Rec-ID | Code | Recommendation |
---|---|---|
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
REC321-4211 | 1 - Land-use and building regs | We recommend that CFA (in consultation with FRV) improves planning on private land to ensure risk assessments and plans are conducted consistently across public and private land to address state-wide bushfire risk based on where and how they can most effectively reduce risk. |
REC321-4214 | 1 - Land-use and building regs | We recommend that DELWP determines which elements of different regional planning approaches are the most effective and implements these across the state. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4215 | 1 - Land-use and building regs | We recommend that DELWP develops more holistic bushfire-management planning that focuses on the best mix of risk treatments rather than planned burning alone. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC294-1364 | 24 - Govt responsibility | The Chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services recommend implementing the Mackay District Improvement Strategy (refer to page 53 of the inquiry). |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1195 | 5 - Hazard reduction burns | The Committee finds that on the evidence presented, that the Fuel Reduction Burn Program should be maintained and have its budget directly funded to ensure that the program continues and does not hinder other services or programs. |
REC288-1199 | 36 - Volunteers | The Committee finds that on the evidence presented, that volunteer firefighters are at risk of being undervalued and underrated and that the Government should use best endeavours to ensure the full acknowledgement and recognition of these services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2521 | 36 - Volunteers | The report recommends that Ambulance Tasmania investigate whether higher proportions of volunteers were impacting on mobilisation times in the North. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC279-1230 | 36 - Volunteers | Volunteer Retention: By April 2015, develop strategies and resources to improve volunteer retention, including: a) induction and development of leaders b) health checks for units to identify and address areas for improvement c) pathways for volunteers to take on greater responsibility d) consultation and communication e) recognition for volunteers and their employers |
REC279-1228 | 36 - Volunteers | Volunteer Workforce Plan: By December 2014, develop a volunteer workforce plan to focus resources for recruitment and retention on areas of greatest need. The plan should be based on regional capability plans that assess in a consistent way: a) how many volunteers they have and need b) the gaps and risks around volunteer numbers, skills and training |
REC279-1227 | 36 - Volunteers | Improve Analysis and Reporting: By December 2014, improve analysis and reporting on management information about volunteers, including: a) numbers, contribution, skills, profile, availability and turnover b) reasons for joining and leaving c) gaps in data completeness and quality This should enable SES to demonstrate an improvement in the completeness and accuracy of management information by April 2015 |
Rec-ID | Code | Recommendation |
---|---|---|
REC276-1177 | 36 - Volunteers | Within 12 months, develop volunteer specific policies and procedures, including fatigue management, consistent with the Guidelines for Successful Partnerships between Public Sector Agencies and Volunteers. |
REC276-1176 | 36 - Volunteers | Within 12 months, improve its processes for collecting and maintaining volunteer membership, availability and training records. To do this it will need to work with local information. governments to improve the accuracy of LG volunteer membership |
REC276-1175 | 36 - Volunteers | Continue to implement the major change projects it has in place, including Professional Pathways, and review them to assess if they will address all the key findings in this report. In particular, within six months DFES should set priorities and Sustainability Strategy. begin implementing the Emergency Services Volunteer Workforce |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
REC268-1431 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider new and emerging technologies for issuing warnings (including opportunities for Emergency Alert to be distributed in other languages or to people with vision or hearing impairment). |
REC268-1427 | 8 - Communications and warnings | The Warning and Alert Systems training package is updated to align the content to the Standard for Disaster Management in Queensland and to include advice and scenarios from the Information Commissioner. |
REC268-1426 | 8 - Communications and warnings | A qualitative assessment of public information and warnings arrangements is undertaken as part of the 2016 disaster management plan assessment process. |
REC268-1425 | 8 - Communications and warnings | The Public Information and Warnings Sub-plan Guide is reviewed to include: |
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
REC268-1433 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider supporting local government in the annual development of at least one pre-formatted Emergency Alert message and polygon map based on a risk assessment and hazard modelling. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1096 | 36 - Volunteers | CFA should: develop exit surveys and associated management reports based on meaningful analysis as a way to better inform it about the reasons that volunteers leave |
REC263-1094 | 36 - Volunteers | CFA and VICSES should: evaluate volunteer support systems and processes |
REC263-1093 | 36 - Volunteers | VICSES should: review and improve data quality around volunteer numbers and skills |
REC263-1091 | 36 - Volunteers | CFA and VICSES should: develop recruitment and retention strategies to guide these activities centrally, regionally and at the district, brigade and unit level, so that approaches are consistent with the organisations’ strategic goals |
REC263-1090 | 36 - Volunteers | CFA and VICSES should: improve their central and regional oversight of volunteer workforce management by strategically using the available information, such as volunteer demographic data, Brigade Operational Skills Profiles and ERAS-e profiles, and developing new information, such as risk assessment, to increase their awareness of: x x actual and required volunteer numbers the gaps and risks around volunteer capability and capacity |
REC263-1098 | 36 - Volunteers | VicSES should: improve ERAS-e profiles to reflect volunteer activity and availability |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0788 | 25 - Inquiry, audit, lessons management and after action review | TFS seek to address the following outstanding items from the recommendations of the Victorian Bushfires Royal Commission. § 45 out of 53 Community Bushfire Response Plans for “at risk” communities have been finalized. The remaining eight should be completed as a priority action. § That TFS progress the development of Community Bushfire Mitigation Plans for the 53 at risk communities, possibly as an action for reactivated Fire Management Area Committees. § TFS, together with other ESOs and local government, should develop a common comprehensive approach to the option of planned evacuation from dangerous or potentially dangerous areas to safer areas and eventual return. § TFS should include factors for consideration for evacuation during a bushfire into their training doctrine for Incident Controllers. § The IAP Template and its application be reinforced as an important operational requirement for IMT’s during the 2013-14 pre-season briefing program. 10 § That TFS review their use of IRMS to ascertain if either its full potential is not being realized through a lack of operator training or it is in fact not providing the required functionality and there is a need to research an improved resource management system which enhances interoperability. § The TFS Publication: Guidelines for Development in Bushfire Prone Areas of Tasmania http://www.fire.tas.gov.au/userfiles/stuartp/file/Publications/BushDeve… s2012.pdf requires an update to reflect the provisions of Planning Directive #5 Bushfire-Prone Areas Code. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2598 | 24 - Govt responsibility | That government considers the establishment of a separate unit to implement and operate a Whole of Government network if existing stakeholders fail to make significant progress toward an agreed Whole of Government solution. |
REC245-2596 | 24 - Govt responsibility | That the Whole of Government project’s objectives should include meeting entity requirements and the consultant be asked to reevaluate the revised set of objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1605 | 24 - Govt responsibility | The Justice and Community Safety Directorate should continue to review its strategic and accountability indicators and the Territory and Municipal Services Directorate should commence a review of its strategic and accountability indicators. The directorates should consult to develop complementary measures which better assess their bushfire management activities. |
REC228-1619 | 1 - Land-use and building regs | The Territory and Municipal Services Directorate, in consultation with the Emergency Services Agency, should improve its management of Land Management Agreements, with respect to rural leaseholders’ fire management responsibilities, by: |
REC228-1618 | 24 - Govt responsibility | The Emergency Services Agency, the Environment and Sustainable Development Directorate and the Territory and Municipal Services Directorate should strengthen across-Government delivery of major projects in the Strategic Bushfire Management Plan and Regional Fire Management Plans by collectively: |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1628 | 8 - Communications and warnings | The Emergency Services Agency should develop and test administrative procedures for the communications systems used for the distribution of public warning and emergency alerts. |
REC228-1610 | 24 - Govt responsibility | The Emergency Services Agency should annually review fire management zones and the Territory and Municipal Services Directorate should subsequently update the Regional Fire Management Plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0228 | 8 - Communications and warnings | Tasmanian entities with responsibilities for bushfire management actively pursue national consistency of warning systems and emergency warning signals through national bodies such as the National Emergency Management Committee. |
REC193-0227 | 5 - Hazard reduction burns | Local government councils implement a zoning approach to fuel management as recommended by COAG 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1928 | 24 - Govt responsibility | That the Queensland Reconstruction Authority finalise the value for money policies and procedures, particularly those that take into account the role and responsibilities of the external service providers. |
REC190-1927 | 24 - Govt responsibility | That the Queensland Reconstruction Authority agree on and finalise the work plan and attach it as a Schedule to the Agreement as required in section 15 of the Agreement. |
REC190-1926 | 24 - Govt responsibility | That the Queensland Reconstruction Authority clarify and communicate the roles of the Lines of Reconstruction sub-committees to the Chairs of each committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2981 | 8 - Communications and warnings | The Department of Human Services should complete work on emergency communication and information management issues. |
REC179-2980 | 24 - Govt responsibility | The Department of Human Services should work with regions and partner agencies at the state level to create consistent, streamlined impact assessment processes and systems. |
REC179-2979 | 24 - Govt responsibility | The Department of Human Services should communicate strategic priorities to achieve state and regional level alignment in building recovery capacity and capability. |
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
REC179-2983 | 24 - Govt responsibility | The Department of Human Services should work with the State Emergency Recovery Planning Committee, regions, and other partners to facilitate understanding and ownership of roles and responsibilities for common recovery services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0049 | 24 - Govt responsibility | SEMC and EM WA should: formally and regularly assess which hazards the state should prepare for |
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
REC170-0050 | 24 - Govt responsibility | SEMC and EM WA should: assess the state’s level of preparedness at least annually, identifying gaps and significant risks |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |
REC111-3936 | 24 - Govt responsibility | To enhance the governance of the Queensland disaster management system, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services ensure that — |
REC111-3935 | 24 - Govt responsibility | To provide the strategic leadership and governance required to implement the Disaster Management Act 2003, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable governance framework for disaster management which includes the establishment of — |