Rec-ID | Code | Recommendation |
---|---|---|
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1254 | 13 - Mapping and data quality | That Government: |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0408 | 13 - Mapping and data quality | the state, in consultation with Bureau of Meteorology and Melbourne Water, take the necessary action to ensure that all flood warnings issued are linked to the geographical location of the gauge the data was derived from. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0429 | 13 - Mapping and data quality | the state take into account any outcomes from the Commonwealth Government’s flood mapping reviews in the continual development of the Victorian flood database and to incorporate into the database flood data currently held by Melbourne Water. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0420 | 13 - Mapping and data quality | the state establish standards for flood mapping to ensure they are kept contemporary and meet the purposes of landuse risk planning and emergency response. In doing so, maps should extend where appropriate to include Probable Maximum Flood, over a range of Annual Exceedence Probability levels and be explicitly linked to a stream gauge. |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0417 | 13 - Mapping and data quality | the state ensure that regional and local flood plans incorporate all available flood mapping and intelligence, including assessments of levees and flood consequence information. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |