Rec-ID | Code | Recommendation |
---|---|---|
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
REC322-4248 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the prescribed burn program for K’gari be developed by the Department of Environment and Science, in collaboration with the Locality Specific Fire Management Group and the Butchulla people, based on the principles of the National Position on Prescribed Burning. This program should incorporate a process for monitoring and evaluation of outcomes and integration of evolving fire management practices. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4251 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services facilitate an annual state level exercise of the Queensland Bushfire Plan that includes all relevant stakeholders and land managers. The exercise should focus on roles, responsibilities, interagency arrangements and handover arrangements between agencies and land managers. |
REC322-4223 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the Department of Environment and Science implements the proposed treatments for fire identified in the Queensland Parks and Wildlife Service K’gari Compliance Strategy. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
REC322-4242 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends the Department of Environment and Science review the format and delivery of Queensland Parks and Wildlife Service annual fire refresher training to include a scenario-based exercise. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3268 | 12 - EM agency and authority | Incorporate Farm Firefighting Units (FFUs) into the Australasian Inter Service Incident Management System (AIIMS) so that IMTs are aware of their presence on the fireground and their welfare and risks are understood. |
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
REC309-2469 | 12 - EM agency and authority | Entities with disaster management responsibilities need to integrate the eight priorities identified within the Emergency Management Sector Adaptation Plan for Climate Change into their disaster management planning cycle. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2444 | 41 - Emergency Management exercises | All disaster management groups should run an exercise that has full involvement of a hazard-specific primary agency in the next 12 months and regularly thereafter. |
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1335 | 12 - EM agency and authority | Explore alternative emergency management models including the alternative model proposed above to establish a South Australian Emergency Management Office and State Relief and Recovery Office within the South Australian Fire and Emergency Services Commission, to ensure that all the objects and guiding principles of the Emergency Management Act 2004, and State Emergency Management Plan are addressed efficiently and effectively. |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1298 | 12 - EM agency and authority | That the State Emergency Service, in consultation with key stakeholders, identify and implement a robust system and procedures for prioritising, allocating and coordinating multiple tasks. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1325 | 12 - EM agency and authority | Review and reinstate the State Emergency Management Training Officer and State Emergency Management Planning Officer (capability development) positions to operate with a broad, strategic and leadership focus. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1322 | 12 - EM agency and authority | Consider opportunities to identify synergies between the incident management systems used in SA being the, Australasian Interservice Incident Management System (AIIMS) and ICCS Plus. This might include joint training and exercising in roles that are common across both systems. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1137 | 12 - EM agency and authority | Review all current SACFS operational facilities (Group, ICC, RCC and SCC) to provide more effective communications, connectivity and resource management. |
REC273-1136 | 12 - EM agency and authority | Plan the establishment of one multi-agency Coordination Centre with sufficient capacity and capability to deal with all incidents in South Australia. |
REC273-1130 | 12 - EM agency and authority | Reviewing how Regional resources are managed and tracked and incorporate into COSO’s to ensure that there is complete situational awareness as to the location and tasking of CFS resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC270-1146 | 12 - EM agency and authority | Strengthens its oversight role as lead agency for mitigating Queensland's bushfire risk to acceptable levels by: · coordinating land managers' efforts to assess and mitigate bushfire risk · formalising the role of fire management groups to manage Queensland's fuel loads, including reporting planned and conducted hazard reduction burns and the effectiveness of hazard reduction burns · amending its bushfire mitigation planning to address prevention, preparedness, response and recovery and to manage Queensland's residual bushfire risk · developing and implementing a coordinated strategy to address arson, deterring would-be offenders and rehabilitating convicted offenders · working with local councils to develop and communicate local bushfire plans for communities located in high risk, bushfire-prone areas |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0957 | 12 - EM agency and authority | That a strong emphasis be placed on the establishment and recruitment of PCYC emergency cadets. |
REC241-0990 | 12 - EM agency and authority | Membership of the District Fire Management Group is at the discretion of the Chair of the District Fire Management Group, however members must have the necessary expertise and experience for the role and membership should include where applicable, the District Inspector - Rural Fire Service Queensland, a representative of relevant local governments and representatives of agencies responsible for parks and wildlife, transport and main roads, forestry and natural resources among other appropriate representatives. |
REC241-1019 | 12 - EM agency and authority | That a local committee consisting of Elders and community leaders be formed in remote and Indigenous communities to determine Brigade membership applications. |
REC241-0962 | 12 - EM agency and authority | That Rural Fire Service Queensland consider service delivery needs with a view to establishing boundary/ staff/budget changes according to State standards. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1038 | 12 - EM agency and authority | That District Inspectors retain the discretion to allocate gratuity to Fire Wardens for out of pocket expenses if required. |
REC241-0972 | 12 - EM agency and authority | That Rural Fire Service Queensland designate a position of Lands Procurement Officer to support volunteers by project managing the acquisition of land for Brigade sheds and their construction where required. |
REC241-1005 | 12 - EM agency and authority | That fire groups can only be formed through the agreement of all brigades that will become a part of that group, and the management and operational procedures of the group must be approved by the contributing brigades. Local District Inspectors are to provide mentoring and support when brigades form a group. |
REC241-0953 | 12 - EM agency and authority | That a separate area of responsibility be established to provide independent oversight and monitor disaster readiness across all hazards. |
REC241-0989 | 12 - EM agency and authority | That the first tier comprise at least one District Fire Management Group in each Rural Fire Service Queensland District. The District Fire Management Group will be chaired by a person with the necessary expertise and experience, nominated by the community and appointed by Government. Chairs will hold the deciding vote in matters related to fire management at the local level. |
REC241-1014 | 12 - EM agency and authority | That the Rural Fire Service Queensland should engage a private provider offsite and outside the Government firewall to establish an email address for each Brigade and Fire Warden. The email address would reflect the Brigade name and Fire Warden district. E.g.: GreenbankRFB@msn.com.au |
REC241-0961 | 12 - EM agency and authority | That staffing at Rural Fire Service Queensland District offices remain at current levels within establishment and, if needed, base staffing levels be increased. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1037 | 12 - EM agency and authority | That Rural Fire Service Queensland and its staff be exempt from the Travel Management System. The Travel Management System does not work in the rural fire operation areas as it is not flexible in the rapid escalation of wild fire events or cater for volunteering timeframes. It has been proven to be inefficient and costly. |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0952 | 12 - EM agency and authority | That an operational organisation be established comprising of three streams – a. urban fire service; b. rural fire service; and c. the state emergency service. Each of the three organisations will be led by a Deputy Chief Officer, reporting to a Chief Officer. |
REC241-0988 | 12 - EM agency and authority | That the planning system is to have a two tiered structure comprising District Fire Management Groups and linking to the State Disaster Management Group. |
REC241-1010 | 12 - EM agency and authority | That where a Brigade supports another community and this involves the use of any brigade equipment it shall be the decision of that brigade in relation to the deployment and use of their equipment and resources. |
REC241-0960 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices remain at least at their current number of 14, with consideration given by the Rural Fire Service Queensland to expanding the number of District offices by opening an office in the South Burnett, considering a new office in the southern Central Highlands, and the option of part time offices on a risk/need/growth basis, particularly in north-west Queensland. |
REC241-0993 | 12 - EM agency and authority | That wherever possible, for future appointments of Fire Wardens, where that Wardens’ district is totally covered a by Rural Fire Brigade, consideration should be given that the appointed Fire Warden is a Rural Brigade Member. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-0966 | 12 - EM agency and authority | That District offices be located in areas that enhance ease of access for out of town volunteers and the general public and also provide suitable parking, onsite storage and be suitable for operational use. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0987 | 12 - EM agency and authority | That to assist the Rural Fire Service Queensland and other agencies in managing wildfire risk, a planning system for wildfire management be established in legislation that complements the existing disaster management arrangements. |
REC241-1008 | 12 - EM agency and authority | That the colour of Rural Fire Service Queensland Brigade operational vehicles remain yellow and that they retain the Rural Fire Service Queensland logo. |
REC241-0959 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices report directly to the Deputy Chief Officer. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-1021 | 12 - EM agency and authority | That Brigades that do not have a truck and are currently classified as Rural conduct a self-determination to ascertain if they wish to be reclassified as a Primary Producer Brigade. |
REC241-0964 | 12 - EM agency and authority | That the position of Regional Manager Rural Operations be re-designated to Regional Co-ordinator in the North, Central and South-East regions to emphasise the supporting role the position will take. |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-0986 | 12 - EM agency and authority | That the founding principle of the Rural Fire Service, that Brigades are formed on the principle of neighbour helping neighbour to collectively manage fire events, remains on of the foundation of Rural Fire Service Queensland. |
REC241-1007 | 12 - EM agency and authority | That the Rural Fire Service Queensland consider a less formal uniform which volunteers can better identify with, and that National rank markings be retained. |
REC241-0958 | 12 - EM agency and authority | That the Rural Operations division currently sitting within the Queensland Fire and Rescue Service become an autonomous unit called Rural Fire Service Queensland and be led by a Deputy Chief Officer. Structure and Leadership of the Rural Fire Service |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-1020 | 12 - EM agency and authority | That members of Village and Izone classified Brigades only be required to conduct a criminal history check when they first join a Brigade. Criminal history checks will no longer be required when a Member who has already undergone a criminal history check takes an office bearing role within a Brigade or changes Brigades. Criminal history checks are to still be conducted on Rural Fire Service volunteers undertaking interstate deployments. Members of other voluntary organisations in Queensland (e.g. State Emergency Service, Volunteer Marine Rescue) who wish to join the Rural Fire Service Queensland will not be required to undertake an additional criminal history check with an internal check to be conducted by the Department of Community Safety. |
REC241-0963 | 12 - EM agency and authority | That there be three (3) RFSQ regions in Queensland - North, Central and South-East. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-0975 | 12 - EM agency and authority | That employee selection panels for field staff positions only comprise three members and include a Rural Fire Service Queensland representative, a Rural Fire Brigades Association of Queensland representative and one representative from the District Fire Management Group. |
REC241-1006 | 12 - EM agency and authority | That Brigades’ financial contributions to groups must be voluntary and approved by a recorded minute at a meeting of that brigade. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0677 | 1 - Land-use and building regs | Authorities responsible for the management of sewerage infrastructure should conduct a review of their existing infrastructure to identify electrical infrastructure that may be vulnerable to inundation and perform risk and cost/benefit assessments to determine if it should be relocated to a higher level. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0628 | 1 - Land-use and building regs | The Queensland Government should draft model flood planning controls, using a similar format and structure to that in the Queensland Planning Provisions, that councils can adapt for local conditions. The Queensland Government should require these controls to be reflected in new planning schemes. This may be achieved by including the controls in either: • a state planning policy dealing with flood, with an accompanying amendment to the Sustainable Planning Act 2009, or • the Queensland Planning Provisions. The Queensland Government should consult councils to determine which of the two state planning instruments is the more appropriate to include the model flood planning controls. |
REC210-0649 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters. |
REC210-0691 | 1 - Land-use and building regs | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0612 | 1 - Land-use and building regs | For non-urban areas or areas where limited development is expected to occur councils should consider, on a risk basis, what level of information about flood risk is required for the area, and undertake the highest ranked of the following options which is appropriate to that need and within the capacities (financial and technical) of the council: a. a map showing ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. a map showing the extent of floods of a range of likelihoods (at least three) c. a flood map based on historic flood levels that have been subjected to a flood frequency analysis to estimate the annual exceedance probability of the selected historical flood d. a historic flood map without flood frequency analysis e. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay as a way to determine those areas for which further flood studies are required, or f. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay (preferably refined using local flood information) as a trigger for development assessment. |
REC210-0635 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to expressly provide either a power to remake or a power to extend a temporary local planning instrument containing interim flood regulation for a further limited period. The power to remake or extend should: a. permit the modification of the temporary local planning instrument to the extent required to ensure its provisions remain relevant, having regard to any requirement that may have been introduced or any information that may have become available while the original temporary local planning instrument was in force b. be contingent on the Minister’s being satisfied that the circumstances listed in section 105 of the Sustainable Planning Act continue to exist and that there are proper grounds for the failure to make a permanent scheme amendment while the original temporary local planning instrument was in force. |
REC210-0658 | 1 - Land-use and building regs | The Queensland Government should consult with councils to determine an effective method for the regulation of the construction of levees in Queensland. In particular, the Queensland Government should consider: • requiring a development permit for the construction of a levee by designating levees as assessable development in the Sustainable Planning Regulation 2009, or • requiring, by way of a state planning policy or mandatory provision in the Queensland Planning Provisions, that councils nominate the construction of a levee as assessable development in their planning schemes. |
REC210-0697 | 1 - Land-use and building regs | Queensland Rail and QR National should continue to investigate opportunities for increasing the flood resilience of their networks, including raising the height of critical equipment. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0622 | 1 - Land-use and building regs | If, as part of a state interest review process, the Department of Local Government and Planning decides that no condition should be imposed requiring a council’s proposed planning scheme to incorporate the effect of the Department of Community Safety’s comments about State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide, it should advise the Department of Community Safety of the reasons for its decision. |
REC210-0640 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0666 | 1 - Land-use and building regs | The Queensland Government should draft a model planning scheme policy to be included in the model flood planning controls that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0676 | 1 - Land-use and building regs | Authorities responsible for the construction of sewerage infrastructure should, when embarking on new works, undertake risk and cost/benefit assessments to determine the level at which electrical infrastructure that may be vulnerable to inundation should be placed. |
REC210-0627 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to require that consideration be given to the risk of flooding in the preparation or revision of a regional plan. |
REC210-0647 | 1 - Land-use and building regs | The Department of Environment and Resource Management should ensure that, when applications for a material change of use for an environmentally relevant activity are approved by the department, the details of those activities, including their nature and location, are provided to the council within whose area the activity will be conducted. |
REC210-0690 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0611 | 1 - Land-use and building regs | For urban areas or areas where development is expected to occur: a. councils with the requisite resources should develop a flood map which shows ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. councils without the requisite resources to produce a flood behaviour map should develop a flood map which shows the extent of floods of a range of likelihoods (at least three). |
REC210-0634 | 1 - Land-use and building regs | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include in their planning schemes a planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as a part of the development application, or • for development proposed on land where potential for flooding is unknown requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information to allow an assessment of the flood risk. |
REC210-0657 | 1 - Land-use and building regs | Levees should be regulated. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0621 | 1 - Land-use and building regs | The Queensland Government should: a. narrow the definition of ‘development commitment’ in State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide to ensure more development applications are assessed for compatibility with flood, and b. investigate whether the compensation provisions of the Sustainable Planning Act 2009 act as a deterrent to the inclusion of flood controls in a planning scheme and consider whether they ought be amended. |
REC210-0639 | 1 - Land-use and building regs | The Queensland Government should consider extending the application of a state planning policy dealing with flood to the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood. |
REC210-0662 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0675 | 1 - Land-use and building regs | The Queensland Government should consider including in the criteria in the Queensland Plumbing and Wastewater Code a requirement that the risk of leakage from private on-site sewerage systems during floods be minimised. |
REC210-0626 | 1 - Land-use and building regs | Councils should consider using the limited development (constrained land) zone in their planning schemes for areas that have a very high flood risk. |
REC210-0646 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend the template assessment report used to assess applications for a material change of use for environmentally relevant activities so that it prompts departmental officers to give specific consideration, as part of the assessment process, to the risk of flooding at the site where the activity is proposed to occur. |
REC210-0685 | 1 - Land-use and building regs | In assessing and determining development applications for material change of use in areas susceptible to flood, councils should consider whether the new developments locate essential services infrastructure above basement level, or, alternatively, whether essential services infrastructure located at basement level can be constructed so that it can continue to function during a flood. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0633 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as part of the development application, or • for development proposed on land where the potential for flooding is unknown, requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information, to allow an assessment of the flood risk. |
REC210-0656 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Regulation 2009 so that operational work or plumbing or drainage work (including maintenance and repair work) carried out by or on behalf of a public sector entity authorised under a state law to carry out the work is not exempt development under the Sustainable Planning Act 2009 if the development has the potential to reduce floodplain storage. |
REC210-0694 | 1 - Land-use and building regs | The Queensland Government should consider whether there should be a legislative requirement that customer dedicated assets be built at or above the applicable defined flood level and if so, the Queensland Government should consider which legislation should contain such a requirement. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0617 | 1 - Land-use and building regs | The Queensland Government should consider implementing a mechanism by which prospective purchasers of property are alerted to the issue of flood risk. To that end, the Queensland Government should consider consulting the Real Estate Institute of Queensland and the Law Society of Queensland as to the appropriateness of amending standard contract conditions so as to include a ‘subject to flood search’ condition, or other means of achieving the same objective. |
REC210-0638 | 1 - Land-use and building regs | The Coordinator-General should amend the guideline for preparing an ‘initial advice statement’ for a significant project under the State Development and Public Works Organisation Act 1971 so that it specifically requires an applicant to consider and provide information about the project’s flood risk. |
REC210-0661 | 1 - Land-use and building regs | There should be a common set of considerations in the decision whether to approve an application to build a levee, including: • the impacts of the proposed levee on the catchment as a whole • the benefits of the proposed levee to the individual or entity applying to build the levee and to any nearby community as a whole • any adverse impacts on other landholders, including the risk of levee failure • the implications of the proposed levee for land planning and emergency management procedures • whether any structural, land planning or emergency management measures can be taken to mitigate the adverse impacts of the proposed levee. |
REC210-0674 | 1 - Land-use and building regs | The Queensland Government should consider amending the ‘Limitation’ section of the proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, to allow for the possible application of ‘acceptable solution A1’ to a building located on a lot if: • it is reasonable to expect the part of the lot on which the building work is proposed to be subjected to a maximum velocity of less than 1.5 metres per second, or • the part of the lot on which the building work is proposed is located in an inactive flow or backwater area. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0625 | 1 - Land-use and building regs | The Queensland Government should change Temporary State Planning Policy 2/11: Planning for stronger more resilient floodplains to remove the possibility of councils’ using the interim floodplain assessment overlay mapping and Model Code as part of a permanent amendment to their existing planning scheme or as part of a new planning scheme. |
REC210-0645 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend its information sheet about applications for a material change of use for environmentally relevant activities so that applicants are prompted to include information (if any) about the risk of flooding at the site where the activity is proposed to occur. |
REC210-0684 | 1 - Land-use and building regs | Councils should consider amending their planning schemes to include provisions directed to consideration of the flood resilience of basements as a factor in determining the appropriateness of a material change of use. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0631 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0654 | 1 - Land-use and building regs | The Queensland Government should consider drafting assessment criteria to be included in the model flood planning controls which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the applicable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms) • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0616 | 1 - Land-use and building regs | Councils that do not currently do so should consider offering an online database which allows the public to conduct a search on a parcel of land to find development approvals relevant to that parcel of land. |
REC210-0637 | 1 - Land-use and building regs | The Queensland Government should consider amending the Urban Land Development Authority Act 2007, the South Bank Corporation Act 1989, the State Development and Public Works Organisation Act 1971 insofar as it governs state development areas, and other legislation which establishes alternative planning systems that operate independently of the Sustainable Planning Act 2009, to require that: • any planning scheme, interim or otherwise, appropriately reflects any state planning policy with respect to flood • flood risk be considered in the assessment of any development application. |
REC210-0660 | 1 - Land-use and building regs | There should be a consistent process for the determination of applications to build levees. That process should include: • consulting landholders who may be affected by the proposed levee • obtaining or commissioning appropriate hydrological and hydraulic studies to assess the impacts of the proposed levee. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0624 | 1 - Land-use and building regs | The Queensland Government should ensure that the circumstances in which the Department of Community Safety is to consult the Department of Environment and Resource Management about a planning scheme’s flood modelling and flood mapping are clear. |
REC210-0644 | 1 - Land-use and building regs | The Queensland Government should ensure that the criteria under the Environmental Protection Act 1994 that apply to the assessment of development applications for material change of use for environmentally relevant activities include consideration of the risk of flooding at the site on which the activity is proposed to occur. |
REC210-0673 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirements about utilities and sanitary drains (Performance Requirement P2 and P3) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot. |
REC210-0682 | 1 - Land-use and building regs | The Department of Environment and Resource Management should review the Queensland Urban Drainage Manual to determine whether it requires updating or improvement, in particular, to reflect the current law and to take into account insights gained from the 2010/2011 floods. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0629 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a requirement that councils have a flood overlay map in their planning schemes. The map should identify the areas of the council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0652 | 1 - Land-use and building regs | The Queensland Government should review the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003 to consider whether the design and construction standards should be made more stringent than the existing standards. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0613 | 1 - Land-use and building regs | Councils should ensure that areas for which there has been no assessment of the likelihood of flooding are indicated on a map and that, as part of the development assessment process for these, there is at least some enquiry into whether a site proposed for development could be subject to flooding. |
REC210-0636 | 1 - Land-use and building regs | The Queensland Government should consider allowing councils to amend a planning scheme to update existing flood mapping information by way of the minor amendment process, provided that adequate public consultation has occurred. |
REC210-0659 | 1 - Land-use and building regs | The Queensland Government should consult with councils to formulate a definition of ‘levee’ to identify what should be regulated. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0623 | 1 - Land-use and building regs | The Department of Community Safety should put in place administrative arrangements which ensure it can readily ascertain whether its comments are being reflected in council planning schemes. If the Department of Community Safety becomes aware that its comments are not being adequately addressed, it should take steps to follow this up with the Department of Local Government and Planning. |
REC210-0642 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require the impact of flood on commercial property to be minimised. |
REC210-0672 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirement relating to building design and construction (Performance Requirement P1) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot, and • either: – declared a velocity to be the expected maximum velocity of flood water for the area in which the lot is located, or – designated the area in which the lot is located an inactive flow or backwater area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0269 | 12 - EM agency and authority | that QFRS implement procedures to provide a clear grievance process which is available to rural fire brigade volunteers. |
REC191-0264 | 12 - EM agency and authority | that QFRS update its website to include the Rural Fire Service as part of its www.fire.qld.gov.au web presence. |
REC191-0263 | 12 - EM agency and authority | that QFRS investigate and implement an internal email system for rural fire brigades. |
REC191-0272 | 12 - EM agency and authority | that QFRS establish the position of Assistant Commissioner, Rural Fire Service to lead the proposed Rural Fire Service division within QFRS. |
REC191-0262 | 12 - EM agency and authority | that QFRS include consultation with rural fire brigades as mandatory when boundary changes are proposed. |
REC191-0271 | 12 - EM agency and authority | that QFRS should establish a Rural Fire Service division within QFRS with the aim of integrating and strengthening the relationship between the urban and rural fire services. |
REC191-0270 | 12 - EM agency and authority | that QFRS implement procedures to ensure that rural fire brigades receive written confirmation of the Commissioner’s approval after office bearer elections in compliance with section 81 of the Fire and Rescue Service Act 1990. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1800 | 12 - EM agency and authority | That the South Australian Country Fire Service utilise wherever possible the skills of paid, professional staff to perform the roles of Incident Controller and/or Planning Officer in Level 2 Incident Management Teams. |
REC153-1783 | 12 - EM agency and authority | That South Australian Country Fire Service create and develop the role of a Regional Public Warnings Officer as a member of the paid staff of the SACFS whose role it would be to identify the need for, and to deliver, timely bushfire warnings to the public during the course of a bushfire incident. |
REC153-1779 | 4 - Fire season preparation | That the South Australian Farmers’ Federation encourage its members and constituents to keep and maintain on rural land in proper working order machinery that is capable of removing, modifying or reducing cropping stubble at short notice in order to minimise or mitigate bushfire risk. |
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
REC153-1802 | 12 - EM agency and authority | That the South Australian Country Fire Service create as part of a Level 2 and 3 Incident Management Team Logistics Division an Officer whose function it is to seek out, locate and identify sources of water, be they on land or provided by carrier. |
REC153-1801 | 12 - EM agency and authority | That the South Australian Country Fire Service identify and impart minimum skills and competencies to members who fulfil the roles of the four core AIIMS functionaries of a Level 2 Incident Management Team. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3121 | 12 - EM agency and authority | QFRS utilise performance information on brigade activity as a factor in determining brigade resource and funding needs. |
REC150-3114 | 12 - EM agency and authority | QFRS implement a process to review brigade plans and incorporate specific issues identified into forward planning at the area and regional levels. |
REC150-3120 | 12 - EM agency and authority | QFRS provide assistance to brigades in determining and budgeting for their resource needs. |
REC150-3113 | 12 - EM agency and authority | QFRS provide guidance and support to rural fire brigades in the development of their one year operational plan and three year management plan. |
REC150-3119 | 12 - EM agency and authority | QFRS implement a system to collate and analyse brigade funding information. |
REC150-3112 | 12 - EM agency and authority | Queensland Fire and Rescue Service (QFRS) implement a forward planning process specific to rural fire management as part of the QFRS strategic planning process, which involves regional and area offices and incorporates: |
REC150-3118 | 12 - EM agency and authority | QFRS review the financial accountability and audit requirements of the rural fire brigades to reflect their status as part of QFRS. |
REC150-3124 | 12 - EM agency and authority | QFRS establish a suitable process to reliably capture that information. |
REC150-3117 | 12 - EM agency and authority | QFRS ensure compliance with the brigade accountability requirements for funding received by rural fire brigades as specified in the Rural Fire Brigade Manual |
REC150-3123 | 12 - EM agency and authority | QFRS determine the performance information needed to support effective decision making . |
REC150-3116 | 12 - EM agency and authority | QFRS implement a brigade issues management process to capture, manage and report specific brigade issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
REC122-3777 | 1 - Land-use and building regs | The Committee recommends that native vegetation, excluding road reserves be fenced. |
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |