Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4339 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends that Queensland Fire and Emergency Services review and update the State Disaster Risk Report, including re-evaluating the risk of flooding by all types. Queensland Fire and Emergency Services should publish the updated State Disaster Risk Report by 1 November 2023. |
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4328 | 9 - Community education | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services establish a community education program by 1 November 2023 that complements the implementation of the Australian Warning System. An evaluation process should be incorporated into the program to determine effectiveness. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4255 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends a set of guiding principles that reflect a unified response to World Heritage listed sites in Queensland be included in the Queensland State Disaster Management Plan and reflected in the Queensland Bushfire Plan. |
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4249 | 9 - Community education | The Inspector-General Emergency Management recommends all Area Fire Management Groups in Queensland make their Bushfire Risk Mitigation Plans, bushfire risk mapping and methodology easily understood and available to the community. All public plans should be dated to ensure currency and incorporate mechanisms for community feedback. |
REC322-4221 | 9 - Community education | The Inspector-General Emergency Management recommends Department of Environment and Science implement an awareness and engagement strategy aimed at deterring the lighting of campfires to encourage behavioural change amongst visitors. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4226 | 9 - Community education | The Inspector-General Emergency Management recommends the Bushfire Risk Mitigation Plan for Fraser Coast Area Fire Management Group include a schedule of planned engagement activities, or a community engagement sub-plan outlining these activities, and be publicly available. |
REC322-4253 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends the Queensland State Disaster Management Plan and the Queensland Bushfire Plan be reviewed to enhance appropriate arrangements for the management of bushfire and disaster events where a threat is posed to significant environmental and cultural heritage sites. |
REC322-4239 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends entities with responsibilities for land and fire management consider the establishment of roles for Traditional Owner and First Nations representatives in incident management structures for significant bushfire or disaster events including those that may impact on cultural heritage in Queensland’s World Heritage sites. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC322-4254 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends that the Queensland Government works with the Commonwealth Government to review the Project Agreement for World Heritage Management to ensure Queensland and Australia continue to meet their obligations under the World Heritage Convention to protect, conserve and present our World Heritage properties. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4026 | 12 - EM agency and authority | The role, level, requirements and expectations of an ECC LO be clarified in the Emergency Plan and ECC Ops Sub-plan. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4022 | 12 - EM agency and authority | That when determining their Management Executive, at a minimum the EC should consider appointing Director-General JACS and the PIC as standing members. |
REC316-4036 | 12 - EM agency and authority | Government give consideration to investment in professional specialities such as fire behaviour analysts, airbase managers, aerial firefighting technical specialists etc for the RFS. |
REC316-4045 | 42 - Culture and Heritage | WHoG desktop exercise should be conducted to test and support relocation and evacuation planning. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4016 | 12 - EM agency and authority | That the Emergency Plan be amended to include considerations for declaring a State of Alert or Emergency (and also wind back from these) and guidance as to what actions and decisions at a minimum should be taken as a consequence of such a declaration. |
REC316-4031 | 12 - EM agency and authority | The ESA hold bi-lateral executive level meetings with the utility providers on a regular basis in consultation with other relevant Government stakeholders. |
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
REC316-4015 | 12 - EM agency and authority | The working group should report to SEMSOG on progress. |
REC316-4027 | 12 - EM agency and authority | All organisations who have a role in the ECC should review their existing arrangements to ensure there is a sufficient cohort of staff to maintain a presence in the ECC at a level and with an imprimatur sufficient to make decisions and allocate resources and have access to senior executive levels if needed. |
REC316-4039 | 12 - EM agency and authority | Establish a Communications Working Group (CWG) with representatives from across key Directorates (CMTEDD, ESA, ACT Policing, Health, CHS, EPSDD for example) to review the CCIP and to further identify how the CCIP can be best implemented and utilised. The CWG should report its progress though SEMSOG and coordinate with other WG’s. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC312-2506 | 9 - Community education | The chairpersons of disaster management groups within the Townsville Disaster District, supported by the Queensland Police Service, Queensland Fire and Emergency Services and the Queensland Reconstruction Authority develop a district action plan based on the capability enhancement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
REC311-2501 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, a joint Sunwater/council community engagement program be conducted to prepare the community downstream from Paradise Dam for events in the 2019/2020 storm and cyclone season, including the possibility of a Paradise Dam failure. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2500 | 9 - Community education | To enable the community to make informed choices about disaster management, Bundaberg and North Burnett regional councils and Sunwater undertake a community-informed audible test of the Paradise Dam siren. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2489 | 9 - Community education | To enable the community to have a shared understanding of risks and enhance community engagement, flood scenarios in Emergency Action Plans be published, and in a format that can be utilised by public mapping systems. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2503 | 9 - Community education | To enable the casual/itinerant worker and tourism sector, including those who do not have English as a first language, to make informed choices about disaster management, community engagement and communication strategies about Paradise Dam and floods in the Burnett river system be tailored to this sector. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2502 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, Sunwater develop and deliver a sustainable long-term communication strategy on the community safety issues and |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2483 | 9 - Community education | 09-Community education/engagement/preparedness |
REC310-2482 | 9 - Community education | Practical guidance on what community-led recovery means, and how it can be best implemented should be captured and shared with all who have responsibility for it. This should be done to help individuals and communities to take the lead in recovery and so that community-led recovery becomes the norm following disasters and other events. |
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
REC310-2486 | 9 - Community education | State arrangements for on-the-ground support to recovering local governments should be in line with Queensland’s disaster management arrangements, and ensure the best balance between local relationships, suitable capability and sufficient capacity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2469 | 12 - EM agency and authority | Entities with disaster management responsibilities need to integrate the eight priorities identified within the Emergency Management Sector Adaptation Plan for Climate Change into their disaster management planning cycle. |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2467 | 9 - Community education | Further work be undertaken to develop effective public flood risk messaging and community education materials that are easy to understand and tested with the community to ensure flood risk is understood. |
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2461 | 24 - Govt responsibility | A strategy should be developed between the key tourism and transport operators, and local and state government. It should address the arrival of visitors and tourists after a disaster, and should ensure that their arrival matches communities’ needs for recovery and return to normal business. The Department of Tourism, Major Events, Small Business and the Commonwealth Games should monitor its implementation. |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2430 | 9 - Community education | All Area Fire Management Groups should adopt and be guided by a good neighbour policy. |
REC307-2447 | 9 - Community education | Clear public messaging regarding risks (if any) from the use of suppressants, including to 'organic' producers, should be developed and socialised before the next fire season and be readily available for dissemination when needed. |
REC307-2429 | 9 - Community education | A good neighbour policy such as that of the Queensland Parks and Wildlife Service, setting out clear expectations, be developed to guide all landholders. |
REC307-2439 | 9 - Community education | Education on bushfires should include information about: |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2433 | 24 - Govt responsibility | To make planned burning and land clearing easier to understand and implement for landholders, a single point of contact for all bushfire mitigation inquiries and permits should be established. |
REC307-2431 | 9 - Community education | Area Fire Management Groups should share seasonal risk information with local groups and actively and appropriately contribute to disaster management planning. |
REC307-2448 | 9 - Community education | Targeted education about the short- and long-term effects of chemical suppressants should reach those likely to be exposed to them before aerial chemical suppressants are used in Queensland again. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0952 | 12 - EM agency and authority | That an operational organisation be established comprising of three streams – a. urban fire service; b. rural fire service; and c. the state emergency service. Each of the three organisations will be led by a Deputy Chief Officer, reporting to a Chief Officer. |
REC241-0987 | 12 - EM agency and authority | That to assist the Rural Fire Service Queensland and other agencies in managing wildfire risk, a planning system for wildfire management be established in legislation that complements the existing disaster management arrangements. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-0959 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices report directly to the Deputy Chief Officer. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-0964 | 12 - EM agency and authority | That the position of Regional Manager Rural Operations be re-designated to Regional Co-ordinator in the North, Central and South-East regions to emphasise the supporting role the position will take. |
REC241-1008 | 12 - EM agency and authority | That the colour of Rural Fire Service Queensland Brigade operational vehicles remain yellow and that they retain the Rural Fire Service Queensland logo. |
REC241-0986 | 12 - EM agency and authority | That the founding principle of the Rural Fire Service, that Brigades are formed on the principle of neighbour helping neighbour to collectively manage fire events, remains on of the foundation of Rural Fire Service Queensland. |
REC241-1021 | 12 - EM agency and authority | That Brigades that do not have a truck and are currently classified as Rural conduct a self-determination to ascertain if they wish to be reclassified as a Primary Producer Brigade. |
REC241-0958 | 12 - EM agency and authority | That the Rural Operations division currently sitting within the Queensland Fire and Rescue Service become an autonomous unit called Rural Fire Service Queensland and be led by a Deputy Chief Officer. Structure and Leadership of the Rural Fire Service |
REC241-0993 | 12 - EM agency and authority | That wherever possible, for future appointments of Fire Wardens, where that Wardens’ district is totally covered a by Rural Fire Brigade, consideration should be given that the appointed Fire Warden is a Rural Brigade Member. |
REC241-0963 | 12 - EM agency and authority | That there be three (3) RFSQ regions in Queensland - North, Central and South-East. |
REC241-1007 | 12 - EM agency and authority | That the Rural Fire Service Queensland consider a less formal uniform which volunteers can better identify with, and that National rank markings be retained. |
REC241-0979 | 24 - Govt responsibility | That the Queensland Government liaise with the Federal Government with a view to securing incentives for employers that recognise loss of income and employee time for emergency operations. |
REC241-1020 | 12 - EM agency and authority | That members of Village and Izone classified Brigades only be required to conduct a criminal history check when they first join a Brigade. Criminal history checks will no longer be required when a Member who has already undergone a criminal history check takes an office bearing role within a Brigade or changes Brigades. Criminal history checks are to still be conducted on Rural Fire Service volunteers undertaking interstate deployments. Members of other voluntary organisations in Queensland (e.g. State Emergency Service, Volunteer Marine Rescue) who wish to join the Rural Fire Service Queensland will not be required to undertake an additional criminal history check with an internal check to be conducted by the Department of Community Safety. |
REC241-0957 | 12 - EM agency and authority | That a strong emphasis be placed on the establishment and recruitment of PCYC emergency cadets. |
REC241-0990 | 12 - EM agency and authority | Membership of the District Fire Management Group is at the discretion of the Chair of the District Fire Management Group, however members must have the necessary expertise and experience for the role and membership should include where applicable, the District Inspector - Rural Fire Service Queensland, a representative of relevant local governments and representatives of agencies responsible for parks and wildlife, transport and main roads, forestry and natural resources among other appropriate representatives. |
REC241-0962 | 12 - EM agency and authority | That Rural Fire Service Queensland consider service delivery needs with a view to establishing boundary/ staff/budget changes according to State standards. |
REC241-1006 | 12 - EM agency and authority | That Brigades’ financial contributions to groups must be voluntary and approved by a recorded minute at a meeting of that brigade. |
REC241-0975 | 12 - EM agency and authority | That employee selection panels for field staff positions only comprise three members and include a Rural Fire Service Queensland representative, a Rural Fire Brigades Association of Queensland representative and one representative from the District Fire Management Group. |
REC241-1019 | 12 - EM agency and authority | That a local committee consisting of Elders and community leaders be formed in remote and Indigenous communities to determine Brigade membership applications. |
REC241-0954 | 24 - Govt responsibility | That a Ministerial Advisory Council be established to inform the Minister of matters relating to Rural Fire Service and SES volunteers. |
REC241-0989 | 12 - EM agency and authority | That the first tier comprise at least one District Fire Management Group in each Rural Fire Service Queensland District. The District Fire Management Group will be chaired by a person with the necessary expertise and experience, nominated by the community and appointed by Government. Chairs will hold the deciding vote in matters related to fire management at the local level. |
REC241-1038 | 12 - EM agency and authority | That District Inspectors retain the discretion to allocate gratuity to Fire Wardens for out of pocket expenses if required. |
REC241-0961 | 12 - EM agency and authority | That staffing at Rural Fire Service Queensland District offices remain at current levels within establishment and, if needed, base staffing levels be increased. |
REC241-1005 | 12 - EM agency and authority | That fire groups can only be formed through the agreement of all brigades that will become a part of that group, and the management and operational procedures of the group must be approved by the contributing brigades. Local District Inspectors are to provide mentoring and support when brigades form a group. |
REC241-0972 | 12 - EM agency and authority | That Rural Fire Service Queensland designate a position of Lands Procurement Officer to support volunteers by project managing the acquisition of land for Brigade sheds and their construction where required. |
REC241-1014 | 12 - EM agency and authority | That the Rural Fire Service Queensland should engage a private provider offsite and outside the Government firewall to establish an email address for each Brigade and Fire Warden. The email address would reflect the Brigade name and Fire Warden district. E.g.: GreenbankRFB@msn.com.au |
REC241-0953 | 12 - EM agency and authority | That a separate area of responsibility be established to provide independent oversight and monitor disaster readiness across all hazards. |
REC241-0988 | 12 - EM agency and authority | That the planning system is to have a two tiered structure comprising District Fire Management Groups and linking to the State Disaster Management Group. |
REC241-1037 | 12 - EM agency and authority | That Rural Fire Service Queensland and its staff be exempt from the Travel Management System. The Travel Management System does not work in the rural fire operation areas as it is not flexible in the rapid escalation of wild fire events or cater for volunteering timeframes. It has been proven to be inefficient and costly. |
REC241-0960 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices remain at least at their current number of 14, with consideration given by the Rural Fire Service Queensland to expanding the number of District offices by opening an office in the South Burnett, considering a new office in the southern Central Highlands, and the option of part time offices on a risk/need/growth basis, particularly in north-west Queensland. |
REC241-1001 | 24 - Govt responsibility | That the extent of forest and plantation fuel load fire risk in South East Queensland requires a designated government resources fire team to manage this risk and proactively conduct fuel mitigation burning; and provide a wildfire response to government land. |
REC241-0966 | 12 - EM agency and authority | That District offices be located in areas that enhance ease of access for out of town volunteers and the general public and also provide suitable parking, onsite storage and be suitable for operational use. |
REC241-1010 | 12 - EM agency and authority | That where a Brigade supports another community and this involves the use of any brigade equipment it shall be the decision of that brigade in relation to the deployment and use of their equipment and resources. |