Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4306 | 6 - Insurance and legal liability | NSW Reconstruction Authority: That, to provide rapid and effective recovery from floods (and other disasters) and to provide maximum mitigation of the impacts of future floods (and other disasters), Government establish a permanent state-wide agency, the NSW Reconstruction Authority (NSWRA) dedicated to disaster recovery, reconstruction and preparedness. The NSWRA should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3848 | 17 - Assets and technology | That, in order to enhance NSW’s ability to improve situational awareness, Government expand FRNSW’s Remotely Piloted Aerial Systems (RPAS) capability (both capital assets and trained operators) to major regional centres and ensure the NSW RFS and other NSW government agencies can access this capability as required. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3847 | 17 - Assets and technology | That, in order to ensure Australia’s fire fighting aerial capacity capitalises on existing assets and is made up of the right mix, Government: |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3843 | 17 - Assets and technology | That, in order to improve early fire suppression, the NSW RFS trial initial aerial dispatch in areas of high bush fire risk. The trial should identify the most appropriate and cost-effective mix of aircraft, and any associated infrastructure improvements that would be required. |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3837 | 17 - Assets and technology | That, in order to improve firefighter safety, Government fire authorities: |
REC315-3815 | 17 - Assets and technology | That, in order to equip NSW RFS with comprehensive information on all structures and assets at risk of bush fire, Government ensures that: |
REC315-3836 | 17 - Assets and technology | That, in order to ensure frontline personnel have appropriate personal protective clothing during bush fires: |
REC315-3849 | 17 - Assets and technology | That, in order to enhance NSW’s fire fighting capacity, Government trial aerial fire fighting at night in the 2020-21 season with a view to full implementation if successful. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4005 | 40 - Equipment and consumables | Where safety-lamps are used the lock should be of such a character as to prevent any workman opening it. If the "Protector" type of lamp be employed the necessity for a lock is the less necessary, as the unscrewing of this type of lamp extinguishes the light. |
REC002-4002 | 19 - Offences | Where safety-lamps are necessary - gas being present for (say) one month after being found in dangerous quantity - they should be securely locked by a man duly appointed, and tampering with them must be punishable by a simple and inexpensive process of law. |
REC002-4013 | 19 - Offences | Infringement of the regulations by either party should be followed by a summary form of justice, instituted before two Magistrates. |
REC002-4007 | 40 - Equipment and consumables | A measure of safety may be found in the use of high explosives combined with wet tamping, or, still better, water cartridges, instead of powder under any of its modifications. Encouragement ought also to be given to the use of patent multiple wedges and applicances of a like nature, for supplanting the use of explosives. Under all circumstances and conditions some provision should be adopted for compelling workmen to thoroughly undercut, shear, or nick, and generally to work the coal as directed by the Manager. |
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2339 | 19 - Offences | I recommend that the Law, Crime and Community Safety Council develop a mechanism to ensure that all information on criminal history (including bail) that is relevant to the investigation and prosecution of criminal offences is readily accessible to police and prosecutors across all Australian jurisdictions. |
REC292-2348 | 17 - Assets and technology | I recommend that if it has not already done so, the New South Wales Police Force acquires the audio surveillance technology that in similar circumstances would allow a device to be monitored in the Police Forward Command Post and/or the Police Operations Centre and that the organisation ensures that its capacity in this regard keeps pace with technological advances in the area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1402 | 6 - Insurance and legal liability | That the Ministry for Police and Emergency Services and NSW Treasury: |
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC280-1401 | 6 - Insurance and legal liability | That the NSW Government take all reasonable steps to expedite the process of establishing any legal liability for the losses incurred by property owners as a result of the Wambelong fire, and in the event that it is found liable, expedite the process of paying compensation claims. |
REC280-1400 | 6 - Insurance and legal liability | That the Office of State Revenue investigate mechanisms to enhance the affordability of insurance for properties and assets in fire affected areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1513 | 17 - Assets and technology | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC261-1519 | 6 - Insurance and legal liability | That the Ministry for Police and Emergency Services and NSW Treasury: |
REC261-1518 | 6 - Insurance and legal liability | That the NSW Government take all reasonable steps to expedite the process of establishing any legal liability for the losses incurred by property owners as a result of the Wambelong fire, and in the event that it is found liable, expedite the process of paying compensation claims. |
REC261-1517 | 6 - Insurance and legal liability | That the Office of State Revenue investigate mechanisms to enhance the affordability of insurance for properties and assets in fire affected areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1063 | 5 - Hazard reduction burns | That the National Parks and Wildlife Service consider reviewing its guidelines and protocols in respect of hazard reduction planning and burning-off operations in the light of the evidence from experts witnesses in these proceedings that the incidence of, and intensity of, major fires is increasing and in the light of expert evidence given in these proceedings concerning the dangers of vorticity-driven lateral spread. |
REC260-1070 | 5 - Hazard reduction burns | The NPWS conduct a review of its prescribed burns program to ensure, as far as reasonably practicable, that all necessary managerial approvals for a prescribed burn are provided as promptly as possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC259-1047 | 6 - Insurance and legal liability | That the insurance industry be asked to include in its “Code of Practice” the need to consult policy holders in bushfire prone areas on the issue of Bushfire Attack Level (BAL). This will ensure, to some extent, that policy holders insure their properties to a level commensurate with building costs under a variety of building standards and requirements.(For checking with RFS). |
Rec-ID | Code | Recommendation |
---|---|---|
REC163-1935 | 19 - Offences | The prescribed penalty notice penalty amount for section 99(6) of the Rural Fires Act 1997 be increased to $1,100. |
REC163-1934 | 19 - Offences | The prescribed penalty notice penalty amount for section 100(2) of the Rural Fires Act 1997 be increased to $1,100. |
REC163-1941 | 19 - Offences | A working group be established to consider methods of preventing criminal firestarting. |
REC163-1940 | 19 - Offences | That legislation be prepared by the Criminal Law Review Division of the Attorney General’s Department allowing designated officers of the Rural Fire Service to apply for a warrant in certain circumstances. |
REC163-1937 | 19 - Offences | That the Attorney General’s Department’s Crime Prevention Division consider the causes of, and any solution to, the high number of juveniles involved in causing bushfires. |
REC163-1936 | 19 - Offences | The prescribed penalty notice penalty amount for section 66(7) of the Rural Fires Act 1997 be increased to $1,100. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3703 | 6 - Insurance and legal liability | Alcohol and drug testing should be mandatory for any train driver or guard involved in any accident or incident. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3975 | 5 - Hazard reduction burns | To burn, where necessary, at least 33 feet where there is a risk of fire, on the outside of the railway fence, in conjunction with the railway employees. |
REC013_3973 | 40 - Equipment and consumables | To arrange for uniform water facilities, where possible, by having large taps attached to elevated tanks, suitable approaches made to dams for filling carts, and convienient gates to approach same. |
REC013_3972 | 40 - Equipment and consumables | To recommend to shire councils the purchase of fire carts and necessary equipment for fire fighting. |
REC013_3983 | 19 - Offences | To prohibit persons throwing lighted cigarettes, cigars and tobacco among any straw, stubble, grass or herbage during the months of September to March in any Bush Fire area, under a penalty not exceeding $10. |
REC013_3969 | 6 - Insurance and legal liability | The subsidy of such Fire Brigade organisations by the insurance companies and the Government to be given favourable consideration, from a proportion of which the expenses of the Central Administration might be met. |
REC013_3982 | 19 - Offences | To prohibit persons taking into a harvest field or through any grass or bush lands any motor, tractor, harvester, &c., which is not supplied with an approved fire extinguisher or without the exhaust being properly fitted and protected, under a penalty not exceeding $50. |
REC013_3980 | 6 - Insurance and legal liability | To provide that any person desirous of insuring his crops against fire shall first submit his proposal to two responsible persons for their endorsement that, in their opinion, the crop is likely to produce the value for which the insurer proposes to take out the oolicy, and that, in the event of such endorsement not being obtained, the risk be not accepted. |