Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4194 | 8 - Communications and warnings | Public communications: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and / or the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils and government to refine an operational relief and recovery public communications strategy that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4099 | 8 - Communications and warnings | Australian, state and territory governments should continue to explore the feasibility of a national, all-hazard emergency warning app. |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4098 | 8 - Communications and warnings | The Australian Government should facilitate state and territory governments working together to develop minimum national standards of information to be included in bushfire warnings apps. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4096 | 8 - Communications and warnings | State and territory governments should urgently deliver and implement thevall-hazard Australian Warning System. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4063 | 23 - Climate Change | Australian, state and territory governments should produce downscaled climate |
REC317-4094 | 8 - Communications and warnings | State and territory governments should expedite the development and implementation of the Australian Fire Danger Rating System. It should ensure that there is national consistency in the visual display of the AFDRS and action to be taken in response to each rating. |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1089 | 8 - Communications and warnings | GDF Suez improve its crisis management communication strategy for the Hazelwood mine in line with international best practice. |
REC264-1082 | 8 - Communications and warnings | The State review and revise its communication strategy, to: • needed for effective and rapid public communications during an emergency; and ensure all emergency response agencies have, or have access to, the capability and resources • ensure, where appropriate, that private operators of essential infrastructure are included in the coordination of public communications during an emergency concerning that infrastructure. |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1592 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy will work with the Communications Sector Group within the Trusted Information Sharing Network to develop best practice guidance for owners of critical communications infrastructure regarding public messaging during a prolonged telecommunications outage covering: |
REC233-1604 | 8 - Communications and warnings | Governments and other stakeholders consider reviewing their existing emergency management arrangements to ensure public communications are clear and the public is kept informed of the incident response. |
REC233-1603 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy (DBCDE) to work with the Triple Zero Awareness Work Group through Australian Communications and Media Authority's (ACMA) Emergency Service Advisory Committee to review Triple Zero awareness messages with regard to telecommunications outages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2823 | 8 - Communications and warnings | The Australian Government, in consultation with consumers and other relevant federal, state and territory agencies, develop a national communication strategy for consumers to be used in the event of an infectious disease outbreak. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1628 | 8 - Communications and warnings | The Emergency Services Agency should develop and test administrative procedures for the communications systems used for the distribution of public warning and emergency alerts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1873 | 8 - Communications and warnings | Fire services can improve outcomes by implementing standard procedures that ensure the welfare and safety of crews and the public are not compromised |
REC215-1877 | 39 - Disaster Risk Management | Regulators can help to achieve improved outcomes by considering the issues identified by this review |
REC215-1876 | 39 - Disaster Risk Management | Fire services can improve outcomes by initiating discussions with landfill operators about fire management planning and emphasising the critical importance of water supplies and early intervention |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0244 | 8 - Communications and warnings | Educate and engage with fire-affected landholders about the types of warnings, what they might expect from the warnings and their responsibility for response to prevent loss of life. |
REC196-0237 | 8 - Communications and warnings | Ensure that warning terminology used in the templates and FireWeb is consistent. |
REC196-0243 | 8 - Communications and warnings | Review the potential use of ‘crowdsourcing’ sites such as Bushfire Connect in community bushfire warnings. |
REC196-0236 | 8 - Communications and warnings | Review the use of the terms in the templates e.g. ‘out of control’ so that community misconceptions are minimised. |
REC196-0242 | 8 - Communications and warnings | Integrate social media into the OSOM system. |
REC196-0231 | 8 - Communications and warnings | Allow the MFB and SES access to using OSOM. |
REC196-0241 | 8 - Communications and warnings | Review OSOM to enable monitoring or tracking of where messages were sent, who they were sent to and when they are due for review. |
REC196-0246 | 8 - Communications and warnings | Review the suite of community bushfire warning systems available to tourists across the State. |
REC196-0229 | 8 - Communications and warnings | Amend SOP J4.01and other strategic and procedural documents to reflect the goal of ‘timely, relevant and tailored’ for community bushfire warnings. |
REC196-0240 | 8 - Communications and warnings | Improve links and interactions between the communication systems e.g. customise OSOM messages to each of the communication mechanisms, link OSOM with Emergency Alert. |
REC196-0245 | 8 - Communications and warnings | Develop a robust evaluation framework to review community bushfire warning policies, processes, systems and procedures both internally and with communities at regular intervals and immediately after a major bushfire event. |
REC196-0239 | 8 - Communications and warnings | Review Emergency Alert and OSOM systems to improve ease of use. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0328 | 8 - Communications and warnings | The Fire Services ensure that information and warnings are developed in accordance with the Victorian Warning Protocol |
REC195-0325 | 8 - Communications and warnings | The Fire Services evaluate the new information and warning systems to identify ways to integrate them and improve their capacity to issue timely, relevant and tailored messages. This should include the use of social media. |
REC195-0324 | 8 - Communications and warnings | The Fire Services, in consultation with media outlets, develop a more effective strategy for informing the community of Total Fire Ban days. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0331 | 8 - Communications and warnings | The Fire Services ensure information and warning projects are able to be integrated with a common operating platform. |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0399 | 8 - Communications and warnings | The committee recommends the government consider granting public broadcasters priority access to fuel during times of emergency for the purpose of broadcasting emergency warnings and information, and in a way that does not impede the ability of emergency service organisations to access fuel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2981 | 8 - Communications and warnings | The Department of Human Services should complete work on emergency communication and information management issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0143 | 8 - Communications and warnings | The Commonwealth Government work with the states and their agencies to ensure consistent terminology is used when communicating with the public. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3503 | 8 - Communications and warnings | Emergency Service Organisations review their use of Emergency Alerting System paging message categories to ensure that priority messages are not compromised by inappropriate use. An education program may be required to ensure that all users understand message categories, their intended use and ramifications of each category on network and message delivery sequence. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3497 | 8 - Communications and warnings | Emergency Service Organisations work with government departments, local governments and private industry to identify and implement a model for communication flow during an emergency incident. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3491 | 8 - Communications and warnings | The Victoria State Emergency Service improve its communication with local governments, especially in relation to severe weather and storm warning information. |
REC156-3515 | 8 - Communications and warnings | The electricity distribution businesses enhance power outage information on their websites which are accessible to electricity retail businesses, the media and the public and also consider improving their capacity to communicate with customers. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3509 | 8 - Communications and warnings | The Victoria State Emergency Service, Department of Primary Industries, Energy Safe Victoria and the energy sector develop a coordinated set of safety messaging about preparedness for storm events and clearly outline the responsibilities for delivering these messages before during and after an emergency. |
REC156-3507 | 8 - Communications and warnings | Victoria progress, as a matter of priority, a telephony based public emergency notification system to reduce demand on Triple Zero and other emergency telephone lines during a major emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3594 | 8 - Communications and warnings | Need for scripting of messages by fire agency representatives when promoting VBIL services via radio, TV and newspapers. |
REC132-3590 | 8 - Communications and warnings | Investigate procedures for updating the Victoria Bushfire Information Line (VBIL) Integrated Voice Response recorded message system to allow recording of permanent bushfire safety, and incident-specific, messages, accessible when the VBIL is experiencing high call volumes during large and/or numerous significant incidents |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1982 | 8 - Communications and warnings | That the Australian Federal Police and the Emergency Services Agency agree on a policy on community safety and evacuation during bushfires, based on the Australasian Fire Authorities Council position outlined in its paper Community Safety and Evacuation during Bushfires. Community education programs should incorporate advice on this, including the ‘stay or go’ policy |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-1998 | 8 - Communications and warnings | That a system of public warnings that uses grid references shown on the maps in the Canberra telephone directory be adopted |
REC126-1997 | 8 - Communications and warnings | That the Emergency Services Agency conduct investigations - and liase with emergency services agencies in other jurisdicions - in order to ascertain what technologies exist and are effective for use in disseminating warnings and associated information to the community of the ACT |
REC126-1994 | 8 - Communications and warnings | That the Emergnecy Services Agency publicise and demonstrate the use of the Standard Emergency Warning Signal and provide to the community adequate explanation of the application of the signal. This should occur at least annually, in conjunction with any pre-summer fire awareness initiatives |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3888 | 8 - Communications and warnings | Strengthen internal and external communications to ensure adequate stakeholder involvement throughout the prescribed burning program: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2112 | 8 - Communications and warnings | The Working Group recommends that the Commonwealth Attorney General’s Department hold discussions with the Commonwealth Department of Communications, Information, Technology and the Arts regarding the Integrated Public Telephone Network Database (IPND) being made accessible for use in times of emergency where the need to disseminate community information and warnings to telephones within a specified area is identified. Discussions should also be held between the Commonwealth Attorney General’s Department and with the Federal Privacy Commissioner’s Office to identify any impediments to the use of the IPND in such circumstances. |
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2299 | 8 - Communications and warnings | That consideration be given to formalising Australian Broadcasting Corporation Local Radio as the official emergency radio station for Victoria, given it is the only radio station that can cover the whole of the State. |
REC104-2215 | 8 - Communications and warnings | That the Coordinator-in-Chief of Emergency Management directs the Media sub-committee of the State Emergency Response Committee to review the use of the Standard Emergency Warning Signal and its accompanying message. |
REC104-2298 | 8 - Communications and warnings | That relevant Government agencies including Emergency Communications Victoria, the Bureau of Emergency Services Telecommunications and the Victoria Police Media Unit, evaluate the proposals put forward by the Australian Communications Authority with respect to the hearing impaired. |
REC104-2297 | 8 - Communications and warnings | That the model of community engagement developed by DSE and CFA and applied during the 2002-2003 fires is further developed and refined, particularly in regard to short-duration, rapidly escalating incidents. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2302 | 8 - Communications and warnings | That opportunities be explored to use community radio to complement other methods of communication with isolated communities. |
REC104-2296 | 8 - Communications and warnings | That in relation to the provision of information to communities affected by fires and other emergencies, DSE and CFA ensure that: |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2301 | 8 - Communications and warnings | That CFA and DSE work with Australian Broadcasting Corporation Local Radio to identify black spots, and explore opportunities to further improve coverage for broadcasting emergency information. |
REC104-2287 | 8 - Communications and warnings | That DSE and CFA work with the Bureau of Emergency Services Telecommunications to ensure that rural communication issues are appropriately addressed in the Statewide Integrated Public Safety and Communications Strategy, and that priorities and business cases are agreed for critical issues. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2300 | 8 - Communications and warnings | That Victoria Police Media Unit coordinate work with the Australian Broadcasting Corporation and the emergency service agencies to implement this arrangement. |
REC104-2216 | 8 - Communications and warnings | That Victoria include an agenda item for both the National Emergency Management Committee and the National Meeting of Emergency Services Ministers recommending that the Australian Communications Authority review both the Commercial Radio Codes of Practice and Guidelines, and Community Broadcasting Codes of Practice, to ensure they provide necessary guidance and obligations on radio stations during emergencies and in relation to emergency warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |