Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4339 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends that Queensland Fire and Emergency Services review and update the State Disaster Risk Report, including re-evaluating the risk of flooding by all types. Queensland Fire and Emergency Services should publish the updated State Disaster Risk Report by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1269 | 35 - Business and Industry in relation to industry | That Government engages with non-government organisations that may provide services during emergency events to clarify the terms and conditions for support through a written arrangement (MOU or similar). |
REC297-1257 | 35 - Business and Industry in relation to industry | That in the event that Hydro Tasmania decides to start cloud seeding again, water managers, represented by DPIPWE, work with Hydro Tasmania to ensure appropriate, best practice application of the guidelines issued by the Agricultural and Resource Management Council of Australia and New Zealand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2813 | 38 - Agency/Department Reporting | To strengthen its oversight of Queensland reconstruction progress, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce: |
REC234-2810 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Australian Government Reconstruction Inspectorate and the National Disaster Recovery Taskforce seek to maximise the benefits from their value for money review activities by obtaining more timely and comprehensive information on project progress and completion from the Queensland Reconstruction Authority, to enable the preliminary value for money assessments to be finalised based on the scope and cost of works that were actually delivered (rather than estimates). |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2820 | 21 - Role of Commonwealth Government | Having regard to the terms of the Torres Strait Treaty, the Department of Health and Ageing, Queensland Health, AusAID and the Papua New Guinea Government: |
REC232-2817 | 21 - Role of Commonwealth Government | The Australian Government work with the state and territory governments to assess the viability of providing a centralised refugee and migrant health service in each state and territory, which would automatically refer people who move from immigration detention into the wider Australian community. |
REC232-2826 | 21 - Role of Commonwealth Government | The Australian Government coordinate the development of a highly skilled workforce which can respond effectively to a sustained pandemic in Australia. |
REC232-2825 | 21 - Role of Commonwealth Government | The Commonwealth Government support the growth of vaccine development and production capacity for vaccines in Australia, to enhance Australia’s preparedness to respond to outbreaks of infectious disease in Australia, and in particular, pandemic influenza. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0763 | 35 - Business and Industry in relation to industry | Seqwater should ensure that the Somerset Dam gallery is not susceptible to flooding during overtopping events. |
REC210-0708 | 35 - Business and Industry in relation to industry | The Queensland Government should work collaboratively with the Commonwealth Government and mine operators to ensure co-ordinated and effective monitoring of salts, metals and other contaminants in marine environments that may be affected by mine discharges. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0427 | 35 - Business and Industry in relation to industry | the state require dam owners and operators provide regular situational reports to the relevant control agency where dam issues may impact incident management. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0426 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform people situated downstream of water storages if the owners/operators become aware of an immediate threat arising from the dam to the safety of those people. The owner/operators should provide this information as soon as the owner/operators become aware of the threat. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0425 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform the control agency and the Bureau of Meteorology about the management and operation of dams and weirs consistent with the flood warning requirements of the relevant river systems, including providing telemetry at sites as necessary. This may require the state proactively liaising with other states to ensure equivalent obligations are placed on interstate dam operators where the dam may impact Victorian communities. |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0424 | 35 - Business and Industry in relation to industry | the state require dam owners and operators to review storage operating manuals to incorporate lessons from the 2010–11 floods and make this information publicly available. The manuals should include a clear policy on dam surcharging and pre-release. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2946 | 21 - Role of Commonwealth Government | That a national agency sponsored by the Commonwealth Government be established to undertake national coordination of flood risk management and to operate the system of premium discounts and the flood risk reinsurance facility. The Agency would: |
REC187-2918 | 21 - Role of Commonwealth Government | That an agency sponsored by the Commonwealth Government be created to manage the national coordination of flood risk management and to operate a system of premium discounts and a flood risk reinsurance facility, supported by a funding guarantee from the Commonwealth. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3493 | 35 - Business and Industry in relation to industry | The electricity distribution businesses and retailers work with the Department of Human Services and hospitals to review the registration, notification and removal process for those on life support machinery. |
REC156-3496 | 21 - Role of Commonwealth Government | The Bureau of Meteorology contact list for severe weather warning be strategically managed in consultation with Emergency Service Organisations, to identify critical contacts. The Bureau of Meteorology must ensure the detail for these critical contacts remains up to date. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3502 | 35 - Business and Industry in relation to industry | The Emergency Services Telecommunications Authority in partnership with Telstra should develop testing regimes that will ensure the integrity of the call queue arrangements and correct configuration of the Recorded Voice Announcements. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3151 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse |
REC148-3164 | 21 - Role of Commonwealth Government | That there be similar facilities for the unloading and transfer of horses at any other airport in Australia that might receive horses imported from places other than New Zealand. |
REC148-3178 | 38 - Agency/Department Reporting | That the officer responsible for the importation of horses prepare a report to the Executive Director of AQIS that: |
REC148-3148 | 21 - Role of Commonwealth Government | That the Secretary of the Department of Agriculture, Fisheries and Forestry designate, without delay, a Senior Executive Service officer to be primarily responsible and accountable for the importation of horses into Australia and to that end to have the power to exercise all necessary authority. |
REC148-3149 | 38 - Agency/Department Reporting | That there be established the position of Inspector General of Horse Importation, the duties of that position being: |
REC148-3163 | 21 - Role of Commonwealth Government | That there be provided without delay at Sydney (Kingsford Smith) and Tullamarine Airports facilities to enable people who might have had contact with imported horses to shower and change their clothes, under supervision, before leaving the airport. |
REC148-3162 | 21 - Role of Commonwealth Government | That facilities for the unloading and transferring of horses at Tullamarine Airport in Melbourne be constructed urgently, upon advice of experts in biosecurity containment, to enable adequate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. |
REC148-3168 | 21 - Role of Commonwealth Government | That each government controlled and operated quarantine station have sufficient staff to carry out properly all activities and measures required by the current operating procedures dealing with the quarantine of horses. |
REC148-3161 | 21 - Role of Commonwealth Government | That the facilities for unloading and transferring of horses at Sydney (Kingsford Smith) Airport be upgraded without delay, following the advice of experts in biosecurity containment, so as to enable appropriate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. The facilities should include at least one padded box or stall sound-proofed to the extent that it is reasonable to do so. |
REC148-3166 | 21 - Role of Commonwealth Government | That, in the absence of other satisfactory government controlled and operated post-arrival quarantine stations becoming available before the options to renew the leases of Eastern Creek and Spotswood Quarantine Stations expire, those options be exercised. |
REC148-3152 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse Importation may be removed in the following circumstances only: |
REC148-3165 | 21 - Role of Commonwealth Government | That there continue to be in Australia government controlled and operated post-arrival quarantine stations for horses. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC134-3520 | 21 - Role of Commonwealth Government | To improve the management of the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing incorporate into its governance framework: |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3620 | 35 - Business and Industry in relation to industry | We recommend that NSW Health continue with its good work and conclude agreements with private health providers specifying roles, and expectations in the case of an infectious disease pandemic. |
REC129-3625 | 38 - Agency/Department Reporting | We recommend that NSW Health continue with its good work and establish a performance management framework with targets and indicators to assess progress in preparing for infectious disease emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3619 | 38 - Agency/Department Reporting | That the Department of Primary Industries should ensure the roles and capacities of Rural Lands Protection Boards and industry are effectively monitored to enable assessment of the effectiveness of animal health programs. |
REC128-3605 | 38 - Agency/Department Reporting | That the Department of Primary Industries make every effort to meet its targets for the TSE program and encourage public and private sector veterinarians across the State to submit samples. The Department should include reports on its performance against these targets in annual reports. |
REC128-3602 | 38 - Agency/Department Reporting | That the Department’s performance against tactical and strategic benchmarks be regularly reported in annual reports or animal and plant health emergency evaluation reports and compared to other jurisdictions where possible. |
REC128-3601 | 38 - Agency/Department Reporting | That, as a matter of principle, the NSW Government provide public reports on the lessons learned from emergency exercises which it manages or in which it participates. If necessary, such reports should exclude material which might jeopardise security. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3893 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures that stakeholders (and especially local councils) are fully consulted before and during the development of drainage strategies and plans. These plans should consider councils’ drainage systems. |
REC125-3892 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures stakeholder expectations are fully considered when setting flood risk reduction targets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3918 | 35 - Business and Industry in relation to industry | That DPI effectively communicates to all sectors of the industry their responsibilities to report new threats, and how to report them. |
REC112-3913 | 35 - Business and Industry in relation to industry | That DPI works with industry to develop a training module on the certification and verification system for inclusion in industry quality assurance programs. |
REC112-3929 | 35 - Business and Industry in relation to industry | That DPI develops a comprehensive strategy for communicating to industry their rights and responsibilities in relation to threats, incursions, outbreaks and post-outbreak; and also for communicating internally. |