Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3271 | 8 - Communications and warnings | Better coordinate public information and warnings including evacuation plans and provide a single source of information about, the location and direction of fires, how and when to use Safer Places, Places of Last Resort, relief and recovery centres and directed evacuations. |
REC314-3267 | 16 - Training and behaviour | Invest in fireground leadership and incident management training for CFS, SES and MFS personnel to improve safety on the fireground. Invest in greater technological interoperability such as AVL, Thermal Imagery, Burnover Protection Systems (BOPS), lightning tracking and appropriate vehicle fleets for bushfire conditions including at the peri-urban interface. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2404 | 8 - Communications and warnings | Review the effectiveness of emergency public information arrangements, and give consideration to embedding an ABC Manager (not a journalist) into the RFS headquarters during emergencies to broadcast warnings to the community that can be pooled to commercial media outlets |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1243 | 8 - Communications and warnings | The Department of Fire and Emergency Services to investigate and adopt a system that will allow the public to opt in, monitor and receive, through a ‘push mechanism’, bushfire and other emergency warnings, maps and information using a wide variety of devices including personal hand held smart devices. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1190 | 16 - Training and behaviour | That a full review be undertaken of the benefts and costs of training a cadre of Tasmanian volunteer firefghters in remote area firefghting, with reference to the experience of jurisdictions interstate that already do so. |
REC287-1189 | 16 - Training and behaviour | That suffcient Tasmanian firefghters are trained in winch operations to sustain a ‘first strike’ capability until they can be reinforced (if necessary) by interstate capability; and that consideration be given to how winch-capable aircraft can be sourced to support this activity at fire incidents. |
REC287-1187 | 16 - Training and behaviour | All Tasmanian fire agency staff who are assigned to aviation-related roles be required to complete the formal nationally recognised training appropriate to that role. Tasmanian fire agencies arrange secondments to larger states for staff who are going to undertake aviation-related roles, to give them practical experience of the role in advance of any major incidents. |
REC287-1183 | 16 - Training and behaviour | Further conversations take place between TFS and SES to identify what skills and capabilities may be transferable between the agencies, not just in the event of a future fire, but in case of future hazards for which SES is the primary response agency, including food, earthquake and tsunami. |
REC287-1181 | 16 - Training and behaviour | The Tasmanian fire agencies develop a multi-agency position to ensure that training for incident controllers includes training in how the transition from local incident control to Divisional Command is managed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1140 | 8 - Communications and warnings | Review the current practise of issuing an ‘emergency alert’ telephone message or an emergency warning and/or watch and act alert to ensure that it is consistent, relevant and necessary. Prior to issuing an emergency alert message, consider state level involvement so that other agencies are made aware of message and intent. |
REC273-1134 | 8 - Communications and warnings | That future declarations be undertaken to ensure that the areas affected by the declaration are clear and concise. |
REC273-1144 | 7 - Inter-agency communication | That SACFS consider a review to develop an effective interagency messaging system and agency resource management system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1076 | 13 - Mapping and data quality | The State equip itself to undertake rapid air quality monitoring in any location in Victoria, to: • collect all relevant data, including data on PM , carbon monoxide and ozone; and 2.5 • ensure this data is used to inform decision-making within 24 hours of the incident occurring. |
REC264-1089 | 8 - Communications and warnings | GDF Suez improve its crisis management communication strategy for the Hazelwood mine in line with international best practice. |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1082 | 8 - Communications and warnings | The State review and revise its communication strategy, to: • needed for effective and rapid public communications during an emergency; and ensure all emergency response agencies have, or have access to, the capability and resources • ensure, where appropriate, that private operators of essential infrastructure are included in the coordination of public communications during an emergency concerning that infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1057 | 16 - Training and behaviour | That the Rural Fire Service and National Parks and Wildlife Service introduce training, exercises or information packages, or other suitable forms of professional development, for operational fire fighters and analysts concerning the potential effects of atmospheric instability and vorticity-driven lateral spread on fire behaviours in severe-catastrophic fire danger conditions. |
REC260-1051 | 8 - Communications and warnings | That the Rural Fire Service consider redrafting the disclaimer in its fire predictions to make abundantly clear where the potential errors or omissions may affect the prediction and how to detect them if they are there (for example, by comparing them with linescans) and what other factors (such as VLS) may affect the predictions and in what way. |
REC260-1068 | 16 - Training and behaviour | That the National Park and Wildlife Service review its fire weather training regime and consider adopting or adapting the fire weather training courses introduced in Victoria following the 2009 bushfire disaster. |
REC260-1050 | 13 - Mapping and data quality | Alternatively, I recommend that the RFS consider developing such capacity to deploy weather balloons itself, in conjunction with mobile weather stations, for this purpose. |
REC260-1062 | 16 - Training and behaviour | That the National Parks and Wildlife Service consider incorporating “worst-case scenario” training, as proposed in Mr Conway’s report, in its suite of fire-fighting protocols, exercises and training packages for senior incident controllers and other senior managers. |
REC260-1049 | 13 - Mapping and data quality | That the Rural Fire Service consider proposing an arrangement with the Bureau of Meteorology to deploy weather balloons specifically for the purpose of assessing atmospheric instability during periods of severe to catastrophic fire danger in locations most likely to be severely affected, for example, areas in which a very high C-Haines index reading is registered and local fires have been identified. |
REC260-1060 | 7 - Inter-agency communication | That the Rural Fire Service and National Parks and Wildlife Service review the procedures for requesting aerial support in ‘severe’ or worse fire conditions to ensure that delays in providing it are reduced to the minimum time possible. |
REC260-1059 | 8 - Communications and warnings | That the Rural Fire Service and National Parks and Wildlife Service consider amending their protocols for upgrading advices to higher levels to emphasise the significance and urgency of raising warning levels as soon as the potential dangers of fire to lives or property materially increase. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1540 | 16 - Training and behaviour | Commanding Officer Defence Explosive Ordnance Training School, assisted by Joint Logistics Command Regional Explosive Ordnance Serices staff, conduct explosive ordnance accounting training for all instructional staff as a matter of priority and that such training be conducted for Defence Explosive Ordnance Training School staff on an annual basis. |
REC257-1536 | 16 - Training and behaviour | The Australian defence Force Explosive Ordnance Disposal course be reviewed by Manager Joint Training - Air Force, to ensure the assessments meet the learning outcomes specificed in the relevant Training Management Package. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0902 | 7 - Inter-agency communication | That evacuation centres and other centres have a standard operating procedure for communications. |
REC247-0917 | 8 - Communications and warnings | That the State Emergency Management Committee makes timely decisions and resource commitments on the appropriate use of social media in emergency management. |
REC247-0924 | 16 - Training and behaviour | That an exercise program — to establish and maintain an acceptable state of readiness for agencies and organisations required to be involved in emergency operations — be developed and implemented. |
REC247-0858 | 7 - Inter-agency communication | That all agencies and the Government support moving to an integrated communications technology for police and the emergency services. |
REC247-0900 | 8 - Communications and warnings | That a public information plan be developed as a part of the State Special Emergency Plan–Recovery, for implementation in the immediate recovery phase. |
REC247-0916 | 8 - Communications and warnings | That Tasmania Fire Service ensures that the priority on warning communities at risk of active bushfires is not confined to when bushfires are burning out of control. |
REC247-0922 | 8 - Communications and warnings | That Tasmania Fire Service develops a research base from which to inform the design of communication campaigns for communities threatened by bushfire. |
REC247-0851 | 13 - Mapping and data quality | That if a sound business case is developed, the Emergency Information Management and Sharing Project be supported. |
REC247-0868 | 16 - Training and behaviour | That Tasmania Fire Service, Forestry Tasmania, and Parks and Wildlife Service have a process for ensuring fire strategy and tactics are appropriate and remain focussed. |
REC247-0915 | 8 - Communications and warnings | That Tasmania Fire Service actively uses predictive modelling to design emergency communications for communities threatened by bushfire, unless there is a compelling reason for not doing so. |
REC247-0920 | 8 - Communications and warnings | That Tasmania Fire Service reviews its approach to communicating with communities threatened by bushfire and consider the matters referred to in this Report. |
REC247-0850 | 13 - Mapping and data quality | That police and other emergency service agencies establish and maintain effective recording systems for emergency operations. |
REC247-0867 | 7 - Inter-agency communication | That Tasmania Fire Service reviews the communication systems used for all emergency management operations, ensures operators are qualified, and ensures there is appropriate accountability. |
REC247-0905 | 8 - Communications and warnings | That the Government consider whether it should discuss options for greater mobile phone coverage and redundancy in areas of high risk in emergency situations where there are presently telecommunications limits. |
REC247-0919 | 8 - Communications and warnings | That Tasmania Fire Service and Tasmania Police review their use of modern forms of communication with the community, including social media, and commit resources to fully use this capability where appropriate. |
REC247-0936 | 16 - Training and behaviour | That the State Fire Management Committee note the decline in machinery and skilled operators from the forestry industry in the private sector and determines how this reduction in fire management capability can be addressed. |
REC247-0860 | 13 - Mapping and data quality | That Tasmania Fire Service establishes suitable systems and practices for recording fire management objectives and tactics. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0918 | 8 - Communications and warnings | That the State Emergency Management Committee makes arrangements to actively manage the use of social media in the community during an emergency, to avoid negative consequences for emergency operations. |
REC247-0925 | 16 - Training and behaviour | That training and development of personnel to establish a suitable state of readiness, be included in the recommended review by Tasmania Police of its approach to emergency management. |
REC247-0859 | 7 - Inter-agency communication | That police and other emergency services examine options for achieving radio interoperability between them in the absence of an integrated radio system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0518 | 16 - Training and behaviour | The Department of Environment and Conservation explore human resourcing models that: · make succession planning a priority; · look at options for the attraction and retention of staff; and · review how the salary levels of staff matches the decision making required in major activities such as prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0252 | 7 - Inter-agency communication | FESA must actively manage the transition to WAERN and provide alternative means for regional crews to communicate when in areas where WAERN is not operated. |
REC201-0250 | 8 - Communications and warnings | Initial StateAlert messages should provide timely broad advice to a wide audience authorised by the SDD, while subsequent messages may provide more detail. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1730 | 16 - Training and behaviour | The Fire and Emergency Services Authority and local governments examine the current competencies of Chief Bushfire Control Officers and Community Emergency Services Managers (or Community Fire Managers) and consider what further development is needed to ensure these staff are capable of: |
REC200-0390 | 16 - Training and behaviour | The Fire and Emergency Services Authority and local governments examine the current competencies of Chief Bushfire Control Officers and Community Emergency Services Managers (or Community Fire Managers) and consider what further development is needed to ensure these staff are capable of: measuring and mapping fuel loads maintaining fuel load databases drawing up prescriptions for, and overseeing controlled burns building effective working relationships with all relevant stakeholders. |
REC200-1689 | 8 - Communications and warnings | The Fire and Emergency Services Authority consider alternative wording to Total Fire Ban that ensures people gain a more complete understanding of what actions are prohibited. |
REC200-0355 | 13 - Mapping and data quality | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-1713 | 7 - Inter-agency communication | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-0372 | 7 - Inter-agency communication | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0352 | 13 - Mapping and data quality | The Fire and Emergency Services Authority and local governments ensure that the ability to: measure and map fuel loads maintain fuel load databases draw up prescriptions for, and oversee controlled burns are included as key competencies in any future recruitment of Chief Bushfire Control Officers and Community and Emergency Services Managers. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0371 | 8 - Communications and warnings | FESA develop in partnership with other emergency service agencies a ‘one source: one message’ multi layered system similar to that recommended by the Victoria Bushfire royal Commission. |
REC200-1711 | 8 - Communications and warnings | FESA develop in partnership with other emergency service agencies develop a 'one source: one message' multi layered system similar to that recommended by the Victoria Bushfire royal Commission. |
REC200-0370 | 8 - Communications and warnings | The Fire and Emergency Services Authority and the ABC commence a thorough review of emergency warning messages. This review should give consideration to: The content, structure and presentation of emergency warning messages Media access to the Incident Management Team and State Operations Centre. This review should be expanded to include other media organisations should they demonstrate a willingness and capacity to contribute. 20 |
REC200-1710 | 8 - Communications and warnings | The Fire and Emergency Services Authority and the ABC commence a thorough review of emergency warning messages. This review should give consideration to: |
REC200-0359 | 13 - Mapping and data quality | The State Government ensure that the continued development of the Fire and Emergency Service Authority’s Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1731 | 16 - Training and behaviour | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. |
REC200-1690 | 8 - Communications and warnings | The Fire and Emergency Services Authority work in partnership with Main Roads Western Australia and local governments to develop and implement a comprehensive strategy for the use of mobile variable message boards to alert the community to the declaration of a total fire ban and what it means. |
REC200-0358 | 13 - Mapping and data quality | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. The system should enable public access to allow members of the community to access information about the fuel load in a given locality. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0110 | 16 - Training and behaviour | DEC should emphasise the principle of foresight by adopting an appreciation and decision making process and training staff in that process. |
REC183-0122 | 16 - Training and behaviour | A staff recognition and reward framework for service to fire management should be considered for DEC fire staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0066 | 8 - Communications and warnings | That arrangements be put in place for signage to be retained at Norseman and available at short notice to enable motorists to be warned of potential problems existing on the Great Eastern Highway west of Coolgardie. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1792 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the duties and responsibilities attaching to that position insofar as they apply to an ongoing fire incident, and in particular to recognise the need to conduct a risk assessment in relation to an incident and the need to scrutinise, evaluate and validate the strategies and Incident Action Plans of Incident Management Teams. |
REC153-1797 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1784 | 8 - Communications and warnings | That the South Australian Country Fire Service empower the Regional Public Warnings Officer to create and deliver public warnings on that Officer’s initiative without the necessity of seeking the approval of personnel at State Headquarters. |
REC153-1796 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in risk assessment. |
REC153-1782 | 8 - Communications and warnings | That the Minister for Emergency Services, the Chief Officer of the South Australian Country Fire Service, the Chief Officer of the South Australian State Emergency Services and the Commissioner of Police establish a panel to develop policies and practices to ensure that at the time bushfire warnings are created and delivered, all such warnings are made known to all emergency service entities, and to ensure that warnings of an approaching fire are delivered in a timely manner with detailed and specific information relevant to the circumstances of the section of the public to whom they are directed. |
REC153-1795 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in risk assessment. |
REC153-1781 | 8 - Communications and warnings | That the Minister for Emergency Services in conjunction with the Chief Officer of the South Australian Country Fire Service, the Chief Officer of the South Australian State Emergency Services and the Commissioner of South Australia Police develop policies and practices regarding the issuing of public warnings that address the risk posed to the public by an existing fire incident with a view to disseminating such warnings to the public at a time before the escalation of an existing fire incident occurs. |
REC153-1794 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of all Incident Management Team members, in particular but not limited to the Incident Controller and Planning Officer, of the need to conduct a full risk assessment that not only addresses operational risk, but the risk posed to the general public by an existing incident and at all times to consider and identify the ‘worst case scenario’ outcome. |
REC153-1793 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the need to deliver to the Deputy State Coordinator timely, accurate and relevant information pertaining to an ongoing fire incident. |
REC153-1798 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3594 | 8 - Communications and warnings | Need for scripting of messages by fire agency representatives when promoting VBIL services via radio, TV and newspapers. |
REC132-3590 | 8 - Communications and warnings | Investigate procedures for updating the Victoria Bushfire Information Line (VBIL) Integrated Voice Response recorded message system to allow recording of permanent bushfire safety, and incident-specific, messages, accessible when the VBIL is experiencing high call volumes during large and/or numerous significant incidents |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1961 | 7 - Inter-agency communication | That the Emergency Services Agency review the communications systems used by the four services (the ACT Ambulance Service, the ACT Rural Fire Service, the ACT State Emergency Service and the ACT Fire Brigade), by the Australian Federal Police, by NSW emergency services and by aircraft and ensure the systems are compatible |
REC126-1983 | 16 - Training and behaviour | That the Australian Federal Police and the Emergency Services Agency ensure that personnel in their respective organisations are fully briefed on the agreed policy on evacuations |
REC126-1960 | 13 - Mapping and data quality | That an appropriate geographic information systems capability be maintained to enable the production of fire-specific maps as the need arises and that personnel from the Emergency Services Agency and other agencies be trained in the operation of map production systems, so that 9maps can be modified to include fire-specific information as required |
REC126-1982 | 8 - Communications and warnings | That the Australian Federal Police and the Emergency Services Agency agree on a policy on community safety and evacuation during bushfires, based on the Australasian Fire Authorities Council position outlined in its paper Community Safety and Evacuation during Bushfires. Community education programs should incorporate advice on this, including the ‘stay or go’ policy |
REC126-1998 | 8 - Communications and warnings | That a system of public warnings that uses grid references shown on the maps in the Canberra telephone directory be adopted |
REC126-1959 | 13 - Mapping and data quality | That the Emergency Services Agency introduce a program with land management agencies in the ACT to ensure that maps of all public and private land in the ACT are subjected to regular review and amendment as required. Maps of a scale sufficient to facilitate fire management operations should be available in printed form and maintained on an electronic database capable of modification to add relevant features during a firefighting operation |
REC126-1980 | 16 - Training and behaviour | That public land management agencies ensure that their senior personnel have appropriate experience in fire management and are provided with adequate resources and suitable experienced and trained staff to effectively implement fire management programs |
REC126-1997 | 8 - Communications and warnings | That the Emergency Services Agency conduct investigations - and liase with emergency services agencies in other jurisdicions - in order to ascertain what technologies exist and are effective for use in disseminating warnings and associated information to the community of the ACT |
REC126-1957 | 16 - Training and behaviour | That the Emergency Services Agency review the level of understanding among firefighting personnel of the latest information available nationally and internationally about wildfire behaviour and suppression and provide additional training if warranted |
REC126-1969 | 16 - Training and behaviour | That a review be conducted of the adequacy of training and the numbers of firefighters experienced in performing effective, safe large-scale back-burning operations |
REC126-1994 | 8 - Communications and warnings | That the Emergnecy Services Agency publicise and demonstrate the use of the Standard Emergency Warning Signal and provide to the community adequate explanation of the application of the signal. This should occur at least annually, in conjunction with any pre-summer fire awareness initiatives |
REC126-1955 | 16 - Training and behaviour | That training of all personnel involved with emergency services be under constant review |
REC126-1968 | 16 - Training and behaviour | That land managers ensure their staff are properly trained in the effective use of large bulldozers at wildfires and that staff are available to be assigned to supervise bulldozer operations |
REC126-1987 | 7 - Inter-agency communication | That measures be taken to ensure that ACT and NSW Rural Fire Service radio communications systems are integrated, so that ACT and NSW firefighting units can communicate with each other |