REC314-3260 | 32 - Doctrine, standards, and reform | Align risk assessment tools and processes to Risk Management Standard ISO 31000 and the National Emergency Risk Assessment Guidelines (NERAG) and communicate these on public-facing platforms. Make Bushfire Management Area Plans (BMAP) accountable for managing and reporting on region-specific risk and identifying critical infrastructure such as mobile phone towers as key risks. |
REC314-3259 | 32 - Doctrine, standards, and reform | Implement previous review recommendations for bushfire management including those relating to the 2009 amendments to the Fire and Emergency Services Act 2005, State Bushfire Coordination Committee operation, State Bushfire Management Plan, as well as urgent completion of Codes of Practice for fuel hazard reduction on all land tenures, and redevelopment of Bushfire Management Area Plans accompanied by effective community engagement to build an understanding of risk. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3269 | 32 - Doctrine, standards, and reform | Develop and practice procedures for the CFS, DEW and local governments to access and deploy heavy plant and machinery for fuel reduction operations both before and during bushfires. |
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1280 | 32 - Doctrine, standards, and reform | That a State Plan be developed for managing the consequences of a black system event or other major power outage. The plan should include: |
REC295-1314 | 32 - Doctrine, standards, and reform | That an Emergency Management Assurance Framework be established as soon as possible to support the emergency management arrangements and the State Emergency Management Plan. Consider establishing an Inspector General Emergency Management department or position. |
REC295-1289 | 32 - Doctrine, standards, and reform | That SA Police, emergency services, health facilities, utility providers and other key service providers, review their Business Continuity Plans giving consideration to factors such as: a) identification of: business critical needs; essential services power requirements; back-up power requirements for all facilities including State, regional and local facilities such as Police, SES, MFS and CFS stations; the need for any arrangements for back-up power to be included in contracts for design and or lease of Government premises b) contingencies for black system events and extended power outages c) regular back-up generator testing regime protocols, including testing under load and for long durations d) contingencies for communications when mobile, landline and/or radios are not operational e.g. satellite phones; and e) alternative State control centre facilities that are pre-identified, equipped and have procedures for moving to the alternative facility. |
REC295-1333 | 32 - Doctrine, standards, and reform | Develop a State Relief and Recovery Plan as a distinct part of the State Emergency Management Plan which should include: a) potential locations for suitable facilities for relief and recovery centres which: are in locations safe from hazards such as flooding and bushfire; and, have appropriate access and suitable ablutions. b) formalisation of roles and capabilities of non-government organisations such as Red Cross |
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1311 | 32 - Doctrine, standards, and reform | That the State Emergency Management Plan be reviewed and updated including: a) a better description of the responsibilities of Hazard Leaders Page xx b) establish a mechanism for a hazard leader to identify systemic failures in coordination of their hazard, with a clear process to raise those issues with SEMC and seek a remedy c) establish resilience as a key heading in the plan, with clearly documented strategies and responsibilities; and d) consider the Schar/Mulroney submission and taking a ‘fresh eyes’ approach |
REC295-1287 | 32 - Doctrine, standards, and reform | That the glossary of terms in the State Emergency Management Plan be reviewed to ensure all relevant language is included. All agencies need to ensure the use of clear communication and accurate use of terminology, including in describing the status of critical services e.g. Triple Zero (000), SA Government Radio Network, electrical and water supplies and infrastructure. |
REC295-1332 | 32 - Doctrine, standards, and reform | Develop a Disaster Waste Management Plan to form part of the State Emergency Management Plan which describe participating agencies and responsibilities for various aspects of waste management during and after emergencies. |
REC295-1301 | 32 - Doctrine, standards, and reform | Establish an ‘Interstate Deployment Support Plan’ for incoming interstate resources. The plan should outline responsibilities and arrangements for this function. Consider including this plan into the State emergency management arrangements. |
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1310 | 32 - Doctrine, standards, and reform | That additional guidance be provided in the State Emergency Management Plan regarding the activation, structure and operation of Zone Emergency Support Teams. This should include: a) the reporting relationship between the Zone Emergency Support Teams, the State Emergency Centre and the State Coordinator b) briefing requirements between the State Coordinator (or their representative) and the Zone Emergency Support Teams when the State Emergency Centre is activated c) responsibilities for provision of local public information; and d) the appointment of public information officers in Zone Emergency Support Teams (where there is no incident management team (established) to provide information to local communities |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1331 | 32 - Doctrine, standards, and reform | Task South Australian Fire and Emergency Services Commission with further developing the Emergency Alerts capability across government agencies including to: a) establish and maintain a centralised training program for emergency alert initial and refresher training. b) establish a pool of endorsed Emergency Alert personnel from across government agencies to enable control agencies to assist each other with the emergency alert function during emergencies. c) develop supporting processes to ensure that the capability supports: emergencies involving any hazard; consistent issuing of alerts and warnings; consistent messages; and effective communication and notification of alerts issued to relevant internal and external stakeholders |
REC295-1295 | 32 - Doctrine, standards, and reform | That resources be provided to support the implementation of recommendations in the South Australian Levee Bank Management Issues Paper (DEWNR, 2015) including: a) development of relevant policy; and b) identification of responsibilities in relation to levee management and flood mitigation |
REC295-1277 | 32 - Doctrine, standards, and reform | That the Department of Planning, Transport and Infrastructure review their Business Continuity Plan to: |
REC295-1309 | 32 - Doctrine, standards, and reform | That members of Emergency Management Council ensure they are prepared to undertake their roles and responsibilities during emergency events, including establishing: a) contingencies for communication e.g. satellite phone b) access to relevant documents such as the State Emergency Management Plan, supporting plans, ministerial guidelines, agency plans and contacts in hard copy and/or portable device c) formalised arrangements for briefings (up and down), and d) arrangements for suitable representation e.g. relevant Chief Executive(s) or their deputy, at all Emergency Management Council meetings . |
REC295-1282 | 32 - Doctrine, standards, and reform | That the Office for Digital Government, in close partnership with telecommunications companies (e.g. Telstra, Optus, Vodaphone), develop a Control Agency Plan for Information and Communication Technology including mobile communications. The plan should consider: |
REC295-1330 | 32 - Doctrine, standards, and reform | Update the Public Information Functional Support Group Plan to include: a) standards, outputs, systems and processes required to be used by control agencies and the Public Information Functional Support Group during emergencies b) guidance on the public information cycle through the prevention, preparedness, response and recovery phases which includes the responsibilities and information requirements during different phases, and effective transition between phases c) establishing a public information intelligence cell within the Public Information Functional Service Group; and d) identifying tools or resources to monitor social media |
REC295-1292 | 32 - Doctrine, standards, and reform | That, giving consideration to the previous recommendation, the Flood |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1281 | 32 - Doctrine, standards, and reform | In order to increase resilience and public safety during emergencies, the State Emergency Management Committee should request the Australia and New Zealand Emergency Management Committee to place on the agenda, and consider establishing a national position, on redundancies for mobile communications (including phone tower back-up power) and the National Broadband Network. |
REC295-1323 | 32 - Doctrine, standards, and reform | Review and update the role, function, workload and focus of the groups/committees that contribute to incident management and emergency management capabilities including the State Emergency Management Training Committee, Interagency Incident Management Sub-Committee and the Central Exercise Writing Team. |
REC295-1290 | 32 - Doctrine, standards, and reform | Continue development of the Damage Assessment Support Plan to: |
REC295-1306 | 9 - Community education | Develop practical policy outcomes to support resilience (e.g. the 72- hour model) and promote this broadly to community through media, awareness campaigns, policies etc. Research should be undertaken to gain insight into the types of messaging and activities that have the most impact on sustained behaviour change within the community before committing to a particular model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1141 | 21 - Role of Commonwealth Government | SACFS and the BoM review current weather, fuel loads and curing rates to determine the most appropriate and accurate forecast is prepared, issued and validated against current conditions. |
REC273-1133 | 32 - Doctrine, standards, and reform | That a complete review of current naming conventions of personnel and centres, in accordance with the outcomes of the Victorian Bushfire Royal Commission is undertaken, to ensure clarity around command, control and coordination within SA. |
REC273-1129 | 32 - Doctrine, standards, and reform | Incorporating ‘triggers’ within Chief Officers Standing Orders No. 17, which requires the escalation of the State Controller role to the rank of Assistant Chief Officer or greater, depending on the increased risk or activity. |
REC273-1128 | 32 - Doctrine, standards, and reform | Incorporate in operational doctrine the ability for the State Controller to determine the operational readiness levels of the state or regions based on either the predicted and/or actual risk and/or activity to some or all of the regions. |
REC273-1145 | 32 - Doctrine, standards, and reform | Review relevant Legislation associated Acts and Plans to establish a consistent approach to fire and emergency management to minimise duplication and risk of contradiction. That the Hazard and Functional area plans be amalgamated and establish a SA Bushfire Plan, under the SEMP, which clearly define role of SACFS. |
REC273-1143 | 32 - Doctrine, standards, and reform | That SACFS in consultation with SAMFS consider adopting common terminology and capability requirements for strike teams being ‘4-5 appliances and a group officer’ in line with other jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1078 | 32 - Doctrine, standards, and reform | The State review and revise the community carbon monoxide response protocol and the firefghter carbon monoxide response protocol, to: |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1077 | 32 - Doctrine, standards, and reform | The State take the lead in advocating for a national compliance standard for PM |
REC264-1084 | 32 - Doctrine, standards, and reform | GDF Suez revise its Emergency Response Plan, to: • require an increased state of readiness on days of Total Fire Ban; • require pre-establishment of an Emergency Command Centre; • require pre-positioning of an accredited Incident Controller as Emergency Commander; and • require any persons nominated as Emergency Commander to have incident controller accreditation and profciency in the use of the Australasian Inter-service Incident Management System. |
REC264-1075 | 32 - Doctrine, standards, and reform | The State: • bring forward the commencement date of s.16 of the Mineral Resources (Sustainable Development) Amendment Act 2014 (Vic), to facilitate the requirement that approved work plans specifcally address fre prevention, mitigation and suppression; and • acquire the expertise necessary to monitor and enforce compliance with fre risk measures adopted by the Victorian coal mining industry under both the mine licensing and occupational health and safety regimes. |
REC264-1083 | 9 - Community education | The State, led by Emergency Management Victoria, develop a community engagement model for emergency management to ensure all State agencies and local governments engage with communities and already identifed trusted networks as an integral component of emergency management planning. |
REC264-1074 | 32 - Doctrine, standards, and reform | The State enact legislation, to: • require Integrated Fire Management Planning; and • authorise the Emergency Management Commissioner to develop and implement regional and municipal fire management plans. |
REC264-1080 | 32 - Doctrine, standards, and reform | The State develop and widely disseminate an integrated State Smoke Guide, to: • incorporate the proposed State Smoke Plan for the management of public health impacts from large scale, extended smoke events; • include updated Bushfre Smoke, carbon monoxide and PM protocols; and 2.5 • provide practical advice and support materials to employers, communities and individuals on how to minimise the harmful effects of smoke. |
REC264-1079 | 32 - Doctrine, standards, and reform | The State review and revise the Bushfre Smoke Protocol and the PM Health Protection Protocol, to: 2.5 • ensure both protocols are consistent with each other; and • ensure both protocols include assessment methods and trigger points for specifc responses. |
REC264-1088 | 32 - Doctrine, standards, and reform | GDF Suez adopt and apply the firefghter carbon monoxide response protocol. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2628 | 32 - Doctrine, standards, and reform | Amend the F&ES Act to reflect the SES expanded responsibilities as Hazard Leader for ‘Extreme Weather’ including their community education role. |
REC244-2611 | 32 - Doctrine, standards, and reform | Review the format and necessity for Schedules 9 and 10 of the Regulations |
REC244-2635 | 32 - Doctrine, standards, and reform | The requirement to consult with members of the unit and the SESVA before an SES Unit is dissolved should remain but the need for public meetings be removed from the regulations. |
REC244-2622 | 32 - Doctrine, standards, and reform | Amend Sections 28, 61 and 110 to provide the Chief Officers greater flexibility over organisational structure. |
REC244-2603 | 32 - Doctrine, standards, and reform | Should the State Bushfire Coordination Committee continue to exist under the F&ES Act, then Section 71 of the Act be amended to provide for the appointment of an independent presiding member of the committee. |
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2610 | 32 - Doctrine, standards, and reform | Amend Regulation 33 (6) and (8) to include respectively ‘notice given’ and ‘permit application’ using the online medium. |
REC244-2633 | 32 - Doctrine, standards, and reform | Amend Section 143 to strengthen the capacity of the ESOs to recover outstanding debts (e.g. penalty for late payment provisions). |
REC244-2615 | 32 - Doctrine, standards, and reform | In consultation with stakeholders including CFA, develop a Forest Industry Brigade standard for inclusion in the Fire and Emergency Services Regulations. |
REC244-2602 | 32 - Doctrine, standards, and reform | That South Australia’s Hazard Leader Plan for Rural Fire, prepared in accordance with the State Emergency Management Plan, replace the F&ES Act requirement for a separate State Bushfire Management Plan. |
REC244-2626 | 32 - Doctrine, standards, and reform | Section 70 (5) be amended to preclude a person from being elected as a group officer, brigade captain or brigade lieutenant if he or she is an employee of the CFS. |
REC244-2609 | 32 - Doctrine, standards, and reform | That the proposed ‘Permit Information Management System’ (PIMS) be implemented as soon as possible and incorporated into the Call Receipt and Dispatch process. Following implementation, amend Regulation 33 (5) (d) and (10) (c) in line with the automated notification process. |
REC244-2632 | 32 - Doctrine, standards, and reform | Section 142 be amended to include the SES |
REC244-2614 | 32 - Doctrine, standards, and reform | Consider the amendment of Section 82 (2) to include the power to order the cessation of harvesting or any other actions (including the lighting of fires authorised under Section 81) that because of the weather conditions, may cause a fire, if ignited, to get out of control. |
REC244-2599 | 32 - Doctrine, standards, and reform | That the MFS, CFS and SES be incorporated into a departmental structure under the direction of a Chief Executive based on interstate developments over the past two decades, which establishes this arrangement as the benchmark for the governance of Emergency Services in Australia. The MFS, CFS and SES would operate as separate units under the ultimate direction of the CEO. |
REC244-2625 | 32 - Doctrine, standards, and reform | Sections 42 and 97 be amended to provide greater flexibility in the engagement of contractors by Senior MFS and CFS Officers. Consideration be given to providing similar powers in Section 118 to enable the SES to engage contractors. |
REC244-2608 | 32 - Doctrine, standards, and reform | Consider whether Regulation 71 be amended to extend the range of offences for which expiation fees apply to include a breach of any permit condition imposed by an authorised officer. |
REC244-2630 | 32 - Doctrine, standards, and reform | Clarify that Section 128 of the F&ES Act is not compromised by any other legislation. |
REC244-2613 | 32 - Doctrine, standards, and reform | Should the State Bushfire Coordination Committee continue to exist under the F&ES Act amend Section 94 (4) (c) to refer to the ‘State Bushfire Coordination Committee’. |
REC244-2624 | 32 - Doctrine, standards, and reform | The F&ES Act be amended to clarify the meaning of ‘closure’ in Section 38 and that provisions relating to the extension and rescission of closure orders be reviewed. |
REC244-2607 | 32 - Doctrine, standards, and reform | Amend Regulation 41 to exempt the use of prescribed appliances when a Hot Work Permit compliant with AS1674.1 has been issued. |
REC244-2629 | 32 - Doctrine, standards, and reform | The power of the Chief Officer to appoint officers from the staff of the SES as well as appoint volunteer officers of the SES be clarified. A command structure section (similar to Section 70) be incorporated into the Act and include the power to register, appoint, disqualify and terminate volunteer members. |
REC244-2612 | 32 - Doctrine, standards, and reform | Develop a code of practice which is referenced by the F&ES Act for burning off including the option to issue seasonal permits for relevant purposes throughout the State. |
REC244-2636 | 32 - Doctrine, standards, and reform | Amend the F&ES Act to provide for the operation of interstate fire and emergency service workers in South Australia. The issue of liability may need to be considered. |
REC244-2623 | 32 - Doctrine, standards, and reform | That the F&ES Act be amended to enable fire safety inspections in and outside fire districts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0844 | 32 - Doctrine, standards, and reform | That the State Government give high priority to liaising with interstate and Federal processes, and offer to take a lead, on changing the climatic and fire rating arrangements to ensure these match the conditions that can create dangerous bushfire conditions at short notice. |
REC243-0839 | 32 - Doctrine, standards, and reform | That noting the precedents for legislated charters in the Carers Recognition Act 2005 and the Health and Community Services Complaints Act 2004, that the Government support the Fire and Emergency Services (Volunteer Charters) Amendment Bill introduced by the Member for Morphett in November 2012 to enshrine the Country Fire Service and the State Emergency Service at law. |
REC243-0837 | 32 - Doctrine, standards, and reform | That the Government’s Workers Rehabilitation and Compensation (SAMFS Firefighters) Amendment Bill be amended to include Country Fire Service firefighters alongside Metropolitan Fire Service firefighters. |
REC243-0847 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC243-0845 | 21 - Role of Commonwealth Government | That Government agencies work closely with the Bureau of Meteorology and radio stations that broadcast emergency service announcements, to ensure the earliest possible determination of, and communications about, dangerous bushfire conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2649 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC242-2641 | 32 - Doctrine, standards, and reform | That noting the precedents for legislated charters in the Carers Recognition Act 2005 and the Health and Community Services Complaints Act 2004, that the Government support the Fire and Emergency Services (Volunteer Charters) Amendment Bill introduced by the Member for Morphett in November 2012 to enshrine the Country Fire Service and the State Emergency Service at law. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0431 | 9 - Community education | the state allocate core funding for the ongoing delivery of the ‘FloodSafe’ program to flood prone communities across Victoria. |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
REC199-0430 | 9 - Community education | the state undertake a community education program to inform households of their respective flood risk. This may include information on rate notices of heights of houses above flood level and educating people about flash flooding. |
REC199-0483 | 9 - Community education | the state ensure: • where external assistance is provided to Victoria during emergencies, communities are advised of the specific purpose of that assistance, through media and other information channels; and • all agencies provide incident management personnel with information regarding the arrangements for tasking Australian Defence Force resources and that this advice is reinforced during emergencies where Australian Defence Force support is provided. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1741 | 9 - Community education | A. The CFA further develop community education programs to specifically engage culturally and linguistically diverse (CALD) communities to address the importance of ethnic diversity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC192-1923 | 21 - Role of Commonwealth Government | The Committee recommends that Parliament establish a standing committee for natural disasters. The purpose of this committee would be to ensure that Government agencies and emergency services are fully prepared to deal with natural disasters and to provide an opportunity for Members of Parliament, as opposed to Cabinet, to have input into disaster management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3475 | 9 - Community education | That in relation to Fire Operations Plans, the Department Sustainability and Environment extends the number of community meetings during the public consultation period to a minimum of one meeting for each Fire District, with the possibility of repeat visits to particular areas. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3483 | 9 - Community education | That the Department of Sustainability and Environment and its partner agencies continue to develop a proactive approach to engagement with the local and wider media to achieve continuous improvement in the standard of community information and education. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3482 | 32 - Doctrine, standards, and reform | That the Victorian Government, and responsible agencies, expedite the implementation of the Integrated Fire Management Planning framework. |
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
REC155-3479 | 32 - Doctrine, standards, and reform | That a process of year round community engagement in the preparation of Fire Operations Plans be established. In addition a record of year round community engagement, as contained in the Gippsland Fire Operations Plan, should be a requirement of all Fire Operations Plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3073 | 32 - Doctrine, standards, and reform | Sections 56 and 83 be repealed and replaced with a single section which unifies their provisions. |
REC151-3094 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to ‘South Australian Volunteer Fire-Brigades Association’ this be removed and replaced with, ‘Country Fire Service Volunteers Association’. |
REC151-3082 | 32 - Doctrine, standards, and reform | The Regulations be amended to include appropriate references to the Unit Managers Advisory Group (SASES) consistent with those of the Group Committee (SACFS). |
REC151-3102 | 32 - Doctrine, standards, and reform | Regulations 22 and 62 be reviewed to ensure reports regarding conduct must be relevant to the enquiry. |
REC151-3064 | 32 - Doctrine, standards, and reform | The FES Act be amended to include a definition of ‘operations’ and/or ‘operational’. |
REC151-3088 | 32 - Doctrine, standards, and reform | Sections 68 and 116 – provisions relating to the establishment/dissolution of SACFS Brigades and SASES Units be amended so as to retain the head of power in the principal FES Act and that the procedural provisions within each of these sections be placed in the Regulations. |
REC151-3110 | 32 - Doctrine, standards, and reform | Further to Recommendations 11 and 12 above concerning the joining of Sections 56 and 83 of the FES Act, that these existing provisions be examined to determine whether they provide sufficient authority to address Recommendation 29.9(4) of the Wangary Coronial Inquest so as to require the owners or occupiers of rural land to create fire breaks and/or the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
REC151-3072 | 32 - Doctrine, standards, and reform | Provisions in the FES Act relating to, “land management principles” be reviewed in consultation with appropriate agencies and having due regard to the recommendations of the Wangary Coronial Inquest. |
REC151-3094 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to ‘South Australian Volunteer Fire-Brigades Association’ this be removed and replaced with, ‘Country Fire Service Volunteers Association’. |
REC151-3081 | 32 - Doctrine, standards, and reform | So as to increase the pool of volunteers from which the Minister can appoint Advisory Board members, Section 18(3)(c) and (d) be amended to include nominations from the Group Committee (SACFS) and Unit Managers Advisory Group (SASES). |
REC151-3101 | 32 - Doctrine, standards, and reform | Divisions and Subdivisions and Regulations 22 and 62 headings relating to conduct and discipline be changed to have similar wording and should include, “Conduct, Discipline and Grievance Procedures for Members”. |
REC151-3063 | 32 - Doctrine, standards, and reform | The preamble of the Fire and Emergency Services (FES) Act be amended to include a stronger emphasis on the strategic and policy purposes of the Commission, highlighting its key role in the governance of the emergency services sector. |
REC151-3087 | 32 - Doctrine, standards, and reform | Section 90 – provisions relating to smoking, and throwing burning material be removed from the principal FES Act and placed in the Regulations. |
REC151-3106 | 32 - Doctrine, standards, and reform | A schedule for revocation of permits be included in the Regulations. |
REC151-3070 | 32 - Doctrine, standards, and reform | Crown law opinion be obtained to determine whether additional functions now undertaken by the Commission following the devolvement of the functions of the Security and Emergency Management Office (SEMO) require an amendment to the FES Act. |
REC151-3093 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to, ‘an officer of the National Parks and Wildlife Service’ this be removed and replaced with, ‘an officer of the Department for Environment and Heritage’. |
REC151-3076 | 32 - Doctrine, standards, and reform | Provisions in Section 11(1)(e)(i) and (ii) relating to appointments of volunteer associations to the SAFECOM Board be removed. |
REC151-3100 | 32 - Doctrine, standards, and reform | Section 70(12) (relating to disciplinary action) be amended to include, where the officer is an employee of a government agency, the Chief Officer shall advise an appropriate representative of the agency prior to any disciplinary action being taken. |
REC151-3086 | 32 - Doctrine, standards, and reform | Section 88 – requirement to carry fire extinguishers in a caravan be removed from the principal FES Act and placed in the Regulations. |
REC151-3105 | 32 - Doctrine, standards, and reform | With the implementation of the Ministerial Review of Bushfire Management in South Australia, the provisions in Sections 84 and 85 be reviewed in terms of enforcing hazard reduction on council or Crown land. |
REC151-3069 | 32 - Doctrine, standards, and reform | Consistent with the requirement for Emergency Service Organisations, the FES Act be amended to require South Australian Fire and Emergency Commission (SAFECOM) to submit a workforce plan to the Board. |
REC151-3091 | 32 - Doctrine, standards, and reform | Regulation 48 regarding prescribed offences be amended to include Section 79(2)(e) or its equivalent under the amendment proposed in Recommendation 22 above. |
REC151-3075 | 32 - Doctrine, standards, and reform | Section 92 include the facility to issue a warrant for the relevant authority to break into land or buildings for the purposes of determining what measures have been taken for the prevention, control or suppression of fire or for the prevention of, or for dealing with, the escape of hazardous materials; and that costs and expenses in doing so are recoverable. |
REC151-3097 | 32 - Doctrine, standards, and reform | Regulation 8(4)(b) be amended to allow persons of or above 16 years of age to register as fire-fighters. |
REC151-3085 | 32 - Doctrine, standards, and reform | With the implementation of the Ministerial Review of Bushfire Management in South Australia, consideration should be given to provisions within Part 4, Division 7 of the principal FES Act which would be more appropriately placed in the Regulations. |
REC151-3104 | 32 - Doctrine, standards, and reform | SAFECOM in consultation with SAMFS consider the merits of amending Sections 49- 51 to replace the right to appeal from the District Court to the South Australian Industrial Relations Commission. |
REC151-3068 | 32 - Doctrine, standards, and reform | The FES Act be amended so as to allow the Chief Executive (CE) to manage the Commission (SAFECOM) Office by removing provisions relative to the SAFECOM Board’s managerial and administrative oversight of the Commission. |
REC151-3090 | 32 - Doctrine, standards, and reform | Following the amendment to Section 79 as proposed above in Recommendation 22, a definition of, ‘properly constructed fire place’ and ‘properly constructed incinerator’ be included in the new Regulation. |
REC151-3074 | 32 - Doctrine, standards, and reform | Sections 56 and 83 (amended as suggested above) include the facility to issue a warrant for the relevant authority to break into land or buildings to carry out requirements regarding flammable undergrowth or material; and that costs and expenses in doing so are recoverable. |
REC151-3096 | 32 - Doctrine, standards, and reform | All Regulations relating to constitutions be deleted; the FES Act be amended to allow the Chief Officers to prescribe the constitution; and the process for the management of a SACFS brigade/group and a SASES unit to be in the form of an administrative instruction. |
REC151-3084 | 32 - Doctrine, standards, and reform | Section 79(1) – provisions relating to lighting or maintaining a fire in the open air during the fire danger season be retained in the principal FES Act; Section 79(2) be amended to provide that a fire may be lit or maintained in accordance with the Regulations; provisions specifying the conditions under which a fire can be lit or maintained, and currently under Section 79(2), be placed in the Regulations. |
REC151-3103 | 32 - Doctrine, standards, and reform | Provisions be included in the Regulations for mediation in appropriate circumstances. |
REC151-3065 | 32 - Doctrine, standards, and reform | The FES Act be amended to create the position which currently has the working title of ‘Commissioner of Fire and Emergencies’ to replace the position of CE and that the FES Act be amended in places where this position is mentioned. |
REC151-3089 | 32 - Doctrine, standards, and reform | The definition of ‘officer’ in Section 3 be amended to include reference to the designation being made by the Chief Officer. |
REC151-3111 | 32 - Doctrine, standards, and reform | Crown law opinion be obtained as to what amendments, if necessary or appropriate, are required to satisfy Recommendation 29.9(7) of the Wangary Coronial Inquest, that a dedicated bushfire prevention officer be appointed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3592 | 32 - Doctrine, standards, and reform | Clarifying protocols for activating VBIL beyond normal working hours and for 24 hour activations |
REC132-3591 | 32 - Doctrine, standards, and reform | Joint development of templates for provision of core incident information by regional Incident Management Teams to CFA and DSE emergency coordination centres as basis for updates to the VBIL and other authorised information recipients |
REC132-3595 | 32 - Doctrine, standards, and reform | Development of framework document investigating future direction of VBIL including its role during incidents and its role in the transition from bushfire preparation to incident to bushfire recovery phases |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
REC122-3797 | 9 - Community education | The Committee recommends that the Native Vegetation Council continue to seek mechanisms to interact with, and educate the individual farmer and landholder with respect to the Native Vegetation Act, its regulations and exemptions. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |
REC122-3786 | 32 - Doctrine, standards, and reform | The Committee recommends that the Native Vegetation Act be amended to allow for prescribed burning. |
REC122-3796 | 9 - Community education | The Committee recommends that the government undertake public education programs to increase the awareness of the community to bushfires, the role fire plays in ecosystems and what steps they should take to minimise the impact of a fire. |
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
REC122-3790 | 32 - Doctrine, standards, and reform | The Committee recommends that prescribed burning should only be undertaken by professionally trained personnel. |
REC122-3777 | 1 - Land-use and building regs | The Committee recommends that native vegetation, excluding road reserves be fenced. |
REC122-3784 | 34 - Local knowledge | The Committee recommends that the government provide authority to a single community representative body to authorise clearing of native vegetation for fire management. (The community representative body must incorporate the CFS, DEH, Native Vegetation Council and local council) |
REC122-3789 | 32 - Doctrine, standards, and reform | The Committee recommends that the native vegetation planning and approval process for prescribed burning be amended to allow flexibility for burning on optimum days. |
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3788 | 32 - Doctrine, standards, and reform | The Committee recommends that the Native Vegetation Council have a consistent approach to prescribed burning on both public and private lands. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3410 | 32 - Doctrine, standards, and reform | The Committee recommends that, following the development of standards of fire cover, related standards be established for: |
REC061-3257 | 9 - Community education | The Committee recommends that the FireVision concept used by the Metropolitan Fire Brigades Board be extended through the Directorate of School Education's Interactive Television Program to all emergency services and in particular to rural fire and emergency services. |
REC061-3247 | 32 - Doctrine, standards, and reform | The Committee recommends that the Ministry for Police and Emergency Services seek common national fire standards. |
REC061-3422 | 9 - Community education | The Committee recommends that the FireVision concept used by the Metropolitan Fire Brigades Board be extended through the Directorate of School Education's Interactive Television Program to all emergency services and in particular to rural fire and emergency services. |
REC061-3244 | 32 - Doctrine, standards, and reform | The Committee recommends that, following the development of standards of fire cover, related standards be established for: |
REC061-3412 | 32 - Doctrine, standards, and reform | The Committee recommends that the Ministry for Police and Emergency Services seek common national fire standards. |