Rec-ID | Code | Recommendation |
---|---|---|
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2016 | 6 - Insurance and legal liability | Review legal liability of participants in prevention and mitigation preparedness, response and recovery activities. |
REC286-2093 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami warning arrangements with signage and audible warning systems at key exposed locations (e.g. Port Arthur and Kingston Beach). |
REC286-2092 | 37 - Funding | Ensure sufficient investment in controls across the PPRR spectrum with a focus on Prevention and Mitigation. |
REC286-2091 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami detection buoy network. |
REC286-2077 | 6 - Insurance and legal liability | Improve working relationship with the insurance industry to access impact information. |
REC286-1479 | 6 - Insurance and legal liability | Ensure appropriate levels of insurance of public assets from flood risks. |
REC286-2047 | 6 - Insurance and legal liability | Raise public awareness of the limitations of general insurance relating to landslide. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-2020 | 6 - Insurance and legal liability | Improve insurance affordability. |
REC286-2095 | 37 - Funding | Investigate the costs and benefits of delivering a public education and awareness program. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1408 | 7 - Inter-agency communication | That the Department of Health & Human Services uses Emergency Services Telecommunications Authority Computer Aided Dispatch data to report ambulance emergency response time performance. |
REC274-1405 | 37 - Funding | That the Department of Justice & Regulation broadens Budget Paper 3 response time measures to more comprehensively cover emergency responses to fires, rescues and other emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1483 | 7 - Inter-agency communication | That the Emergency Services Telecommunications Authority includes Victoria State Emergency Service vehicle capability details in the Computer Aided Dispatch database. |
REC262-1491 | 7 - Inter-agency communication | That Emergency Management Victoria expedites the expansion of the Rural Mobile Radio network to all emergency services organisations. |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
REC262-1487 | 7 - Inter-agency communication | That the Emergency Services Telecommunications Authority, assisted by the Inspector-General for Emergency Management and responder agencies, improves the process for changing call-taking and dispatch procedures by comprehensively appraising the costs, benefits and operational impacts of these changes and agreeing a plan for their implementation with all affected agencies. |
REC262-1486 | 7 - Inter-agency communication | That Emergency Management Victoria novates the head contract for the StateNet Mobile Radio network to the Emergency Services Telecommunications Authority. |
REC262-1485 | 7 - Inter-agency communication | That Victoria Police implements the recommendations relating to protective services officers in the Service Demand and Dispatcher Capacity Analysis dated September 2013 and: |
REC262-1484 | 7 - Inter-agency communication | That Ambulance Victoria: |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2592 | 37 - Funding | That duplication of infrastructure be costed and taken into account when considering whether to proceed with the Whole of Government network. |
REC245-2589 | 7 - Inter-agency communication | That TFS and Ambulance Tasmania work together to resolve problems around congestion, particularly during the fire season. |
REC245-2588 | 7 - Inter-agency communication | That Tasmania Police, Tasmania Fire Service (TFS), Ambulance Tasmania and State Emergency Services (SES) investigate ways of providing secure and confidential radio communications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2616 | 6 - Insurance and legal liability | That once the review of the Emergency Management Act has been finalised, any reference to the liability of councils should be mirrored in both the EM Act and the F&ES Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0838 | 37 - Funding | That the Government cease drawing from South Australia Police or other Community safety and emergency service budgets to fund the Directorate and instead merge its work and functions with the pre-existing South Australia Fire and Emergency Services Commission for zero total State and other Community safety and emergency service budget impact. |
REC243-0843 | 6 - Insurance and legal liability | That the Government work with the Local Government Association to resolve questions of liability by volunteers who work for Councils, as raised with the Select Committee. |
REC243-0835 | 37 - Funding | That the Government increase the budgets of all emergency services and community safety organisations, including: i. seeking Federal funding where appropriate (and assisting at no cost volunteer organisations with the grants application process); and ii. considering, with full public and cost benefit analysis, reviewing the effectiveness and efficiency of the Emergency Services Levy; and iii. consider including St John Ambulance Australia SA Ltd in the bodies to benefit from the Emergency services Levy if the funding of other Community Safety and Emergency services providers is improved in line with this recommendation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2637 | 37 - Funding | That the Government increase the budgets of all emergency services and community safety organisations, including: |
REC242-2650 | 37 - Funding | That the Government resume funding for the helicopter surveillance service rather than by fixed-wing aircraft along Adelaide, South Coast and other high-risk coastlines during summer recreational periods for monitoring shark and other rescue situations, to bring the State back into line with interstate best practice. |
REC242-2648 | 37 - Funding | That the Government adequately fund Community Safety and Emergency Services budgets so that fire-bombing aircraft are available on call for rapid deployment throughout Autumn and Spring at short notice to bomb fires at the earliest and safest possible opportunity. |
REC242-2640 | 37 - Funding | That the Government cease drawing from South Australia Police or other Community safety and emergency service budgets to fund the Directorate and instead merge its work and functions with the pre-existing South Australia Fire and Emergency Services Commission for zero total State and other Community safety and emergency service budget impact. |
REC242-2642 | 6 - Insurance and legal liability | That with regard to volunteer community safety and emergency service organisations that do not own land where their facilities exist: |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2791 | 37 - Funding | The committee recommends that the government develop a process by which the ATSB can request access to supplementary funding via the minister. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2835 | 37 - Funding | The committee recommends that the Australian Government direct an appropriate portion of the proceeds derived from the auction of spectrum to fund the allocation of 20 MHz of spectrum in the 700 MHz band for the purposes of a national public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1856 | 37 - Funding | The Ministers for Emergency Services, Environment and Police provide additional funds in the 2013-14 Budget so that the State’s emergency response agencies can implement a Psychological First Aid approach to preparing staff to deal with critical incidents and disasters, as is used in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1892 | 37 - Funding | The Committee recommends that the Australian Government allocate additional and continuing funding in the 2012–2013 budget to the Insurance Law Service to establish a consumer advisory position at the Financial Services Ombudsman. The position should be co-funded by the Insurance Law Service and the insurance industry. |
REC206-1891 | 37 - Funding | The Committee recommends that the Australian Government and relevant State and territory governments jointly allocate additional and continuing funding in the 2012–13 budget to the Insurance Law Service for the mobilisation of a temporary physical presence in areas of need following natural disasters. The service should be available to all persons in an affected disaster area and not subject to means-testing. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC185-1933 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Treasury clarify what is meant by the term 'cost-effective' as it relates to the 2011 NDRRA Determination and the scrutiny of the states' and territories' insurance arrangements. |
REC185-1932 | 6 - Insurance and legal liability | The committee recommends that a particular focus of the Natural Disasters Insurance Review into the adequacy of current insurance arrangements should be on whether the international insurance market offers reinsurance for the states' and territories' road networks. |
REC185-1930 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Government consult with state and territory governments to ensure that the states' and territories' captive insurance and reinsurance arrangements are reported transparently and on a comparable basis. |
REC185-1931 | 37 - Funding | The committee recommends that the Commonwealth Grants Commission ensures that as part of the current redesign of its data request, state and territory governments are required to include their past insurance and reinsurance receipts for natural disaster insurance premiums. These data must be taken into account by the Commission in determining the states' GST share. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0057 | 7 - Inter-agency communication | SEMC and EM WA should: ensure that agencies have a common or compatible crisis information management system in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3016 | 37 - Funding | ESWG recommends investigation of options to fund NGERAC’s on-going activities including through AEMO’s funding model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3189 | 37 - Funding | The ANAO recommends that, to ensure that grant conditions are satisfied, EMA enhance procedures to monitor the progress of projects and follow up those behind schedule or not fulfilling funding agreement requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3207 | 37 - Funding | To further enhance Australia’s disaster mitigation, preparedness, response and recovery arrangements in the event of possible major coastal disasters, the Committee recommends that the Australian Government establish a grants program, the Coastal Natural Disaster Mitigation Program, to fund natural disaster mitigation projects in the Australian coastal zone. |
REC145-3200 | 37 - Funding | The Committee recommends that the Australian Government: |
REC145-3212 | 6 - Insurance and legal liability | The Committee recommends that the Australian Government request the Productivity Commission to undertake an inquiry into the projected impacts of climate change and related insurance matters, with a particular focus on: |
REC145-3236 | 37 - Funding | The Committee recommends that the Australian Government provide funding support for the ongoing activities of the Australian Coastal Alliance in providing a national information and communication interface between research organisations and local government authorities and other coastal stakeholders. |
REC145-3232 | 37 - Funding | The Committee recommends that the Australian Government give consideration to establishing a separate funding program for infrastructure enhancement in coastal areas vulnerable to climate change. Such funding should be provided according to a formula requiring contributions, either financial or in-kind, from state governments and relevant local government authorities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3576 | 37 - Funding | That Fire and Emergency Services Authority of Western Australia and Main Roads Western Australia, in consultation with the Western Australian Local Government Association, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs. In particular consideration should be given to regulations applying in the eastern states i.e. Queensland. |
REC143-3589 | 37 - Funding | That consideration be given to the establishment of a ‘Heritage Reserve Fund’ that might underwrite urgent initial repairs to private heritage listed properties. |
REC143-3586 | 37 - Funding | That the ‘opportunity cost’ for Local Authorities in meeting the 25% contribution to the restoration of eligible public assets damaged by a natural disaster event be considered when FESA and Main Roads Western Australia, in consultation with Western Australian Local Government Authority, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs as recommended in Recommendation 1. |
REC143-3582 | 37 - Funding | That the Department of Treasury and Finance, in consultation with FESA, consider alternative funding arrangements to alleviate the need for FESA to ‘underwrite’ NDRA costs during the year. |
REC143-3581 | 37 - Funding | That, in tandem with their consideration of local government cost sharing arrangements under WANDRA (refer Recommendation 1), the Fire and Emergency Services Authority and Main Roads Western Australia also establish ‘exceptional circumstances’ criteria to provide for additional assistance to local government where it may be warranted in order to avoid undue financial pressure caused by delays to secure reimbursement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3552 | 37 - Funding | Department of Health and Human Services (DHHS) to fund 3 Full-Time Equivalent (FTE) Senior Registrar positions at the Royal Hobart Hospital (RHH) for the Tasmanian Medical Retrieval Service (TMRS). One registrar in the Anaesthesia Department, one in the Intensive Care Unit and one in Emergency Department is proposed. |
REC140-3568 | 37 - Funding | The State Medical Retrieval Cost Centre (TMRS and NETS) be formed and be supported by the appropriate administrative and resource accountant expertise. This cost centre should be placed with those responsible for its management. |
REC140-3567 | 37 - Funding | A uniform retrieval charge to the region of referral should be considered. This should be independent of the mode of transport used. |
REC140-3558 | 6 - Insurance and legal liability | DHHS need to confirm adequate accident insurance coverage for staff working in retrieval medicine. Coverage specific to helicopter and fixed wing duties is required. |
REC140-3554 | 37 - Funding | DHHS fund the equivalent of 2 FTE Consultant positions for retrieval duties (1.5 FTE existing, 0.5 FTE new) |
REC140-3553 | 37 - Funding | RHH Neonatal Emergency Transport Service receive DHHS funding for a Senior Registrar to assume the responsibilities of retrieval staffing, quality assurance, data collection and reporting demands. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3703 | 6 - Insurance and legal liability | Alcohol and drug testing should be mandatory for any train driver or guard involved in any accident or incident. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3640 | 37 - Funding | The ANAO recommends that the Attorney-General’s Department better monitor and account for the expenditure of individual exercise costs under the National Capability Development Exercise Programme, through: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2119 | 6 - Insurance and legal liability | The Working Group recommends that the National Recovery Coordinators Group approach the Investment and Financial Services Association Limited, with a view to identifying the most appropriate way of engaging the life insurance industry in the recovery process. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |