Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0458 | 7 - Inter-agency communication | the state ensure: • a common, functional and accessible system be introduced to enable effective Municipal Emergency Coordination Centre and Incident Control Centre communications • a regime of regular Municipal Emergency Coordination Centre exercising is introduced with oversight by an appropriate independent body. Such exercising should include testing of systems utilised for Incident Control Centre and Municipal Emergency Coordination Centre communications • those required to perform Emergency Management Liaison Officer roles have undertaken appropriate training; and • resource requesting arrangements are clarified and documented so that control and coordination functions do not overlap. |
REC199-0449 | 7 - Inter-agency communication | the state ensure that interoperable information management practices are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0447 | 7 - Inter-agency communication | the state ensure that common and interoperable resource management systems are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0446 | 7 - Inter-agency communication | the state commit to securing effective multi-agency interoperable communications as a high level priority and that all future communications projects and upgrades incorporate compliance provisions mandating interoperability requirements. |
REC199-0418 | 7 - Inter-agency communication | the state develop an efficient process to ensure that, during flood events, temporary construction of flood mitigation works, such as levees, is controlled so as not to unacceptably impact on flood intelligence. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |