Rec-ID | Code | Recommendation |
---|---|---|
REC322-4227 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the membership of the K’gari Locality Specific Fire Management Group be expanded to include representatives of the Butchulla people, community associations from each township and tourism and business operators with interests on the island. |
REC322-4250 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the Locality Specific Fire Management Group for K’gari meet at least twice per year, in person or virtually. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4228 | 8 - Communications and warnings | The Inspector-General Emergency Management recommends a public information resource be developed by Queensland Fire and Emergency Services to inform the community and stakeholders about aerial assets utilised in bushfire response. |
REC322-4251 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services facilitate an annual state level exercise of the Queensland Bushfire Plan that includes all relevant stakeholders and land managers. The exercise should focus on roles, responsibilities, interagency arrangements and handover arrangements between agencies and land managers. |
REC322-4242 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends the Department of Environment and Science review the format and delivery of Queensland Parks and Wildlife Service annual fire refresher training to include a scenario-based exercise. |
REC322-4229 | 16 - Training and behaviour | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services identifies stakeholders that would benefit from predictive service products. Suitable advice and training should be provided to these stakeholders to assist with using and interpreting the products. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4230 | 34 - Local knowledge | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services engages with land managers and other stakeholders on K’gari to source data to inform Predictive Services products. |
REC322-4244 | 16 - Training and behaviour | The Inspector-General Emergency Management recommends the Department of Environment and Science review its training framework and minimum mandatory training requirements for Queensland Parks and Wildlife Service Incident Controllers to ensure they are appropriately trained to manage significant events. |
REC322-4231 | 8 - Communications and warnings | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services examines the use of predictive service capability to inform prevention and preparedness in addition to response activities. |
REC322-4225 | 8 - Communications and warnings | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to prepare and exercise a communications sub-plan with all responsible agencies, to clarify the roles, responsibilities and communication channels used for restricting access to K’gari. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3266 | 14 - Incident Mgt Teams | Engage with the Australian Defence Force (ADF) once or twice a year to understand the capabilities that could potentially be deployed. Educate IMTs about how to deploy ADF assistance effectively and develop a streamlined ‘call out’ procedure. |
REC314-3265 | 14 - Incident Mgt Teams | Prepare to ‘scale up’ capability during major bushfire events with senior representatives (including BoM staff) in the SEC 24/7, ensure adequate facilities for IMTs, base camps (e.g. Humanihuts) and recovery centres. Consider the resource implications of providing firefighters to interstate operations. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3271 | 8 - Communications and warnings | Better coordinate public information and warnings including evacuation plans and provide a single source of information about, the location and direction of fires, how and when to use Safer Places, Places of Last Resort, relief and recovery centres and directed evacuations. |
REC314-3267 | 16 - Training and behaviour | Invest in fireground leadership and incident management training for CFS, SES and MFS personnel to improve safety on the fireground. Invest in greater technological interoperability such as AVL, Thermal Imagery, Burnover Protection Systems (BOPS), lightning tracking and appropriate vehicle fleets for bushfire conditions including at the peri-urban interface. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2474 | 16 - Training and behaviour | The provision of system-wide tools, education, guidance and testing for requests for assistance is strengthened to enhance understanding and outcomes. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2466 | 41 - Emergency Management exercises | Exercising should focus on vertical integration and include all levels of the system. A strategic program of exercises should be developed and implemented. |
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2464 | 16 - Training and behaviour | The provision of system-wide education, guidance and testing to enhance requests for Assistance is strengthened. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2435 | 16 - Training and behaviour | Building capacity in fire simulation and predictive capabilities, including the capability of people to read and interpret these products through training, should be investigated and considered. |
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
REC307-2445 | 16 - Training and behaviour | All agencies should identify the capacity and appropriate positions for the role of liaison officers, and ensure sufficient numbers are trained. |
REC307-2444 | 41 - Emergency Management exercises | All disaster management groups should run an exercise that has full involvement of a hazard-specific primary agency in the next 12 months and regularly thereafter. |
REC307-2440 | 8 - Communications and warnings | Communications protocols about hazard-specific events should be developed to clarify responsibilities and the principles for the release of information and warnings. They should be included in all related hazard-specific plans and published on relevant websites, and used during events. |
REC307-2438 | 8 - Communications and warnings | The national messages for catastrophic fire danger ratings should be integrated with all existing and new community bushfire safety information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1138 | 14 - Incident Mgt Teams | Review the communication and request procedures within SACFS to ensure that the most effective chain of command and line of communications are established between the Incident Management Team, region and state. |
REC273-1135 | 14 - Incident Mgt Teams | That SACFS conduct a review of SIMT with a view to increasing the number of teams from four to six, aligning them with each of the six regions within SA. |
REC273-1144 | 7 - Inter-agency communication | That SACFS consider a review to develop an effective interagency messaging system and agency resource management system. |
REC273-1134 | 8 - Communications and warnings | That future declarations be undertaken to ensure that the areas affected by the declaration are clear and concise. |
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
REC273-1132 | 15 - Inter-service cooperation | Noting the implementation of Common Incident Command and Control System (CICCS) in SA that fire and emergency services together with police (including through AFAC and ANZPAA), continue to liaise regarding the development of a national incident management. |
REC273-1140 | 8 - Communications and warnings | Review the current practise of issuing an ‘emergency alert’ telephone message or an emergency warning and/or watch and act alert to ensure that it is consistent, relevant and necessary. Prior to issuing an emergency alert message, consider state level involvement so that other agencies are made aware of message and intent. |
REC273-1131 | 15 - Inter-service cooperation | That the Emergency Management Australia’s ‘Arrangements for Interstate Assistance (Fire and Emergency Services)’ be applied to all future requests for assistance by the SACFS, SAMFS and SASES. |
REC273-1139 | 14 - Incident Mgt Teams | SACFS appoint the Regional Controller and/or Coordinator as the IC for any Level 3 incident occurring within their Region to provide better continuity and improved coordination. The position of the regional controller and/or coordinator could then be backfilled by a suitably qualified individual as required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1421 | 16 - Training and behaviour | In conjunction with the Queensland Fire and Emergency Services review of guidelines, the Public Safety Business Agency should consider reviewing the cyclone shelter management training package to include guidance to the shelter management team on their roles and responsibilities, and powers available under legislation and how these may be exercised. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0956 | 16 - Training and behaviour | That, wherever possible, combined training take place between volunteers across a wide range of volunteer organisations. |
REC241-1041 | 16 - Training and behaviour | That, as with Recommendation 23 related to Rural Fire employees, all State Emergency Service employees should have a recorded history of volunteering. |
REC241-0977 | 16 - Training and behaviour | That all volunteer training conducted by the Rural Fire Service Queensland will be relevant to employment levels within the Rural Fire Service Queensland. |
REC241-0984 | 16 - Training and behaviour | That Rural Fire Service Queensland work with the State Emergency Service, Surf Life Saving Queensland and other volunteer organisations to develop training programs which can be recognised by all organisations (E.G. chainsaw training, Four-wheel drive training) |
REC241-1022 | 29 - Operational Health and Safety | That Rural Fire Service Queensland in consultation with the Rural Fire Brigades Association Queensland will undertake a full review of the medical and health protocols to support the new Volunteer organisation. |
REC241-0976 | 16 - Training and behaviour | That Rural Fire Service Queensland recognise training and experience in rural fire Brigades as equal to experience gained in other rural fire services when considering candidates for employment. |
REC241-0983 | 16 - Training and behaviour | That the current Primary Producer Brigade manual be withdrawn and a working group comprising Rural Fire Service Queensland staff, Rural Fire Brigade Association of Queensland representatives and Primary Producer Brigade volunteers and as a priority produce a new, simpler and less bureaucratic booklet. |
REC241-1018 | 16 - Training and behaviour | That members of Primary Producer and Rural Classified Brigades will only require a Criminal History Check if they become an office bearer of that Brigade. |
REC241-0974 | 16 - Training and behaviour | That all employees of Rural Fire Service Queensland MUST demonstrate a background in, knowledge or experience of land management and volunteering. |
REC241-0982 | 16 - Training and behaviour | That the requirement for Primary Producer Brigade members to undertake a Firefighter Minimum Skills course be removed and replaced with a ‘Primary Producer Brigade Induction’ course. |
REC241-1015 | 29 - Operational Health and Safety | That the First Officer or Brigade Officer retain the ability to seek assistance from any person whose services are available at the fire. Any person appointed to provide this assistance should be protected under relevant Workplace Health and Safety and Workcover legislation. |
REC241-0969 | 16 - Training and behaviour | That a mobile training program be established for areas with identified above average fire risk to train in fire behaviour and Australasian Inter-Service Incident Management System principles across land tenures. |
REC241-0981 | 16 - Training and behaviour | That Rural Fire Service Queensland utilise external Registered Training Organisations for the training of volunteers and other stakeholders. |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
REC241-0965 | 29 - Operational Health and Safety | That the number of Bushfire Safety Officer positions be, over time, increased so that one BSO operates out of each District office. |
REC241-0980 | 16 - Training and behaviour | That Rural Fire Service Queensland to have its own training support coordinators who, in conjunction with external Registered Training Organisations, co-ordinate the training curriculum throughout Queensland. |
REC241-0985 | 16 - Training and behaviour | That the Department of Community Safety review Rural Fire Service Queensland and other volunteer organisation records and consider options to simplify recognition of training records and competencies, criminal history checks, equipment capacities and other background information for volunteers who belong to more than one volunteer organisation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1782 | 8 - Communications and warnings | That the Minister for Emergency Services, the Chief Officer of the South Australian Country Fire Service, the Chief Officer of the South Australian State Emergency Services and the Commissioner of Police establish a panel to develop policies and practices to ensure that at the time bushfire warnings are created and delivered, all such warnings are made known to all emergency service entities, and to ensure that warnings of an approaching fire are delivered in a timely manner with detailed and specific information relevant to the circumstances of the section of the public to whom they are directed. |
REC153-1794 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of all Incident Management Team members, in particular but not limited to the Incident Controller and Planning Officer, of the need to conduct a full risk assessment that not only addresses operational risk, but the risk posed to the general public by an existing incident and at all times to consider and identify the ‘worst case scenario’ outcome. |
REC153-1799 | 14 - Incident Mgt Teams | That the South Australian Country Fire Service establish preplanned Level 2 Incident Management Teams in each Region for deployment to Level 2 incidents. |
REC153-1781 | 8 - Communications and warnings | That the Minister for Emergency Services in conjunction with the Chief Officer of the South Australian Country Fire Service, the Chief Officer of the South Australian State Emergency Services and the Commissioner of South Australia Police develop policies and practices regarding the issuing of public warnings that address the risk posed to the public by an existing fire incident with a view to disseminating such warnings to the public at a time before the escalation of an existing fire incident occurs. |
REC153-1793 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the need to deliver to the Deputy State Coordinator timely, accurate and relevant information pertaining to an ongoing fire incident. |
REC153-1798 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1792 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the duties and responsibilities attaching to that position insofar as they apply to an ongoing fire incident, and in particular to recognise the need to conduct a risk assessment in relation to an incident and the need to scrutinise, evaluate and validate the strategies and Incident Action Plans of Incident Management Teams. |
REC153-1797 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1791 | 14 - Incident Mgt Teams | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service consider the creation of a position within an Incident Management Team of a Landowner Liaison Officer the duties and responsibilities of whom is to establish contact with and liaise with the owner and/or occupiers of rural land on which a fire is situated. |
REC153-1796 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in risk assessment. |
REC153-1784 | 8 - Communications and warnings | That the South Australian Country Fire Service empower the Regional Public Warnings Officer to create and deliver public warnings on that Officer’s initiative without the necessity of seeking the approval of personnel at State Headquarters. |
REC153-1795 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3125 | 38 - Agency/Department Reporting | QFRS introduce a system to collate and analyse performance information for use in management reporting and to support effective decision making processes. |
REC150-3122 | 29 - Operational Health and Safety | QFRS implement a system to monitor the condition and safety of brigade buildings and equipment. |
REC150-3127 | 16 - Training and behaviour | QFRS improve the capacity to address the brigade training gap by continuing to encourage and facilitate the accreditation of volunteer trainers within brigades where appropriate. |
REC150-3126 | 16 - Training and behaviour | QFRS continue to support area training staff in the development and implementation of brigade training programs and calendars. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3791 | 16 - Training and behaviour | The Committee recommends that training be provided to landholders to enable them to assist with prescribed burns. |
REC122-3784 | 34 - Local knowledge | The Committee recommends that the government provide authority to a single community representative body to authorise clearing of native vegetation for fire management. (The community representative body must incorporate the CFS, DEH, Native Vegetation Council and local council) |