verbal directions in times of disaster responses from a State Controller to DDC to Local Controller, which must be committed to writing promptly to formalise the record. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3942 | 32 - Doctrine, standards, and reform | It is recommended that public sector entities establish frameworks which will provide for more effective governance over business continuity management. |
REC111-3938 | 32 - Doctrine, standards, and reform | To ensure an effective and co-ordinated approach to communication throughout the Queensland disaster management system, it is recommended that — |
REC111-3937 | 16 - Training and behaviour | To enhance the delivery of disaster management services, it is recommended that the Department of Emergency Services — |