Rec-ID | Code | Recommendation |
---|---|---|
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4339 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends that Queensland Fire and Emergency Services review and update the State Disaster Risk Report, including re-evaluating the risk of flooding by all types. Queensland Fire and Emergency Services should publish the updated State Disaster Risk Report by 1 November 2023. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4317 | 32 - Doctrine, standards, and reform | Flood rescue capability: That, to help improve the protection of life across NSW in flood events: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4301 | 32 - Doctrine, standards, and reform | Floodplains as assets: That, to establish the capacity and maximise the economic, social and environmental potential and consequently unlock the value of NSW floodplains, Government adopt the following guiding principles for floodplain management: |
REC324-4302 | 32 - Doctrine, standards, and reform | Disaster adaptation plans for all towns: That, to establish realistic expectations of safe spaces to live and deliver much needed housing quickly, Government through NSWRA working with local government: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1260 | 32 - Doctrine, standards, and reform | That DPIPWE clarifies responsibility for river restoration and riparian management and, having done so, communicates this to councils, landowners and other owners of relevant infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1301 | 32 - Doctrine, standards, and reform | Establish an ‘Interstate Deployment Support Plan’ for incoming interstate resources. The plan should outline responsibilities and arrangements for this function. Consider including this plan into the State emergency management arrangements. |
REC295-1277 | 32 - Doctrine, standards, and reform | That the Department of Planning, Transport and Infrastructure review their Business Continuity Plan to: |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1289 | 32 - Doctrine, standards, and reform | That SA Police, emergency services, health facilities, utility providers and other key service providers, review their Business Continuity Plans giving consideration to factors such as: a) identification of: business critical needs; essential services power requirements; back-up power requirements for all facilities including State, regional and local facilities such as Police, SES, MFS and CFS stations; the need for any arrangements for back-up power to be included in contracts for design and or lease of Government premises b) contingencies for black system events and extended power outages c) regular back-up generator testing regime protocols, including testing under load and for long durations d) contingencies for communications when mobile, landline and/or radios are not operational e.g. satellite phones; and e) alternative State control centre facilities that are pre-identified, equipped and have procedures for moving to the alternative facility. |
REC295-1333 | 32 - Doctrine, standards, and reform | Develop a State Relief and Recovery Plan as a distinct part of the State Emergency Management Plan which should include: a) potential locations for suitable facilities for relief and recovery centres which: are in locations safe from hazards such as flooding and bushfire; and, have appropriate access and suitable ablutions. b) formalisation of roles and capabilities of non-government organisations such as Red Cross |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1314 | 32 - Doctrine, standards, and reform | That an Emergency Management Assurance Framework be established as soon as possible to support the emergency management arrangements and the State Emergency Management Plan. Consider establishing an Inspector General Emergency Management department or position. |
REC295-1287 | 32 - Doctrine, standards, and reform | That the glossary of terms in the State Emergency Management Plan be reviewed to ensure all relevant language is included. All agencies need to ensure the use of clear communication and accurate use of terminology, including in describing the status of critical services e.g. Triple Zero (000), SA Government Radio Network, electrical and water supplies and infrastructure. |
REC295-1332 | 32 - Doctrine, standards, and reform | Develop a Disaster Waste Management Plan to form part of the State Emergency Management Plan which describe participating agencies and responsibilities for various aspects of waste management during and after emergencies. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1311 | 32 - Doctrine, standards, and reform | That the State Emergency Management Plan be reviewed and updated including: a) a better description of the responsibilities of Hazard Leaders Page xx b) establish a mechanism for a hazard leader to identify systemic failures in coordination of their hazard, with a clear process to raise those issues with SEMC and seek a remedy c) establish resilience as a key heading in the plan, with clearly documented strategies and responsibilities; and d) consider the Schar/Mulroney submission and taking a ‘fresh eyes’ approach |
REC295-1282 | 32 - Doctrine, standards, and reform | That the Office for Digital Government, in close partnership with telecommunications companies (e.g. Telstra, Optus, Vodaphone), develop a Control Agency Plan for Information and Communication Technology including mobile communications. The plan should consider: |
REC295-1331 | 32 - Doctrine, standards, and reform | Task South Australian Fire and Emergency Services Commission with further developing the Emergency Alerts capability across government agencies including to: a) establish and maintain a centralised training program for emergency alert initial and refresher training. b) establish a pool of endorsed Emergency Alert personnel from across government agencies to enable control agencies to assist each other with the emergency alert function during emergencies. c) develop supporting processes to ensure that the capability supports: emergencies involving any hazard; consistent issuing of alerts and warnings; consistent messages; and effective communication and notification of alerts issued to relevant internal and external stakeholders |
REC295-1295 | 32 - Doctrine, standards, and reform | That resources be provided to support the implementation of recommendations in the South Australian Levee Bank Management Issues Paper (DEWNR, 2015) including: a) development of relevant policy; and b) identification of responsibilities in relation to levee management and flood mitigation |
REC295-1310 | 32 - Doctrine, standards, and reform | That additional guidance be provided in the State Emergency Management Plan regarding the activation, structure and operation of Zone Emergency Support Teams. This should include: a) the reporting relationship between the Zone Emergency Support Teams, the State Emergency Centre and the State Coordinator b) briefing requirements between the State Coordinator (or their representative) and the Zone Emergency Support Teams when the State Emergency Centre is activated c) responsibilities for provision of local public information; and d) the appointment of public information officers in Zone Emergency Support Teams (where there is no incident management team (established) to provide information to local communities |
REC295-1281 | 32 - Doctrine, standards, and reform | In order to increase resilience and public safety during emergencies, the State Emergency Management Committee should request the Australia and New Zealand Emergency Management Committee to place on the agenda, and consider establishing a national position, on redundancies for mobile communications (including phone tower back-up power) and the National Broadband Network. |
REC295-1330 | 32 - Doctrine, standards, and reform | Update the Public Information Functional Support Group Plan to include: a) standards, outputs, systems and processes required to be used by control agencies and the Public Information Functional Support Group during emergencies b) guidance on the public information cycle through the prevention, preparedness, response and recovery phases which includes the responsibilities and information requirements during different phases, and effective transition between phases c) establishing a public information intelligence cell within the Public Information Functional Service Group; and d) identifying tools or resources to monitor social media |
REC295-1292 | 32 - Doctrine, standards, and reform | That, giving consideration to the previous recommendation, the Flood |
REC295-1309 | 32 - Doctrine, standards, and reform | That members of Emergency Management Council ensure they are prepared to undertake their roles and responsibilities during emergency events, including establishing: a) contingencies for communication e.g. satellite phone b) access to relevant documents such as the State Emergency Management Plan, supporting plans, ministerial guidelines, agency plans and contacts in hard copy and/or portable device c) formalised arrangements for briefings (up and down), and d) arrangements for suitable representation e.g. relevant Chief Executive(s) or their deputy, at all Emergency Management Council meetings . |
REC295-1280 | 32 - Doctrine, standards, and reform | That a State Plan be developed for managing the consequences of a black system event or other major power outage. The plan should include: |
REC295-1323 | 32 - Doctrine, standards, and reform | Review and update the role, function, workload and focus of the groups/committees that contribute to incident management and emergency management capabilities including the State Emergency Management Training Committee, Interagency Incident Management Sub-Committee and the Central Exercise Writing Team. |
REC295-1290 | 32 - Doctrine, standards, and reform | Continue development of the Damage Assessment Support Plan to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1417 | 32 - Doctrine, standards, and reform | That the following disaster management doctrine are reviewed and reissued to ensure consistency and improved guidance to local government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1532 | 32 - Doctrine, standards, and reform | The evacuation sub-plan component of the Local Disaster Managment Plan should be reviewed, including any identified triggers for activation. Ideally, the plan should be tested in a live, multi-agency exercise prior to next summer. |
REC271-1531 | 32 - Doctrine, standards, and reform | Banana Shire Council completes business continuity planning as a matter of priority, including documentation and testing of the plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1149 | 15 - Inter-service cooperation | PES External Surge Program The success of the PES External Surge Program and the willingness of participants to deploy at short notice to support the recovery effort is commendable, as is the readiness of their supervisors to release them from their duties to enable deployment. The Program, supported by an appropriate training program, is one that should be sustained as part of the whole of Government recovery readiness effort. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC235-2809 | 32 - Doctrine, standards, and reform | The Australian National Audit Office recommends that the Department of Regional Australia, Local Government, Arts and Sport improve the arrangements for conducting value for money reviews of Victorian reconstruction projects by pursuing amendments to the operating protocol with Victoria to require that, at regular intervals, the Taskforce is provided with information on all reconstruction projects being delivered within the scope of the National Partnership Agreement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2811 | 32 - Doctrine, standards, and reform | In order to maximise the envisaged benefits from the Inspectorate’s program of value for money reviews, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce improve the application of the sampling approach to make it more representative of the |
REC234-2810 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Australian Government Reconstruction Inspectorate and the National Disaster Recovery Taskforce seek to maximise the benefits from their value for money review activities by obtaining more timely and comprehensive information on project progress and completion from the Queensland Reconstruction Authority, to enable the preliminary value for money assessments to be finalised based on the scope and cost of works that were actually delivered (rather than estimates). |
REC234-2813 | 38 - Agency/Department Reporting | To strengthen its oversight of Queensland reconstruction progress, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3308 | 32 - Doctrine, standards, and reform | Volumes of cement used in connection with barrier installation should be calculated with the assistance of a pro‐forma which records all relevant baseline data, which should be verified by onshore personnel. |
REC177-3325 | 32 - Doctrine, standards, and reform | Relevant personnel from licensees and rig operators should meet face to face to agree on, and document, well control issues/arrangements prior to commencement of drilling operations. Well control should be regarded as a so‐called SIMOP to signify its critical importance to both licensees and rig operators, and to ensure that they each take responsibility for achievement and maintenance of well control. |
REC177-3354 | 32 - Doctrine, standards, and reform | NOPSA develop a policy of engagement with operators so as to enable experts (including safety experts) to canvas all available options for well control in the event of a blowout. |
REC177-3290 | 38 - Agency/Department Reporting | The successful installation of every barrier should be the subject of written verification within and between licensees and rig operators; and should be the subject of explicit reporting to the relevant regulator(s). |
REC177-3314 | 32 - Doctrine, standards, and reform | Secondary barriers (including PCCCs) should only be installed, tested, and removed with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3363 | 32 - Doctrine, standards, and reform | DEWHA, in concert with AMSA and with expert input, should develop ‘off the shelf’ monitoring programs that can be speedily implemented following incidents in Commonwealth waters. In this context, the utility of the current Scientific Monitoring program should be peer reviewed to inform future policy. |
REC177-3300 | 32 - Doctrine, standards, and reform | Licensees and rig operators should install an additional barrier whenever (i) there is any real doubt as to the integrity of any barrier; (ii) whenever the risk of flow from a reservoir increases materially in the course of operations; and (iii) where the consequences of a blowout are grave (for example, for reef systems or shorelines). |
REC177-3319 | 32 - Doctrine, standards, and reform | Drilling programs dealing with barrier installation should incorporate relevant aspects of manufacturer’s instructions. |
REC177-3341 | 32 - Doctrine, standards, and reform | The definition of ‘good oilfield practice’ in the OPGGS Act is unduly narrow. The current definition is incapable of application except where things ‘are generally accepted as good and safe’. The definition should be amended such that ‘good oilfield practice includes…’. |
REC177-3373 | 32 - Doctrine, standards, and reform | Arrangements should be developed to minimise duplication between the EPBC Act and the OPGSS Act Environment Regulation. |
REC177-3277 | 32 - Doctrine, standards, and reform | The concept of ‘good oilfield practice’ should be supplemented by the requirement to incorporate into WOMPs non‐exhaustive minimum compliance standards in relation to well control: for example, stipulations as to when BOPs and/or well control systems must be in place and when they can be removed and minimum barrier requirements (a number of other factors that should be stipulated are outlined in other recommendations below). |
REC177-3307 | 32 - Doctrine, standards, and reform | Any indication of a compromised cemented shoe which cannot be resolved with a high measure of confidence should result in the installation of additional well control barrier(s). |
REC177-3324 | 32 - Doctrine, standards, and reform | The mere fact that the rig is over the platform should not be regarded by licensees or regulators as sufficient justification for reliance on only one barrier. The default position should be that producible wells are shut‐in when a rig is moved on and off a platform, or when a drilling unit is moved between wells on a platform. |
REC177-3353 | 32 - Doctrine, standards, and reform | The regulatory regime should also impose an obligation on an operator to ascertain the availability, and provide details to the regulator, of any potential relief well rigs, prior to the commencement of drilling operations (including prior to each phase of a drilling operation where applicable). |
REC177-3287 | 38 - Agency/Department Reporting | Licensees should be subject to an express obligation to inform regulators of problems which arise in the course of installing barriers, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. |
REC177-3313 | 32 - Doctrine, standards, and reform | Barriers should not be installed or removed off‐line. The derrick should be located over a well at the time of removal and installation of any barrier. This will enable more decisive action to be taken in the event a problem arises. |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3362 | 32 - Doctrine, standards, and reform | Procedures for the approval of development projects should ensure that conditions of approval are comprehensive and clearly set out the obligations of their proponents in relation to environmental matters (including expected monitoring and remediation obligations). |
REC177-3298 | 32 - Doctrine, standards, and reform | Reliance upon one barrier against a blowout must not take place except with the prior written approval of the relevant regulator and then only in a true emergency situation (see below). |
REC177-3318 | 32 - Doctrine, standards, and reform | Manufacturers should be consulted about how to address non‐routine operational problems affecting their well control equipment. |
REC177-3340 | 32 - Doctrine, standards, and reform | To better ensure that ‘risks’ are identified and managed in accordance with sound engineering principles and good oilfield practice, it is recommended that regulation 25(1)(a)(i) and (2)(a)(i) of the Management of Well Operations Regulations, be reworded as follows: ‘A titleholder must not commence / continue a well activity if…a well integrity hazard exists in relation to the well’. |
REC177-3370 | 32 - Doctrine, standards, and reform | Environment plans and OSCPs should be made publicly available as a condition of approval of proposals under the OPGGS Act, and should clearly set out Scientific Monitoring requirements in the event of an oil spill. |
REC177-3276 | 32 - Doctrine, standards, and reform | WOMPs should be comprehensive and freestanding, rather than an overarching document cross‐referencing many other documents (although the Inquiry also recommends a freestanding well control manual; this should be a guide to rig and onshore personnel on good oilfield practice). |
REC177-3306 | 32 - Doctrine, standards, and reform | It should be standard industry practice to re‐test a cemented casing shoe (that is, after WOC) whenever the plugs do not bump or the float valves apparently fail. Standard industry practice should require consideration of other tests in addition to a repeat pressure test. |
REC177-3323 | 32 - Doctrine, standards, and reform | Where multiple wells are drilled, operations and occurrences at one well must be carefully assessed for any implications with respect to well control at other wells. |
REC177-3352 | 32 - Doctrine, standards, and reform | The regulator, rather than the responsible Minister, should be given the power to direct an operator to use a particular rig for the purpose of well control operations, if appropriate in the circumstances, and the power should be used in the future if that rig is the best option available. This would necessarily involve the operator fully compensating for the use of the rig and any other associated costs. The Inquiry suggests that this power could be invoked and given effect as a condition of an operator’s licence. |
REC177-3284 | 32 - Doctrine, standards, and reform | Memoranda of Agreement should be entered into between operators in relation to provision of emergency assistance in the event of blowouts. |
REC177-3312 | 32 - Doctrine, standards, and reform | The BOP and rig should not move from a well until barrier integrity has been verified. |
REC177-3328 | 32 - Doctrine, standards, and reform | All communications between on‐rig and onshore personnel relating to well control should be documented in a timely manner. |
REC177-3361 | 32 - Doctrine, standards, and reform | The National Plan should be revised to ensure that it fully comprehends environmental matters and that it recognises the importance of the prompt implementation of Scientific Monitoring to facilitate the assessment of the environmental impacts of an incident. |
REC177-3297 | 32 - Doctrine, standards, and reform | A minimum of two barriers should be in place at all times (including during batched operations) whenever it is reasonably practicable to do so. |
REC177-3317 | 32 - Doctrine, standards, and reform | Any equipment (including PCCCs) used as, or to install, a barrier should be manufactured for that purpose and be generally recognised as fit for purpose. If equipment is designed in‐house by a licensee or rig operator it should not be approved for use unless and until it is subjected to expert external analysis. |
REC177-3339 | 32 - Doctrine, standards, and reform | The Inquiry supports the objective (rather than prescriptive) approach to regulation now followed in Australia. However, the pendulum has swung too far away from prescriptive standards. In some areas relating to well integrity there needs to be minimum standards. |
REC177-3368 | 32 - Doctrine, standards, and reform | The regulatory framework should provide that in respect of all activities in Commonwealth waters: |
REC177-3275 | 32 - Doctrine, standards, and reform | Well Operations Management Plan (WOMPs) submitted by licensees to the regulator(s) should continue to be the primary framework document for achieving well integrity. |
REC177-3305 | 32 - Doctrine, standards, and reform | Cement integrity should be evaluated wherever practicable by way of cement evaluation tests, rather than relying on pre‐operational calculations of cement and displacement fluid volumes. |
REC177-3322 | 32 - Doctrine, standards, and reform | Batched drilling operations should only be undertaken after careful assessment of the special risks which such operations give rise to; well control must be maintained during the course of batched drilling operations. |
REC177-3350 | 32 - Doctrine, standards, and reform | The recommendations of the Inquiry in relation to suitable ways of achieving well integrity contained in Chapter 3 be included in a guidance manual that is issued for the assistance of industry and regulators. |
REC177-3283 | 32 - Doctrine, standards, and reform | A separate, identifiable barrier manual should be agreed upon and used by licensees, rig operators, and cementing contractors. These manuals should set out best industry practice in relation to achieving and maintaining well integrity. They should describe barrier types, barrier standards, general principles of well integrity, testing and verification methods and technologies, standard operating procedures (including procedures for the capture and communication of relevant information within and between relevant stakeholder entities). Barrier manuals should address blowout control during drilling, completion, re‐entry, tie‐back of casing strings and so on. Barrier manuals should be the subject of expert external review, and should be regularly updated. |
REC177-3311 | 32 - Doctrine, standards, and reform | Horizontal or high angle penetration of a reservoir should be avoided wherever practicable until such time as the apparent problems associated with the cementing of a casing shoe in these situations are satisfactorily overcome. If a casing string does penetrate a well horizontally or at a high angle, standard practice should be to install two secondary barriers in addition to the cemented casing shoe. |
REC177-3327 | 32 - Doctrine, standards, and reform | Information relevant to well control must be captured and communicated within and between licensees and rig operators (and relevant third party contractors), in a manner which ensures it comes to the attention of relevant personnel. In particular, protocols should be developed to ensure that changes in shift and hitch do not operate as communication barriers. |
REC177-3359 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed to clarify the arrangements to apply in Commonwealth waters regarding key roles and responsibilities, including in relation to the ESC, in the event of an oil spill. This should also address any necessary training required. |
REC177-3296 | 32 - Doctrine, standards, and reform | Use of single strings of intermediate casing to penetrate hydrocarbon bearing zones should be carefully risk assessed. Multiple strings of intermediate casing have the advantage of isolating lost circulation zones and sealing off anomalous pressure zones. If intermediate casing is set in a hydrocarbon zone it should be treated as production casing. |
REC177-3316 | 32 - Doctrine, standards, and reform | Wells should be re‐entered with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3335 | 32 - Doctrine, standards, and reform | Licensees, rig operators and relevant third party contractors should develop well control competency standards for key personnel in other entities involved in well control operations. |
REC177-3367 | 32 - Doctrine, standards, and reform | Procedures and accountabilities should be established to ensure, in the event of a future incident, that: |
REC177-3302 | 32 - Doctrine, standards, and reform | Industry, regulators, and training/research institutions should develop standards that address best practices for cementing operations (including liaising, as appropriate, with overseas regulators) with a view to overcoming problems which can effect the integrity of cemented casing shoes, annulus and cement plugs. |
REC177-3320 | 32 - Doctrine, standards, and reform | Any pro‐formas used by licensees, rig operators and contractors for recording information about installation of barriers should explicitly provide for ‘exception reporting’, that is, the form should include provision for recording any unforseen or untoward events which occur in the course of installation. |
REC177-3343 | 32 - Doctrine, standards, and reform | The OPGGS Act should be amended to allow for a power to suspend a petroleum production licence (in addition to the current power to cancel a licence or suspend its conditions). |
REC177-3280 | 32 - Doctrine, standards, and reform | Well construction and management plans should include provision for an independent compliance review of well integrity (i) in the event of stipulated triggers; and (ii) at least once in the period between perceived achievement of well integrity and production. The independent compliance review should be undertaken by an expert who is not involved in the day‐to‐day drilling operations. Reviews should be completed in sufficient time to enable results to be implemented in a meaningful manner. |
REC177-3309 | 32 - Doctrine, standards, and reform | If performance of barrier installation is outsourced by a licensee, the contractor (for example, the cementing company) should be engaged on terms which clearly require the provision of expert advisory services by the contractor with respect to barrier integrity. |
REC177-3326 | 32 - Doctrine, standards, and reform | Prior to commencement of drilling operations, senior representatives of the licensee and rig operator should exchange certificates to the effect that their respective key personnel and contractors have been informed in writing of agreed well control arrangements. |
REC177-3355 | 32 - Doctrine, standards, and reform | The Inquiry also supports Bills and Agostini’s recommendation: ‘…in relation to safety case development and compliance overall, that NOPSA revise its approach to interacting with operators prior to the safety case assessment process and subsequently direct more resources into its advisory functions. We further recommend that NOPSA develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on the latest information, including the interaction with the operator’. |
REC177-3292 | 32 - Doctrine, standards, and reform | Licensees should be subject to an express obligation to inform regulators of the proposed removal of a barrier, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. Removal of a barrier should not take place without prior written approval of the relevant regulator(s). |
REC177-3315 | 32 - Doctrine, standards, and reform | PCCCs should be installed in a timely manner (for example, to prevent corrosion in the MLS apparatus). Non‐installation in order to park a BOP is not acceptable. |
REC177-3334 | 32 - Doctrine, standards, and reform | Licensees, rig operators, and relevant third party contractors should develop well control competency standards for their key personnel. Wherever possible, the competencies of key personnel should be benchmarked against their roles and responsibilities. |
REC177-3366 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed: |
REC177-3301 | 32 - Doctrine, standards, and reform | The industry standard of two barriers should be replaced with the concept of ‘two or more barriers’ as a minimum standard. A minimum standard when operations proceed normally should never be regarded as a sufficient standard in other circumstances. |
REC177-3342 | 32 - Doctrine, standards, and reform | Written (rather than verbal) approval from the DA (or new regulator) should be obtained before the commencement of well activities that lead to a physical change of a wellbore, other than in a true emergency situation (requiring amendment to regulation 17 of the Management of Well Operations Regulations). |
REC177-3377 | 32 - Doctrine, standards, and reform | The Minister consider legislative amendments to the OPGGS Act which make clear that |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0072 | 32 - Doctrine, standards, and reform | SERCon consider that the proposed State Recovery Committee review the recommended considerations arising from |
REC164-0077 | 32 - Doctrine, standards, and reform | SERCon consider the continued development of a State Recovery Sub-Plan (including complementary local and district |
REC164-0071 | 32 - Doctrine, standards, and reform | SERCon consider the establishment of a body, such as a State Recovery Committee, with responsibility for the |
REC164-0076 | 32 - Doctrine, standards, and reform | SERCon consider meeting with the State Emergency Management Committee, Directors General and agency heads to |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
REC125-3895 | 32 - Doctrine, standards, and reform | That all agencies develop drainage asset management plans, consistent with best practice, and that these incorporate: |
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |