Rec-ID | Code | Recommendation |
---|---|---|
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3492 | 22 - Role of local Gvt | The review of the municipal emergency management planning guidelines being led by the Office of the Emergency Services Commissioner clarify local governments’ role in community information about emergencies. |