Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4319 | 26 - Research | Climate and weather research: That, to enable effective mitigation and adaptation measures in response to changing climate risks, Government establish NSW as a world centre of disaster research and technology development. This should include: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
REC324-4307 | 9 - Community education | Flood education: That, to build disaster resilience in future generations as floods and other natural disasters are a fact of Australian life, the Department of Education should design, implement and deliver an evidence-based, targeted education campaign (like sun exposure) in schools (new disaster curriculum). |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4308 | 26 - Research | Compound mental helath studies: That, to inform Government policies and programs for mental health and disasters, Government commission a longitudinal study on the effect of consecutive disasters on community mental health. |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4266 | 1 - Land-use and building regs | That the NSW Government review the provision of temporary and long term housing options provided to those affected by the February-March 2022 floods, with a view to: • ensuring a range of options are identified and embedded within emergency and recovery plans, so that solutions can be implemented as soon as possible after a natural disaster • ensuring that housing options meet individual and community needs • removing planning impediments that prevent those from accessing more safe and secure housing in times of crisis. |
REC323-4267 | 1 - Land-use and building regs | That the NSW Government consider investing in supporting relocations, land swaps and providing fair and adequate compensation for landowners who wish to relocate from severely flood-impacted areas. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4257 | 1 - Land-use and building regs | That the NSW Government work with local government, industry and sustainable planning experts, including the Government Architect, on policy initiatives in the New South Wales planning system that will help deliver more resilient and sustainable homes, buildings and places. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3273 | 26 - Research | Collate data and research the impact of bushfires upon communities, firefighters and animals (both native and domestic) to identify appropriate medium and long-term welfare and support requirements. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3270 | 17 - Assets and technology | Review the use of aviation assets including facilities to operate them given the increased pressure from extended fire seasons on northern and southern hemisphere resources. Review line scanning capability with a view to providing real time data to the IMTs on where fires are burning using aviation assets as an intelligence tool rather than just a fire suppression capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1306 | 9 - Community education | Develop practical policy outcomes to support resilience (e.g. the 72- hour model) and promote this broadly to community through media, awareness campaigns, policies etc. Research should be undertaken to gain insight into the types of messaging and activities that have the most impact on sustained behaviour change within the community before committing to a particular model. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1380 | 13 - Mapping and data quality | That the NSW Rural Fire Service investigate mechanisms to enhance the predictability of megafires and how this information is communicated easily to the public. |
REC280-1386 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC280-1379 | 9 - Community education | That the NSW Rural Fire Service develop and implement a comprehensive community education campaign aimed at increasing community understanding of and support for hazard reduction burns. |
REC280-1385 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
REC280-1383 | 1 - Land-use and building regs | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1382 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC280-1399 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service remove from its boundary fencing policy and standard contract the condition that requires adjoining land owners to maintain a fence that has been damaged by trees falling from national park land. |
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1381 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC280-1398 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service: |
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1144 | 7 - Inter-agency communication | That SACFS consider a review to develop an effective interagency messaging system and agency resource management system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1503 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1502 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC261-1494 | 4 - Fire season preparation | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1515 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service: |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC261-1499 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC261-1514 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service adopt an interim fencing agreement in the immediate aftermath of a fire. This will enable emergency and interim works to commence, but features such as length, fencing components and site of the fence line are not binding. A final fencing agreement would be negotiated no earlier than six months following a major national park fire. |
REC261-1498 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC261-1513 | 17 - Assets and technology | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC261-1496 | 9 - Community education | That the NSW Rural Fire Service develop and implement a comprehensive community education campaign aimed at increasing community understanding of and support for hazard reduction burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0847 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC243-0846 | 17 - Assets and technology | That the Government adequately fund Community Safety and Emergency Services budgets so that fire-bombing aircraft are available on call for rapid deployment throughout Autumn and Spring at short notice to bomb fires at the earliest and safest possible opportunity. |
REC243-0848 | 17 - Assets and technology | That the Government resume funding for the helicopter surveillance service rather than by fixed-wing aircraft along Adelaide, South Coast and other high-risk coastlines during summer recreational periods for monitoring shark and other rescue situations, to bring the State back into line with interstate best practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2649 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0825 | 1 - Land-use and building regs | That the NSW Rural Fire Service hold discussions with the Department of Planning and Infrastructure and Local Government NSW on ways to improve compliance with development consents under section 76A of the Environmental Planning and Assessment Act 1979. |
REC237-0830 | 9 - Community education | That Bush Fire Risk Management Plans be tabled at Local Emergency Management Committees for comment. |
REC237-0829 | 9 - Community education | That Bush Fire Risk Management Plans be posted on the NSW Rural Fire Service website. |
REC237-0828 | 9 - Community education | That the NSW Rural Fire Service develop a strategy to better inform the community and NSW Rural Fire Service members about the NSW bush fire management system and its components. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0074 | 9 - Community education | SERCon consider a review of existing community-based educational programs, with a view to informing the community |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3615 | 9 - Community education | That the Department of Primary Industries should continue to raise awareness among producers of OJD risks and the operation of Sheep Health Statements. |
REC128-3613 | 9 - Community education | That the Department of Primary Industries and Rural Lands Protection Boards employ outreach activities to alert these small producers to their responsibilities and improve their awareness of animal and plant pests and diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3797 | 9 - Community education | The Committee recommends that the Native Vegetation Council continue to seek mechanisms to interact with, and educate the individual farmer and landholder with respect to the Native Vegetation Act, its regulations and exemptions. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |
REC122-3796 | 9 - Community education | The Committee recommends that the government undertake public education programs to increase the awareness of the community to bushfires, the role fire plays in ecosystems and what steps they should take to minimise the impact of a fire. |
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
REC122-3777 | 1 - Land-use and building regs | The Committee recommends that native vegetation, excluding road reserves be fenced. |
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3707 | 29 - Operational Health and Safety | The safety document management system should provide for the distribution of electronic versions of safety documentation to relevant staff. |
REC121-3743 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must have the external emergency door release clearly marked with the words “Emergency Door Release”. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3725 | 13 - Mapping and data quality | The data and information management system should be compatible with any data and information management system established by the ATSB for the designated interstate rail network, provided that the establishment of a compatible system does not reduce the amount or quality of the information obtained by ITSRR below the optimum levels which it needs to conduct trend analysis, and otherwise properly manage the safety of rail operations in New South Wales. |
REC121-3755 | 29 - Operational Health and Safety | The RailCorp Board should require a full review of the safety competence of RailCorp managers to ensure that each has the ability to bring about those safety reforms recommended in this report which are applicable to his or her position. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3735 | 29 - Operational Health and Safety | Risk assessments of occupational health and safety issues by RailCorp should include an analysis of broader public safety risks and not be confined to narrow occupational health and safety issues. |
REC121-3706 | 29 - Operational Health and Safety | RailCorp should establish a comprehensive safety document management system. |
REC121-3741 | 29 - Operational Health and Safety | The operation of the train doors should have an override facility whereby the train driver or the guard can override an internal passenger emergency door release system if the door release is interfered with when there is no emergency. There should be an alarm, together with an intercom, in the train guard’s compartment so that, if a passenger attempts to initiate an emergency door release, there is an appropriate delay during which time an alarm sounds in the train guard’s compartment and the guard can then, after first attempting to speak via the intercom to the person concerned, if necessary, override the door release, and make an appropriate announcement over the intercom system in the train. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3724 | 13 - Mapping and data quality | The ITSRR should establish a data and information management system, containing all data and information that it requires, to continually monitor the safety of the New South Wales rail system. |
REC121-3754 | 29 - Operational Health and Safety | The RailCorp Board should ensure that RailCorp has an adequate and integrated safety management system, including adequate systems for risk assessment, clearly defined safety responsibilities and accountabilities for persons holding management positions, and specific performance criteria against which evaluations can be made of safety performance and accountability for safety performance of all managers. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3734 | 29 - Operational Health and Safety | RailCorp should integrate its management of occupational health and safety into its overall safety management. |
REC121-3702 | 29 - Operational Health and Safety | Random alcohol testing should be continued. |
REC121-3740 | 29 - Operational Health and Safety | The internal passenger emergency door release should be fitted with a facility which prevents it from operating unless the train is stationary. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3711 | 29 - Operational Health and Safety | The ITSRR should establish an electronic document control system to enable effective and reliable information to be gathered for monitoring the safety of the New South Wales rail system. |
REC121-3749 | 29 - Operational Health and Safety | All new rolling stock must be designed with an area of the roof through which emergency services personnel can access a rail car without encountering wiring or other equipment. That access point must be clearly marked with words such as “emergency services cut here”. |
REC121-3682 | 29 - Operational Health and Safety | All new rolling stock should be designed to be compatible with at least level 2 automatic train protection discussed in chapter 7 of this report. |
REC121-3733 | 29 - Operational Health and Safety | RailCorp’s approach to occupational health and safety should be proactive and involve the systematic analysis of all current hazards, risks and controls and an assessment of their adequacy to reduce the risk of injury to, or death of, employees to an acceptable level. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3739 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must be fitted with external emergency door releases which do not require any special key or other equipment to operate. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3748 | 29 - Operational Health and Safety | All new rail cars must have appropriate signage and lighting identifying escape routes in the case of emergency. |
REC121-3681 | 29 - Operational Health and Safety | RailCorp should progressively implement, within a reasonable time, level 2 automatic train protection with the features identified in chapter 8 of this report. |
REC121-3732 | 29 - Operational Health and Safety | If ITSRR accepts such a plan as an appropriate response to the existing weak safety culture, ITSRR should approve it and monitor the effectiveness of the plan. |
REC121-3764 | 29 - Operational Health and Safety | The ITSRR should not grant accreditation to any rail organisation unless it has an integrated safety management system in accordance with any safety management system regulation and the guidelines published from time to time by ITSRR. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3738 | 29 - Operational Health and Safety | All passenger trains must be fitted with an internal passenger emergency door release. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3709 | 29 - Operational Health and Safety | RailCorp should provide access to electronic versions of safety documentation for all operational staff at their workplace. |
REC121-3747 | 29 - Operational Health and Safety | All trains should have windows available through which passengers can escape. |
REC121-3680 | 29 - Operational Health and Safety | All trains must be fitted with a minimum of two independent engineering defences to minimise the risk of derailment or collision in the event of train driver incapacitation. |
REC121-3731 | 29 - Operational Health and Safety | RailCorp should develop a plan to be submitted to ITSRR to address the deficiencies in the safety culture of RailCorp, including: |
REC121-3759 | 29 - Operational Health and Safety | A Safety Reform Program Director (hereafter referred to as SRPD), reporting directly to the Chief Executive of RailCorp, should be retained to manage, as head of a Safety Reform Program Office, any safety reform program being undertaken by RailCorp. The SRPD should work with the Chief Executive and senior management to ensure the implementation of an integrated safety management system and the cultural change required. The SRPD must have qualifications suitable for recognition by the Australian Institute of Project Management as a master program director. He or she should report to and be under the control of the Chief Executive, to ensure that the accountability of the Chief Executive is not reduced. The SRPD should co-ordinate and integrate any existing rail safety reform programs and, in consultation with and with the authority of the Chief Executive he or she should: |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3737 | 29 - Operational Health and Safety | There must be a minimum of two independent methods of self-initiated emergency escape for passengers from all trains at all times. |