Rec-ID | Code | Recommendation |
---|---|---|
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4302 | 32 - Doctrine, standards, and reform | Disaster adaptation plans for all towns: That, to establish realistic expectations of safe spaces to live and deliver much needed housing quickly, Government through NSWRA working with local government: |
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4301 | 32 - Doctrine, standards, and reform | Floodplains as assets: That, to establish the capacity and maximise the economic, social and environmental potential and consequently unlock the value of NSW floodplains, Government adopt the following guiding principles for floodplain management: |
REC324-4317 | 32 - Doctrine, standards, and reform | Flood rescue capability: That, to help improve the protection of life across NSW in flood events: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4266 | 1 - Land-use and building regs | That the NSW Government review the provision of temporary and long term housing options provided to those affected by the February-March 2022 floods, with a view to: • ensuring a range of options are identified and embedded within emergency and recovery plans, so that solutions can be implemented as soon as possible after a natural disaster • ensuring that housing options meet individual and community needs • removing planning impediments that prevent those from accessing more safe and secure housing in times of crisis. |
REC323-4267 | 1 - Land-use and building regs | That the NSW Government consider investing in supporting relocations, land swaps and providing fair and adequate compensation for landowners who wish to relocate from severely flood-impacted areas. |
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
REC323-4257 | 1 - Land-use and building regs | That the NSW Government work with local government, industry and sustainable planning experts, including the Government Architect, on policy initiatives in the New South Wales planning system that will help deliver more resilient and sustainable homes, buildings and places. |
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4001 | 35 - Business and Industry in relation to industry | The Commission consider that in all mines where gas exists the course of the air should be directed to sweep along the working-faces; in mines worked by Pillar and Stall, bratticing must be resorted to to carry the gas from the face as it issues, and so prevent any accumulation of explosive gases or of gases inimical to life. In cases where gas exists it would be better that no bords should be broken off the back or return heading or supplied with air fouled by dangerous gases. The panel system of working by confining and localising districts, or some modification thereof, might be pursued with advantage. |
REC002-4011 | 32 - Doctrine, standards, and reform | The Commission feel that the 4th clause in the present Act, relating to the spacing of cut-throughs, should be amended to admit of any convenient or safe system of mining being pursued. This is a matter of detail that would be better out of the Act. The Commission would advise that the word should not occur at all, and that, if bratticing be used, or the air by some other satisfactory device be conveyed to the face, scope would be given to Managers to introduce systems of mining adapted to the circumstance of each particular coal-seam, with advantage to all concerned. |
REC002-4010 | 35 - Business and Industry in relation to industry | The Commission do not approve of removing any responsibility from the management by increasing the power or number of the Inspectors. The visits of these officials should, so far as possible, be visits of surprise. |
REC002-4008 | 35 - Business and Industry in relation to industry | Where dust exists in quantity, and under conditions favourable for ignition, it should be periodically and sufficiently dampened by water |
REC002-4004 | 35 - Business and Industry in relation to industry | Where safety-lamps are used, and the obligation is laid upon the men to cleanse the same, all examinations, tests, and repairs to these should be done by the owners. |
REC002-4003 | 35 - Business and Industry in relation to industry | Where gas exists, and no provisions are made for its constant removal, no shots should be fired, and, where permitted in a gassy mine, shots should be fired only by a man specially appointed, and at such hours when the miners are not within the mine. All shots should be tamped by stone well damped, and only copper or wooden tools should be employed. As far as possible the use of explosives should be discouraged, and skilful mining encouraged. Danger-boards should be placed further from the faces whence gas issues (say), where practicable, 50 yards. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1257 | 35 - Business and Industry in relation to industry | That in the event that Hydro Tasmania decides to start cloud seeding again, water managers, represented by DPIPWE, work with Hydro Tasmania to ensure appropriate, best practice application of the guidelines issued by the Agricultural and Resource Management Council of Australia and New Zealand. |
REC297-1269 | 35 - Business and Industry in relation to industry | That Government engages with non-government organisations that may provide services during emergency events to clarify the terms and conditions for support through a written arrangement (MOU or similar). |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1260 | 32 - Doctrine, standards, and reform | That DPIPWE clarifies responsibility for river restoration and riparian management and, having done so, communicates this to councils, landowners and other owners of relevant infrastructure. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1532 | 32 - Doctrine, standards, and reform | The evacuation sub-plan component of the Local Disaster Managment Plan should be reviewed, including any identified triggers for activation. Ideally, the plan should be tested in a live, multi-agency exercise prior to next summer. |
REC271-1531 | 32 - Doctrine, standards, and reform | Banana Shire Council completes business continuity planning as a matter of priority, including documentation and testing of the plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2533 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority: |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2555 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority changes the current two-tier regulatory framework (act and regulations) to a three-tier structure (act, regulations and standards), with: |
REC258-2531 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority’s Board exercises full governance control. The nonexecutive directors should possess a range of appropriate skills and backgrounds in aviation, safety, management, risk, regulation, governance and government. |
REC258-2538 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development and Department of Defence (and appropriate agencies) establish an agreed policy position on safety oversight of civil operations into joint user and military airports. |
REC258-2554 | 32 - Doctrine, standards, and reform | Recreational Aviation Administration Organisations, in coordination with the Civil Aviation Safety Authority, develop mechanisms to ensure all aircraft to be regulated under CASR Part 149 are registered. |
REC258-2529 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority utilise the provision in their bilateral Memorandum of Understanding to accredit CASA observers to ATSB investigations. |
REC258-2537 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority delegates responsibility for the day-to-day operational management of airspace to Airservices Australia, including the designation of air routes, short term designations of temporary Restricted Areas, and temporary changes to the classification of airspace for operational reasons. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2536 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority amend the wording of their existing Memorandum of Understanding to make it more definitive about interaction, coordination, and cooperation. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2527 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development plays a stronger policy role in the State Safety Program. |
REC258-2562 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority amends the current Terms of Reference of the Industry Complaints Commissioner so that: |
REC258-2535 | 32 - Doctrine, standards, and reform | Airservices Australia, in conjunction with the Department of Infrastructure and Regional Development and the Civil Aviation Safety Authority, reconsiders the policy on ‘Assessment of Priorities’ that stipulates that air traffic controllers sequence arriving aircraft based on category of operation, rather than on the accepted international practice of ‘first come, first served’. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
REC236-2789 | 32 - Doctrine, standards, and reform | The committee recommends that the Transport Safety Investigation Act 2003 be amended to require that the Chief Commissioner of the ATSB be able to demonstrate extensive aviation safety expertise and experience as a prerequisite for the selection process. |
REC236-2796 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB-CASA Memorandum of Understanding be re-drafted to remove any ambiguity in relation to information that should be shared between the agencies in relation to aviation accident investigations, to require CASA to: |
REC236-2804 | 32 - Doctrine, standards, and reform | The committee recommends that Airservices Australia discuss the safety case for providing a hazard alert service with Fijian and New Zealand ATC (and any other relevant jurisdictions) and encourage them to adopt this practice. |
REC236-2786 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB be required to document investigative avenues that were explored and then discarded, providing detailed explanations as to why. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2803 | 32 - Doctrine, standards, and reform | The committee recommends that the government consider setting a time limit for agencies to implement or reject recommendations, beyond which ministerial oversight is required where the agencies concerned must report to the minister why the recommendation has not been implemented or that, with ministerial approval, it has been formally rejected. |
REC236-2785 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB move away from its current approach of forecasting the probability of future events and focus on the analysis of factors which allowed the accident under investigation to occur. This would enable the industry to identify, assess and implement lessons relevant to their own operations. |
REC236-2794 | 32 - Doctrine, standards, and reform | The committee recommends that CASA, in consultation with an Emergency Medical Services industry representative group (eg. Royal Flying Doctor Service, air ambulance operators, rotary wing rescue providers) consider the merit, form and standards of a new category of operations for Emergency Medical Services. The minister should require CASA to approve the industry plan unless there is a clear safety case not to. Scope for industry to assist as part of an audit team should also be investigated where standardisation is an issue. This should be completed within 12 months and the outcome reported publicly. |
REC236-2802 | 32 - Doctrine, standards, and reform | The committee recommends that where the consideration and implementation of an ATSB recommendation may be protracted, the requirement for regular updates (for example 6 monthly) should be included in the TSI Act. |
REC236-2784 | 32 - Doctrine, standards, and reform | The committee recommends that the minister, in issuing a new Statement of Expectations to the ATSB, valid from 1 July 2013, make it clear that safety in aviation operations involving passengers (fare paying or those with no control over the flight they are on, e.g. air ambulance) is to be accorded equal priority irrespective of flight classification. |
REC236-2807 | 32 - Doctrine, standards, and reform | The committee recommends that the Aeronautical Information Package (AIP) En Route Supplement Australia (ERSA) is updated to reflect the need for caution with regard to Norfolk Island forecasts where the actual conditions can change rapidly and vary from forecasts. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2798 | 32 - Doctrine, standards, and reform | The committee recommends that, where relevant, the ATSB include thorough human factors analysis and discussion in future investigation reports. Where human factors are not considered relevant, the ATSB should include a statement explaining why. |
Rec-ID | Code | Recommendation |
---|---|---|
REC235-2809 | 32 - Doctrine, standards, and reform | The Australian National Audit Office recommends that the Department of Regional Australia, Local Government, Arts and Sport improve the arrangements for conducting value for money reviews of Victorian reconstruction projects by pursuing amendments to the operating protocol with Victoria to require that, at regular intervals, the Taskforce is provided with information on all reconstruction projects being delivered within the scope of the National Partnership Agreement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2811 | 32 - Doctrine, standards, and reform | In order to maximise the envisaged benefits from the Inspectorate’s program of value for money reviews, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce improve the application of the sampling approach to make it more representative of the |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2855 | 32 - Doctrine, standards, and reform | I recommend that arrangements be put in place which would remove the requirements for Masters of Volunteer Marine Rescue vessels to hold a commercial certificate of competency. Operators could then be qualified through the FESA Volunteer Marine Rescue Training pathway as skippers and crew. This would increase the number of available skippers in the event of a search and rescue incident and would make appropriate training easier to arrange. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0622 | 1 - Land-use and building regs | If, as part of a state interest review process, the Department of Local Government and Planning decides that no condition should be imposed requiring a council’s proposed planning scheme to incorporate the effect of the Department of Community Safety’s comments about State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide, it should advise the Department of Community Safety of the reasons for its decision. |
REC210-0640 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0666 | 1 - Land-use and building regs | The Queensland Government should draft a model planning scheme policy to be included in the model flood planning controls that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0697 | 1 - Land-use and building regs | Queensland Rail and QR National should continue to investigate opportunities for increasing the flood resilience of their networks, including raising the height of critical equipment. |
REC210-0763 | 35 - Business and Industry in relation to industry | Seqwater should ensure that the Somerset Dam gallery is not susceptible to flooding during overtopping events. |
REC210-0627 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to require that consideration be given to the risk of flooding in the preparation or revision of a regional plan. |
REC210-0647 | 1 - Land-use and building regs | The Department of Environment and Resource Management should ensure that, when applications for a material change of use for an environmentally relevant activity are approved by the department, the details of those activities, including their nature and location, are provided to the council within whose area the activity will be conducted. |
REC210-0676 | 1 - Land-use and building regs | Authorities responsible for the construction of sewerage infrastructure should, when embarking on new works, undertake risk and cost/benefit assessments to determine the level at which electrical infrastructure that may be vulnerable to inundation should be placed. |
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0634 | 1 - Land-use and building regs | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include in their planning schemes a planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as a part of the development application, or • for development proposed on land where potential for flooding is unknown requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information to allow an assessment of the flood risk. |
REC210-0657 | 1 - Land-use and building regs | Levees should be regulated. |
REC210-0690 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0611 | 1 - Land-use and building regs | For urban areas or areas where development is expected to occur: a. councils with the requisite resources should develop a flood map which shows ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. councils without the requisite resources to produce a flood behaviour map should develop a flood map which shows the extent of floods of a range of likelihoods (at least three). |
REC210-0621 | 1 - Land-use and building regs | The Queensland Government should: a. narrow the definition of ‘development commitment’ in State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide to ensure more development applications are assessed for compatibility with flood, and b. investigate whether the compensation provisions of the Sustainable Planning Act 2009 act as a deterrent to the inclusion of flood controls in a planning scheme and consider whether they ought be amended. |
REC210-0639 | 1 - Land-use and building regs | The Queensland Government should consider extending the application of a state planning policy dealing with flood to the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood. |
REC210-0662 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0626 | 1 - Land-use and building regs | Councils should consider using the limited development (constrained land) zone in their planning schemes for areas that have a very high flood risk. |
REC210-0646 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend the template assessment report used to assess applications for a material change of use for environmentally relevant activities so that it prompts departmental officers to give specific consideration, as part of the assessment process, to the risk of flooding at the site where the activity is proposed to occur. |
REC210-0675 | 1 - Land-use and building regs | The Queensland Government should consider including in the criteria in the Queensland Plumbing and Wastewater Code a requirement that the risk of leakage from private on-site sewerage systems during floods be minimised. |
REC210-0708 | 35 - Business and Industry in relation to industry | The Queensland Government should work collaboratively with the Commonwealth Government and mine operators to ensure co-ordinated and effective monitoring of salts, metals and other contaminants in marine environments that may be affected by mine discharges. |
REC210-0633 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as part of the development application, or • for development proposed on land where the potential for flooding is unknown, requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information, to allow an assessment of the flood risk. |
REC210-0656 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Regulation 2009 so that operational work or plumbing or drainage work (including maintenance and repair work) carried out by or on behalf of a public sector entity authorised under a state law to carry out the work is not exempt development under the Sustainable Planning Act 2009 if the development has the potential to reduce floodplain storage. |
REC210-0685 | 1 - Land-use and building regs | In assessing and determining development applications for material change of use in areas susceptible to flood, councils should consider whether the new developments locate essential services infrastructure above basement level, or, alternatively, whether essential services infrastructure located at basement level can be constructed so that it can continue to function during a flood. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0617 | 1 - Land-use and building regs | The Queensland Government should consider implementing a mechanism by which prospective purchasers of property are alerted to the issue of flood risk. To that end, the Queensland Government should consider consulting the Real Estate Institute of Queensland and the Law Society of Queensland as to the appropriateness of amending standard contract conditions so as to include a ‘subject to flood search’ condition, or other means of achieving the same objective. |
REC210-0638 | 1 - Land-use and building regs | The Coordinator-General should amend the guideline for preparing an ‘initial advice statement’ for a significant project under the State Development and Public Works Organisation Act 1971 so that it specifically requires an applicant to consider and provide information about the project’s flood risk. |
REC210-0661 | 1 - Land-use and building regs | There should be a common set of considerations in the decision whether to approve an application to build a levee, including: • the impacts of the proposed levee on the catchment as a whole • the benefits of the proposed levee to the individual or entity applying to build the levee and to any nearby community as a whole • any adverse impacts on other landholders, including the risk of levee failure • the implications of the proposed levee for land planning and emergency management procedures • whether any structural, land planning or emergency management measures can be taken to mitigate the adverse impacts of the proposed levee. |
REC210-0694 | 1 - Land-use and building regs | The Queensland Government should consider whether there should be a legislative requirement that customer dedicated assets be built at or above the applicable defined flood level and if so, the Queensland Government should consider which legislation should contain such a requirement. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
REC210-0625 | 1 - Land-use and building regs | The Queensland Government should change Temporary State Planning Policy 2/11: Planning for stronger more resilient floodplains to remove the possibility of councils’ using the interim floodplain assessment overlay mapping and Model Code as part of a permanent amendment to their existing planning scheme or as part of a new planning scheme. |
REC210-0645 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend its information sheet about applications for a material change of use for environmentally relevant activities so that applicants are prompted to include information (if any) about the risk of flooding at the site where the activity is proposed to occur. |
REC210-0674 | 1 - Land-use and building regs | The Queensland Government should consider amending the ‘Limitation’ section of the proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, to allow for the possible application of ‘acceptable solution A1’ to a building located on a lot if: • it is reasonable to expect the part of the lot on which the building work is proposed to be subjected to a maximum velocity of less than 1.5 metres per second, or • the part of the lot on which the building work is proposed is located in an inactive flow or backwater area. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0631 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0654 | 1 - Land-use and building regs | The Queensland Government should consider drafting assessment criteria to be included in the model flood planning controls which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the applicable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms) • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0684 | 1 - Land-use and building regs | Councils should consider amending their planning schemes to include provisions directed to consideration of the flood resilience of basements as a factor in determining the appropriateness of a material change of use. |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0637 | 1 - Land-use and building regs | The Queensland Government should consider amending the Urban Land Development Authority Act 2007, the South Bank Corporation Act 1989, the State Development and Public Works Organisation Act 1971 insofar as it governs state development areas, and other legislation which establishes alternative planning systems that operate independently of the Sustainable Planning Act 2009, to require that: • any planning scheme, interim or otherwise, appropriately reflects any state planning policy with respect to flood • flood risk be considered in the assessment of any development application. |
REC210-0660 | 1 - Land-use and building regs | There should be a consistent process for the determination of applications to build levees. That process should include: • consulting landholders who may be affected by the proposed levee • obtaining or commissioning appropriate hydrological and hydraulic studies to assess the impacts of the proposed levee. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0616 | 1 - Land-use and building regs | Councils that do not currently do so should consider offering an online database which allows the public to conduct a search on a parcel of land to find development approvals relevant to that parcel of land. |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0624 | 1 - Land-use and building regs | The Queensland Government should ensure that the circumstances in which the Department of Community Safety is to consult the Department of Environment and Resource Management about a planning scheme’s flood modelling and flood mapping are clear. |
REC210-0644 | 1 - Land-use and building regs | The Queensland Government should ensure that the criteria under the Environmental Protection Act 1994 that apply to the assessment of development applications for material change of use for environmentally relevant activities include consideration of the risk of flooding at the site on which the activity is proposed to occur. |
REC210-0673 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirements about utilities and sanitary drains (Performance Requirement P2 and P3) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0629 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a requirement that councils have a flood overlay map in their planning schemes. The map should identify the areas of the council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0652 | 1 - Land-use and building regs | The Queensland Government should review the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003 to consider whether the design and construction standards should be made more stringent than the existing standards. |
REC210-0682 | 1 - Land-use and building regs | The Department of Environment and Resource Management should review the Queensland Urban Drainage Manual to determine whether it requires updating or improvement, in particular, to reflect the current law and to take into account insights gained from the 2010/2011 floods. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0636 | 1 - Land-use and building regs | The Queensland Government should consider allowing councils to amend a planning scheme to update existing flood mapping information by way of the minor amendment process, provided that adequate public consultation has occurred. |
REC210-0659 | 1 - Land-use and building regs | The Queensland Government should consult with councils to formulate a definition of ‘levee’ to identify what should be regulated. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0613 | 1 - Land-use and building regs | Councils should ensure that areas for which there has been no assessment of the likelihood of flooding are indicated on a map and that, as part of the development assessment process for these, there is at least some enquiry into whether a site proposed for development could be subject to flooding. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0623 | 1 - Land-use and building regs | The Department of Community Safety should put in place administrative arrangements which ensure it can readily ascertain whether its comments are being reflected in council planning schemes. If the Department of Community Safety becomes aware that its comments are not being adequately addressed, it should take steps to follow this up with the Department of Local Government and Planning. |
REC210-0642 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require the impact of flood on commercial property to be minimised. |
REC210-0672 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirement relating to building design and construction (Performance Requirement P1) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot, and • either: – declared a velocity to be the expected maximum velocity of flood water for the area in which the lot is located, or – designated the area in which the lot is located an inactive flow or backwater area. |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0628 | 1 - Land-use and building regs | The Queensland Government should draft model flood planning controls, using a similar format and structure to that in the Queensland Planning Provisions, that councils can adapt for local conditions. The Queensland Government should require these controls to be reflected in new planning schemes. This may be achieved by including the controls in either: • a state planning policy dealing with flood, with an accompanying amendment to the Sustainable Planning Act 2009, or • the Queensland Planning Provisions. The Queensland Government should consult councils to determine which of the two state planning instruments is the more appropriate to include the model flood planning controls. |
REC210-0649 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters. |
REC210-0677 | 1 - Land-use and building regs | Authorities responsible for the management of sewerage infrastructure should conduct a review of their existing infrastructure to identify electrical infrastructure that may be vulnerable to inundation and perform risk and cost/benefit assessments to determine if it should be relocated to a higher level. |
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0635 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to expressly provide either a power to remake or a power to extend a temporary local planning instrument containing interim flood regulation for a further limited period. The power to remake or extend should: a. permit the modification of the temporary local planning instrument to the extent required to ensure its provisions remain relevant, having regard to any requirement that may have been introduced or any information that may have become available while the original temporary local planning instrument was in force b. be contingent on the Minister’s being satisfied that the circumstances listed in section 105 of the Sustainable Planning Act continue to exist and that there are proper grounds for the failure to make a permanent scheme amendment while the original temporary local planning instrument was in force. |
REC210-0658 | 1 - Land-use and building regs | The Queensland Government should consult with councils to determine an effective method for the regulation of the construction of levees in Queensland. In particular, the Queensland Government should consider: • requiring a development permit for the construction of a levee by designating levees as assessable development in the Sustainable Planning Regulation 2009, or • requiring, by way of a state planning policy or mandatory provision in the Queensland Planning Provisions, that councils nominate the construction of a levee as assessable development in their planning schemes. |
REC210-0691 | 1 - Land-use and building regs | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0612 | 1 - Land-use and building regs | For non-urban areas or areas where limited development is expected to occur councils should consider, on a risk basis, what level of information about flood risk is required for the area, and undertake the highest ranked of the following options which is appropriate to that need and within the capacities (financial and technical) of the council: a. a map showing ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. a map showing the extent of floods of a range of likelihoods (at least three) c. a flood map based on historic flood levels that have been subjected to a flood frequency analysis to estimate the annual exceedance probability of the selected historical flood d. a historic flood map without flood frequency analysis e. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay as a way to determine those areas for which further flood studies are required, or f. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay (preferably refined using local flood information) as a trigger for development assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
REC208-0530 | 32 - Doctrine, standards, and reform | That, if necessary, regulation be amended to require Health to approve any script used by any party concerned, for door knocking or other information dissemination, if Health is not the first source of information to affected residents. |
REC208-0529 | 32 - Doctrine, standards, and reform | That, when developing requirements concerning pollution incident response management plans pursuant to the recent legislative amendments, the Office of Environment and Hertiage include appropriate definitions as to the meaning of ‘immediately’, and when ‘material harm to the environment is caused or threatened’. |
REC208-0528 | 32 - Doctrine, standards, and reform | That, as part of the Pollution Incident Management Response Plan to be developed for Orica’s Kooragang Island site, or by another appropriate mechanism, the Office of Environment and Heritage ensure that Orica’s incident-response procedures address the need to consider all relevant factors when assessing potential impacts, including the height and force of emissions as well as the location of any onsite fallout and whether there are off-site impacts following all serious incidents. |
REC208-0527 | 35 - Business and Industry in relation to industry | That the Office of Environment and Heritage require Orica to engage and fund appropriate independent experts to oversee any modifications to the plant in the next major maintenance overhaul of the plant in 2016 and in any upgrades to the plant prior to that date. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0425 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform the control agency and the Bureau of Meteorology about the management and operation of dams and weirs consistent with the flood warning requirements of the relevant river systems, including providing telemetry at sites as necessary. This may require the state proactively liaising with other states to ensure equivalent obligations are placed on interstate dam operators where the dam may impact Victorian communities. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0424 | 35 - Business and Industry in relation to industry | the state require dam owners and operators to review storage operating manuals to incorporate lessons from the 2010–11 floods and make this information publicly available. The manuals should include a clear policy on dam surcharging and pre-release. |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0427 | 35 - Business and Industry in relation to industry | the state require dam owners and operators provide regular situational reports to the relevant control agency where dam issues may impact incident management. |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0426 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform people situated downstream of water storages if the owners/operators become aware of an immediate threat arising from the dam to the safety of those people. The owner/operators should provide this information as soon as the owner/operators become aware of the threat. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2914 | 32 - Doctrine, standards, and reform | The review team recommend that: |
REC189-2909 | 32 - Doctrine, standards, and reform | Equipping the regulator with a wider range of compliance tools under the legislation should continue to be a policy priority. The aim should be to enhance the regulator’s capacity to secure compliance in an appropriately graduated way. The opportunity should be taken to ensure that the regulator and inspectors can, in appropriate cases, bring proceedings that do not require referral to the Commonwealth Director of Public Prosecutions, such as actions for civil penalties or injunctions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3315 | 32 - Doctrine, standards, and reform | PCCCs should be installed in a timely manner (for example, to prevent corrosion in the MLS apparatus). Non‐installation in order to park a BOP is not acceptable. |
REC177-3334 | 32 - Doctrine, standards, and reform | Licensees, rig operators, and relevant third party contractors should develop well control competency standards for their key personnel. Wherever possible, the competencies of key personnel should be benchmarked against their roles and responsibilities. |
REC177-3362 | 32 - Doctrine, standards, and reform | Procedures for the approval of development projects should ensure that conditions of approval are comprehensive and clearly set out the obligations of their proponents in relation to environmental matters (including expected monitoring and remediation obligations). |
REC177-3292 | 32 - Doctrine, standards, and reform | Licensees should be subject to an express obligation to inform regulators of the proposed removal of a barrier, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. Removal of a barrier should not take place without prior written approval of the relevant regulator(s). |
REC177-3342 | 32 - Doctrine, standards, and reform | Written (rather than verbal) approval from the DA (or new regulator) should be obtained before the commencement of well activities that lead to a physical change of a wellbore, other than in a true emergency situation (requiring amendment to regulation 17 of the Management of Well Operations Regulations). |
REC177-3370 | 32 - Doctrine, standards, and reform | Environment plans and OSCPs should be made publicly available as a condition of approval of proposals under the OPGGS Act, and should clearly set out Scientific Monitoring requirements in the event of an oil spill. |
REC177-3276 | 32 - Doctrine, standards, and reform | WOMPs should be comprehensive and freestanding, rather than an overarching document cross‐referencing many other documents (although the Inquiry also recommends a freestanding well control manual; this should be a guide to rig and onshore personnel on good oilfield practice). |
REC177-3301 | 32 - Doctrine, standards, and reform | The industry standard of two barriers should be replaced with the concept of ‘two or more barriers’ as a minimum standard. A minimum standard when operations proceed normally should never be regarded as a sufficient standard in other circumstances. |
REC177-3325 | 32 - Doctrine, standards, and reform | Relevant personnel from licensees and rig operators should meet face to face to agree on, and document, well control issues/arrangements prior to commencement of drilling operations. Well control should be regarded as a so‐called SIMOP to signify its critical importance to both licensees and rig operators, and to ensure that they each take responsibility for achievement and maintenance of well control. |
REC177-3353 | 32 - Doctrine, standards, and reform | The regulatory regime should also impose an obligation on an operator to ascertain the availability, and provide details to the regulator, of any potential relief well rigs, prior to the commencement of drilling operations (including prior to each phase of a drilling operation where applicable). |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3284 | 32 - Doctrine, standards, and reform | Memoranda of Agreement should be entered into between operators in relation to provision of emergency assistance in the event of blowouts. |
REC177-3308 | 32 - Doctrine, standards, and reform | Volumes of cement used in connection with barrier installation should be calculated with the assistance of a pro‐forma which records all relevant baseline data, which should be verified by onshore personnel. |
REC177-3314 | 32 - Doctrine, standards, and reform | Secondary barriers (including PCCCs) should only be installed, tested, and removed with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3361 | 32 - Doctrine, standards, and reform | The National Plan should be revised to ensure that it fully comprehends environmental matters and that it recognises the importance of the prompt implementation of Scientific Monitoring to facilitate the assessment of the environmental impacts of an incident. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3319 | 32 - Doctrine, standards, and reform | Drilling programs dealing with barrier installation should incorporate relevant aspects of manufacturer’s instructions. |
REC177-3341 | 32 - Doctrine, standards, and reform | The definition of ‘good oilfield practice’ in the OPGGS Act is unduly narrow. The current definition is incapable of application except where things ‘are generally accepted as good and safe’. The definition should be amended such that ‘good oilfield practice includes…’. |
REC177-3368 | 32 - Doctrine, standards, and reform | The regulatory framework should provide that in respect of all activities in Commonwealth waters: |
REC177-3275 | 32 - Doctrine, standards, and reform | Well Operations Management Plan (WOMPs) submitted by licensees to the regulator(s) should continue to be the primary framework document for achieving well integrity. |
REC177-3300 | 32 - Doctrine, standards, and reform | Licensees and rig operators should install an additional barrier whenever (i) there is any real doubt as to the integrity of any barrier; (ii) whenever the risk of flow from a reservoir increases materially in the course of operations; and (iii) where the consequences of a blowout are grave (for example, for reef systems or shorelines). |
REC177-3324 | 32 - Doctrine, standards, and reform | The mere fact that the rig is over the platform should not be regarded by licensees or regulators as sufficient justification for reliance on only one barrier. The default position should be that producible wells are shut‐in when a rig is moved on and off a platform, or when a drilling unit is moved between wells on a platform. |
REC177-3352 | 32 - Doctrine, standards, and reform | The regulator, rather than the responsible Minister, should be given the power to direct an operator to use a particular rig for the purpose of well control operations, if appropriate in the circumstances, and the power should be used in the future if that rig is the best option available. This would necessarily involve the operator fully compensating for the use of the rig and any other associated costs. The Inquiry suggests that this power could be invoked and given effect as a condition of an operator’s licence. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3283 | 32 - Doctrine, standards, and reform | A separate, identifiable barrier manual should be agreed upon and used by licensees, rig operators, and cementing contractors. These manuals should set out best industry practice in relation to achieving and maintaining well integrity. They should describe barrier types, barrier standards, general principles of well integrity, testing and verification methods and technologies, standard operating procedures (including procedures for the capture and communication of relevant information within and between relevant stakeholder entities). Barrier manuals should address blowout control during drilling, completion, re‐entry, tie‐back of casing strings and so on. Barrier manuals should be the subject of expert external review, and should be regularly updated. |
REC177-3307 | 32 - Doctrine, standards, and reform | Any indication of a compromised cemented shoe which cannot be resolved with a high measure of confidence should result in the installation of additional well control barrier(s). |
REC177-3313 | 32 - Doctrine, standards, and reform | Barriers should not be installed or removed off‐line. The derrick should be located over a well at the time of removal and installation of any barrier. This will enable more decisive action to be taken in the event a problem arises. |
REC177-3359 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed to clarify the arrangements to apply in Commonwealth waters regarding key roles and responsibilities, including in relation to the ESC, in the event of an oil spill. This should also address any necessary training required. |
REC177-3318 | 32 - Doctrine, standards, and reform | Manufacturers should be consulted about how to address non‐routine operational problems affecting their well control equipment. |
REC177-3340 | 32 - Doctrine, standards, and reform | To better ensure that ‘risks’ are identified and managed in accordance with sound engineering principles and good oilfield practice, it is recommended that regulation 25(1)(a)(i) and (2)(a)(i) of the Management of Well Operations Regulations, be reworded as follows: ‘A titleholder must not commence / continue a well activity if…a well integrity hazard exists in relation to the well’. |
REC177-3367 | 32 - Doctrine, standards, and reform | Procedures and accountabilities should be established to ensure, in the event of a future incident, that: |
REC177-3298 | 32 - Doctrine, standards, and reform | Reliance upon one barrier against a blowout must not take place except with the prior written approval of the relevant regulator and then only in a true emergency situation (see below). |
REC177-3323 | 32 - Doctrine, standards, and reform | Where multiple wells are drilled, operations and occurrences at one well must be carefully assessed for any implications with respect to well control at other wells. |
REC177-3350 | 32 - Doctrine, standards, and reform | The recommendations of the Inquiry in relation to suitable ways of achieving well integrity contained in Chapter 3 be included in a guidance manual that is issued for the assistance of industry and regulators. |
REC177-3377 | 32 - Doctrine, standards, and reform | The Minister consider legislative amendments to the OPGGS Act which make clear that |
REC177-3280 | 32 - Doctrine, standards, and reform | Well construction and management plans should include provision for an independent compliance review of well integrity (i) in the event of stipulated triggers; and (ii) at least once in the period between perceived achievement of well integrity and production. The independent compliance review should be undertaken by an expert who is not involved in the day‐to‐day drilling operations. Reviews should be completed in sufficient time to enable results to be implemented in a meaningful manner. |
REC177-3306 | 32 - Doctrine, standards, and reform | It should be standard industry practice to re‐test a cemented casing shoe (that is, after WOC) whenever the plugs do not bump or the float valves apparently fail. Standard industry practice should require consideration of other tests in addition to a repeat pressure test. |
REC177-3328 | 32 - Doctrine, standards, and reform | All communications between on‐rig and onshore personnel relating to well control should be documented in a timely manner. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3312 | 32 - Doctrine, standards, and reform | The BOP and rig should not move from a well until barrier integrity has been verified. |
REC177-3317 | 32 - Doctrine, standards, and reform | Any equipment (including PCCCs) used as, or to install, a barrier should be manufactured for that purpose and be generally recognised as fit for purpose. If equipment is designed in‐house by a licensee or rig operator it should not be approved for use unless and until it is subjected to expert external analysis. |
REC177-3339 | 32 - Doctrine, standards, and reform | The Inquiry supports the objective (rather than prescriptive) approach to regulation now followed in Australia. However, the pendulum has swung too far away from prescriptive standards. In some areas relating to well integrity there needs to be minimum standards. |
REC177-3366 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed: |
REC177-3297 | 32 - Doctrine, standards, and reform | A minimum of two barriers should be in place at all times (including during batched operations) whenever it is reasonably practicable to do so. |
REC177-3322 | 32 - Doctrine, standards, and reform | Batched drilling operations should only be undertaken after careful assessment of the special risks which such operations give rise to; well control must be maintained during the course of batched drilling operations. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3305 | 32 - Doctrine, standards, and reform | Cement integrity should be evaluated wherever practicable by way of cement evaluation tests, rather than relying on pre‐operational calculations of cement and displacement fluid volumes. |
REC177-3327 | 32 - Doctrine, standards, and reform | Information relevant to well control must be captured and communicated within and between licensees and rig operators (and relevant third party contractors), in a manner which ensures it comes to the attention of relevant personnel. In particular, protocols should be developed to ensure that changes in shift and hitch do not operate as communication barriers. |
REC177-3355 | 32 - Doctrine, standards, and reform | The Inquiry also supports Bills and Agostini’s recommendation: ‘…in relation to safety case development and compliance overall, that NOPSA revise its approach to interacting with operators prior to the safety case assessment process and subsequently direct more resources into its advisory functions. We further recommend that NOPSA develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on the latest information, including the interaction with the operator’. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3311 | 32 - Doctrine, standards, and reform | Horizontal or high angle penetration of a reservoir should be avoided wherever practicable until such time as the apparent problems associated with the cementing of a casing shoe in these situations are satisfactorily overcome. If a casing string does penetrate a well horizontally or at a high angle, standard practice should be to install two secondary barriers in addition to the cemented casing shoe. |
REC177-3316 | 32 - Doctrine, standards, and reform | Wells should be re‐entered with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3335 | 32 - Doctrine, standards, and reform | Licensees, rig operators and relevant third party contractors should develop well control competency standards for key personnel in other entities involved in well control operations. |
REC177-3363 | 32 - Doctrine, standards, and reform | DEWHA, in concert with AMSA and with expert input, should develop ‘off the shelf’ monitoring programs that can be speedily implemented following incidents in Commonwealth waters. In this context, the utility of the current Scientific Monitoring program should be peer reviewed to inform future policy. |
REC177-3296 | 32 - Doctrine, standards, and reform | Use of single strings of intermediate casing to penetrate hydrocarbon bearing zones should be carefully risk assessed. Multiple strings of intermediate casing have the advantage of isolating lost circulation zones and sealing off anomalous pressure zones. If intermediate casing is set in a hydrocarbon zone it should be treated as production casing. |
REC177-3320 | 32 - Doctrine, standards, and reform | Any pro‐formas used by licensees, rig operators and contractors for recording information about installation of barriers should explicitly provide for ‘exception reporting’, that is, the form should include provision for recording any unforseen or untoward events which occur in the course of installation. |
REC177-3343 | 32 - Doctrine, standards, and reform | The OPGGS Act should be amended to allow for a power to suspend a petroleum production licence (in addition to the current power to cancel a licence or suspend its conditions). |
REC177-3373 | 32 - Doctrine, standards, and reform | Arrangements should be developed to minimise duplication between the EPBC Act and the OPGSS Act Environment Regulation. |
REC177-3277 | 32 - Doctrine, standards, and reform | The concept of ‘good oilfield practice’ should be supplemented by the requirement to incorporate into WOMPs non‐exhaustive minimum compliance standards in relation to well control: for example, stipulations as to when BOPs and/or well control systems must be in place and when they can be removed and minimum barrier requirements (a number of other factors that should be stipulated are outlined in other recommendations below). |
REC177-3302 | 32 - Doctrine, standards, and reform | Industry, regulators, and training/research institutions should develop standards that address best practices for cementing operations (including liaising, as appropriate, with overseas regulators) with a view to overcoming problems which can effect the integrity of cemented casing shoes, annulus and cement plugs. |
REC177-3326 | 32 - Doctrine, standards, and reform | Prior to commencement of drilling operations, senior representatives of the licensee and rig operator should exchange certificates to the effect that their respective key personnel and contractors have been informed in writing of agreed well control arrangements. |
REC177-3354 | 32 - Doctrine, standards, and reform | NOPSA develop a policy of engagement with operators so as to enable experts (including safety experts) to canvas all available options for well control in the event of a blowout. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3309 | 32 - Doctrine, standards, and reform | If performance of barrier installation is outsourced by a licensee, the contractor (for example, the cementing company) should be engaged on terms which clearly require the provision of expert advisory services by the contractor with respect to barrier integrity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0076 | 32 - Doctrine, standards, and reform | SERCon consider meeting with the State Emergency Management Committee, Directors General and agency heads to |
REC164-0077 | 32 - Doctrine, standards, and reform | SERCon consider the continued development of a State Recovery Sub-Plan (including complementary local and district |
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
REC164-0071 | 32 - Doctrine, standards, and reform | SERCon consider the establishment of a body, such as a State Recovery Committee, with responsibility for the |
REC164-0072 | 32 - Doctrine, standards, and reform | SERCon consider that the proposed State Recovery Committee review the recommended considerations arising from |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3435 | 32 - Doctrine, standards, and reform | That Harbour Masters have the appropriate powers, authority, accountability, skills, responsibility and indemnity to provide a coordinated response of marine resources in support of emergency services, except where the nominated marine safety authority is the control agency for a marine pollution or marine casualty emergency. |
REC158-3440 | 32 - Doctrine, standards, and reform | That the Water Division Emergency Response Plan is amended, by the Water Division emergency response coordinator, to provide a framework to coordinate a marine response that crosses declared port water boundaries and requires resource coordination and prioritisation. |
REC158-3434 | 32 - Doctrine, standards, and reform | That the accountability relationship between Harbour Masters and the Director of Marine Safety is strengthened in the relevant legislation. |
REC158-3439 | 32 - Doctrine, standards, and reform | That the port marine emergency management arrangements are integrated with the Victorian Water Division Emergency Response Plan. |
REC158-3427 | 32 - Doctrine, standards, and reform | That the standards and guidelines determined by the nominated marine safety authority require port/channel managers to conduct a marine emergency risk assessment using AS/NZ 4360:2004 Risk Management and, in addition, must require port/channel managers to: |
REC158-3438 | 32 - Doctrine, standards, and reform | That the port/channel managers coordinate marine emergency management planning in the port and are required to ensure that individual port stakeholder marine emergency management arrangements plans are integrated with the whole of port marine emergency management arrangements. |
REC158-3453 | 32 - Doctrine, standards, and reform | That, where applicable, consideration is given to legislative amendment that will enable the findings of this report to be applied to areas inside State waters but outside commercial port waters. |
REC158-3426 | 32 - Doctrine, standards, and reform | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner, senior emergency services personnel and relevant port stakeholders, is responsible for establishing appropriate performance standards, risk management guidelines and good practice guidelines for marine emergency management. |
REC158-3437 | 32 - Doctrine, standards, and reform | That port/channel managers coordinate marine emergency planning for the port and are required to ensure that marine emergency arrangements are integrated with whole of port emergency management plans. |
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
REC158-3425 | 32 - Doctrine, standards, and reform | Consequential or complementary amendments to the Emergency Management Act are required to ensure that: |
REC158-3436 | 32 - Doctrine, standards, and reform | That Harbour Masters are the designated principle marine specialists within the port and work directly with emergency services to provide advice and the interface with the marine legislative powers, to manage a marine emergency. |
REC158-3441 | 32 - Doctrine, standards, and reform | That, where practical, risk assessments, emergency planning, training and exercising are integrated to minimise duplication of effort. |
REC158-3424 | 32 - Doctrine, standards, and reform | That legislation is prepared by the Department of Transport to ensure marine emergency management arrangements are clarified and provide: |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3141 | 32 - Doctrine, standards, and reform | NOPSA should complete the next revision of Safety Case guidelines in consultation and agreement with stakeholders and continue its program to achieve consistency with a firmer hand from the CEO and management. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3140 | 32 - Doctrine, standards, and reform | The industry should provide advice to NOPSA on where the regulations do not provide sufficient clarity and consider developing broad policy/process guidelines in consultation with the regulator to provide clarity and consistency. Regulators should not take personal views or preferences. |
REC149-3130 | 32 - Doctrine, standards, and reform | The regulations pertaining to vessels of opportunity or their interpretation should be changed to facilitate a risk based approach to regulation. This approach will be consistent with the approach taken in other jurisdictions. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3129 | 32 - Doctrine, standards, and reform | The consequences of the disapplication of the Navigation Act 1912 should be analysed, the actual consequences identified and unintended consequences addressed. |
REC149-3134 | 32 - Doctrine, standards, and reform | Improved and agreed guidelines for Safety Case application and assessment, including suggested structure and content, would alleviate many current problems related to Safety Case processes. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC137-3531 | 32 - Doctrine, standards, and reform | I recommend that CASA consider creating firm guidelines that require consideration of workload, lines of authority, potential conflicts of interest and any other factors that impact upon the ability of “key personnel” to discharge their responsibilities within an aviation organisation when its officers are approving appointments to those positions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
REC125-3895 | 32 - Doctrine, standards, and reform | That all agencies develop drainage asset management plans, consistent with best practice, and that these incorporate: |
REC125-3893 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures that stakeholders (and especially local councils) are fully consulted before and during the development of drainage strategies and plans. These plans should consider councils’ drainage systems. |
REC125-3892 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures stakeholder expectations are fully considered when setting flood risk reduction targets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3661 | 32 - Doctrine, standards, and reform | The rail displan should include provision for the appointment of a rail emergency management co-ordinator at the RMC, and an on-site rail commander with the sole function of assisting and supporting the emergency services during the rescue phase of the emergency response. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3730 | 32 - Doctrine, standards, and reform | Legislation should be enacted and any necessary arrangements made, to enable the ATSB to review any reports of any investigation by a rail organisation or the OTSI into any serious incident or accident in New South Wales. |
REC121-3773 | 32 - Doctrine, standards, and reform | The ITSRR should ensure that RailCorp establishes a safety management system containing the 29 elements identified in the SMSEP report, and ensure the ongoing monitoring and improvement of the safety management system established. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3696 | 32 - Doctrine, standards, and reform | Defects reporting, recording and rectification should be integrated with the RailCorp regimes for train maintenance. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3705 | 32 - Doctrine, standards, and reform | The ITSRR should develop standards for periodic medical examinations which include the following: |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3660 | 32 - Doctrine, standards, and reform | The rail displan should include the use by all emergency response personnel of a uniform incident command system, involving procedures for such matters as the establishment of inner and outer perimeters, control of access to the site, orderly evacuation of injured passengers and the establishment of a staging area remote from the accident site, in a unified command structure with the site controller co-ordinating the various emergency services through representatives of each service. |
REC121-3690 | 32 - Doctrine, standards, and reform | All communications protocols must be strictly enforced by all accredited rail organisations. |
REC121-3728 | 32 - Doctrine, standards, and reform | Any barriers to communication between OTSI and ITSRR should be removed, so as to ensure that any findings made by OTSI in relation to any investigation it conducts are reported immediately to ITSRR. |
REC121-3772 | 32 - Doctrine, standards, and reform | RailCorp should establish a safety management system containing the 29 elements identified in the SMSEP report which is in volume 2 of this report. |
REC121-3671 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include a requirement for the debriefing of all senior rail and emergency response personnel involved in any rail accident, so as to determine the way or ways in which emergency response arrangements for rail accidents can be continually improved, and thereafter implement such improvements. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3701 | 32 - Doctrine, standards, and reform | Train inspections should be carried out at the time of stabling RailCorp trains, as well as a part of train preparation prior to entering service. |
REC121-3763 | 32 - Doctrine, standards, and reform | The ITSRR should publish guidelines to be followed by accredited organisations. |
REC121-3659 | 32 - Doctrine, standards, and reform | A railway disaster plan, or rail displan, should be developed by RailCorp and the emergency services to ensure co-ordinated inter-agency response to rail accidents and incidents on the RailCorp network. |
REC121-3688 | 32 - Doctrine, standards, and reform | Communications procedures must be standardised throughout the rail network, so that all railway employees describe the same subject matter in an identical way. |
REC121-3727 | 32 - Doctrine, standards, and reform | The relevant legislation should be amended to provide expressly that OTSI and the Chief Investigator have the power to initiate a rail accident or incident investigation. |
REC121-3771 | 32 - Doctrine, standards, and reform | RailCorp should establish an integrated safety management system which includes the following: |
REC121-3668 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include action checklists of the steps that each employee is required to take, and the order for specific employees to follow in case of emergency. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3679 | 32 - Doctrine, standards, and reform | The rail safety regulator should set standards for the design, manufacture, testing and commissioning of rolling stock to ensure that the rolling stock is fit for its purpose. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3762 | 32 - Doctrine, standards, and reform | The Chief Executive of ITSRR should have sole accountability and responsibility for the regulation of rail safety in New South Wales. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3770 | 32 - Doctrine, standards, and reform | A safety management system regulation should be promulgated, specifying the requirements of safety management systems in all accredited organisations, using Annexure I to this report as a guide |
REC121-3667 | 32 - Doctrine, standards, and reform | RailCorp should develop and implement an emergency response plan for management of all rail accidents. Such a plan should be subsumed by the rail displan in the case of serious accidents or incidents. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3750 | 32 - Doctrine, standards, and reform | ITSRR should initiate and/or participate in the development of a national standard for crashworthiness of all passenger trains. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3699 | 32 - Doctrine, standards, and reform | All reported train defects should be certified by a person in a supervisory position in RailCorp as having been rectified. |
REC121-3761 | 32 - Doctrine, standards, and reform | Legislative changes should be enacted to ensure the complete independence of ITSRR from the Minister for Transport Services. |
REC121-3655 | 32 - Doctrine, standards, and reform | Procedures should be put in place by RailCorp to ensure that electrical power supply to the area of an accident can be immediately isolated, if necessary, in the event of a rail accident, so as to reduce any risk of exposure of emergency response personnel to injury or harm. |
REC121-3686 | 32 - Doctrine, standards, and reform | The standard in relation to the collection and use of data from data loggers should provide that such information must be accessed in the circumstances of any accident or incident and can be accessed to monitor driver performance generally. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3769 | 32 - Doctrine, standards, and reform | The ITSRR should continue to participate in the development of a national system for rail safety regulation, provided that any ultimate agreement between the States and Territories and the Australian Government does not produce a safety outcome for New South Wales that is less than would be achieved by the implementation of all the recommendations contained in this report. |
REC121-3662 | 32 - Doctrine, standards, and reform | The rail displan should provide for the site controller to have complete control of the site, with other agencies co-ordinating with and supporting him or her, until the rescue phase of the emergency response has been completed. |
REC121-3692 | 32 - Doctrine, standards, and reform | Communications protocols and procedures should be standardised and mandated by regulations making them a condition of accreditation. |
REC121-3736 | 32 - Doctrine, standards, and reform | The RailCorp passenger containment policy must be abandoned. |
REC121-3674 | 32 - Doctrine, standards, and reform | Uniform verbal descriptions identifying that power has been isolated should be developed by RailCorp and utilised by all railway personnel, electrical service providers and all emergency response personnel. |
REC121-3698 | 32 - Doctrine, standards, and reform | No RailCorp train should enter into revenue service or remain in service if, in the opinion of the driver in charge of that train, any defect in it creates a risk of injury. |
REC121-3760 | 32 - Doctrine, standards, and reform | The Advisory Board established under the Transport Legislation Amendment (Safety and Reliability) Act 2003 must be abolished. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3685 | 32 - Doctrine, standards, and reform | The ITSRR should impose a standard in relation to the collection and use of data from data loggers. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3991 | 32 - Doctrine, standards, and reform | The Commission recommends that the provisios of section 185 of the "Mining Act 1905" relating to exits from coal mines be extended to metalliferous mines employing more than 20 men in any one shift. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-4000 | 32 - Doctrine, standards, and reform | That section 22 of the Police Offences Act 1890 be amended, to enable the burning of grass and debris along the railway lines in the summer season to be carried out at an earlier hour than two o'clock in the afternoon, when, in the judgement of the railway inspectors, it is safe and necessary to do so. |
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3995 | 32 - Doctrine, standards, and reform | That the standard double arrester, fitted to the locomotives during the summer months, be subjected to more careful daily inspection before and after each journey during such months, in addition to the present periodical examination by the locomotive foreman and boiler inspector; and that any omission of this duty on the part of the running staff be severely punished. |
REC004-3993 | 32 - Doctrine, standards, and reform | That in any case where there is primá facie evidence of a fire, creating damage to the extent of $100 or upwards in value, having been caused by the escape of particles of lighted matter from a locomotive engine, or by the action of railway employes in burning off grass or other inflammable material along any line of railway, a Special Board of Inquiry shall investigate and report on the subject, such Board to consist of a Police Magistrate as Chairman, with a railway officer and a competent person chosen from outside the State service as members. |