Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC325-4328 | 9 - Community education | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services establish a community education program by 1 November 2023 that complements the implementation of the Australian Warning System. An evaluation process should be incorporated into the program to determine effectiveness. |
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4317 | 32 - Doctrine, standards, and reform | Flood rescue capability: That, to help improve the protection of life across NSW in flood events: |
REC324-4302 | 32 - Doctrine, standards, and reform | Disaster adaptation plans for all towns: That, to establish realistic expectations of safe spaces to live and deliver much needed housing quickly, Government through NSWRA working with local government: |
REC324-4306 | 6 - Insurance and legal liability | NSW Reconstruction Authority: That, to provide rapid and effective recovery from floods (and other disasters) and to provide maximum mitigation of the impacts of future floods (and other disasters), Government establish a permanent state-wide agency, the NSW Reconstruction Authority (NSWRA) dedicated to disaster recovery, reconstruction and preparedness. The NSWRA should: |
REC324-4307 | 9 - Community education | Flood education: That, to build disaster resilience in future generations as floods and other natural disasters are a fact of Australian life, the Department of Education should design, implement and deliver an evidence-based, targeted education campaign (like sun exposure) in schools (new disaster curriculum). |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4301 | 32 - Doctrine, standards, and reform | Floodplains as assets: That, to establish the capacity and maximise the economic, social and environmental potential and consequently unlock the value of NSW floodplains, Government adopt the following guiding principles for floodplain management: |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2500 | 9 - Community education | To enable the community to make informed choices about disaster management, Bundaberg and North Burnett regional councils and Sunwater undertake a community-informed audible test of the Paradise Dam siren. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2489 | 9 - Community education | To enable the community to have a shared understanding of risks and enhance community engagement, flood scenarios in Emergency Action Plans be published, and in a format that can be utilised by public mapping systems. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2503 | 9 - Community education | To enable the casual/itinerant worker and tourism sector, including those who do not have English as a first language, to make informed choices about disaster management, community engagement and communication strategies about Paradise Dam and floods in the Burnett river system be tailored to this sector. |
REC311-2502 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, Sunwater develop and deliver a sustainable long-term communication strategy on the community safety issues and |
REC311-2501 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, a joint Sunwater/council community engagement program be conducted to prepare the community downstream from Paradise Dam for events in the 2019/2020 storm and cyclone season, including the possibility of a Paradise Dam failure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1256 | 9 - Community education | That SES and Tasmania Fire Service share resources and align their community education programs and adopt an all-hazards approach to awareness. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1251 | 9 - Community education | That all councils include an easily identifiable website link for the public to locate their Municipal Emergency Management Plan and community safety information. |
REC297-1260 | 32 - Doctrine, standards, and reform | That DPIPWE clarifies responsibility for river restoration and riparian management and, having done so, communicates this to councils, landowners and other owners of relevant infrastructure. |
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2365 | 32 - Doctrine, standards, and reform | I recommend that the Australia New Zealand Policing Advisory Agency and the Australia–New Zealand Counter-Terrorism Committee review the Australia New Zealand Guidelines for Deployment of Police to High Risk Situations and the Police Tactical Group Operations Manual to ensure that they adequately describe all aspects of the DA planning and approval pro-cess and present commanders with appropriate guidance on relevant considerations. |
REC292-2343 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force remedy the lack of detailed guidance on how State Protection Group officers should interact and communicate with the Police Forward Commander, and that such guidance be included in policy documents and reinforced with training. |
REC292-2372 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force review its policies, procedures and training to ensure the rapid identification of persons killed or injured in high-risk situations. Those policies should provide appropriate guidance on how and when death messages ought to be conveyed following such incidents. |
REC292-2353 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force develop a comprehensive policy that describes the role and function of a psychological adviser engaged to assist in responses to high-risk situations and that all those involved be made familiar with that policy. |
REC292-2379 | 24 - Govt responsibility | I recommend that the Premier of New South Wales consider whether the Privacy and Personal Information Protection Act 1998 and the Health Records and Information Privacy Act 2002 should be amended to ensure that there is appropriate access to health related information available to ASIO (consistent with recommendation 12 of the report of the Martin Place Siege Joint Commonwealth—New South Wales review) |
REC292-2364 | 32 - Doctrine, standards, and reform | I recommend that the Australia New Zealand Policing Advisory Agency and the Australia–New Zealand Counter-Terrorism Committee review the Australia–New Zealand Guidelines for Deployment of Police to High-Risk Situations and the Police Tactical Group Operations Manual to ensure that those documents give commanders guidance on how to assess imminent or immediate risk. |
REC292-2341 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force review the Management Operational Guidelines to resolve any inconsistency between them and relevant counter terrorism protocols. |
REC292-2371 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force develop a comprehensive policy and set of procedures in relation to family liaison capability for high-risk situations. Those policies and procedures should ensure that: The capability is scalable depending on the nature of the incident, An appropriately senior officer is responsible for overseeing the liaison process, He or she should have direct access to officers in the Police Forward Command Post for the purpose of conveying and receiving information in a timely manner, A dedicated family liaison officer (or officers) is assigned to the family of each victim and given responsibility for managing the needs of that family Officers are given guidance on communi-cating with families, including the appropriate frequency and content of briefings both during and after an incident, Officers are advised of the proper process for gathering and disseminating intelligence from family members. |
REC292-2350 | 32 - Doctrine, standards, and reform | I recommend that the Secretariat of the Australia–New Zealand Counter-Terrorism Committee prepare guidelines regarding the interpretation and scope of the restrictions contained Clause 92 of the National Counter Terrorism Plan 2012. The Secretariat should also update relevant Australia–New Zealand Counter-Terrorism Committee documents and the New South Wales Police Force should update State Protection Group documents to refer to the latest versions of the National Counter-Terrorism Plan |
REC292-2376 | 32 - Doctrine, standards, and reform | I recommend that the Commonwealth Attorney-General, in consultation with states and territories, review existing arrangements for information sharing between federal, state and territory agencies during terrorist events to determine whether those arrangements (and the guidance provided to officers in respect of them) adequately facilitate the efficient identification and transfer of pertinent information between agencies. |
REC292-2363 | 32 - Doctrine, standards, and reform | I recommend that New South Wales Police Force policies be amended to require documentation of triggers for Emer-gency Actions. Consideration should be given to stipulating that “contingency triggers”—specific events that will require initiation of an EA or some other agreed response—should also be recorded. |
REC292-2340 | 32 - Doctrine, standards, and reform | I recommend that the Director of Public Prosecutions develop a policy for overseeing lawyers' exercise of the discretion not to oppose bail that takes into account the seriousness of the offences involved; the experience of the prosecutor appearing; and the views of the police officer in charge of the investigation, insofar as those views are based on facts relevant to bail determinations. |
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
REC292-2348 | 17 - Assets and technology | I recommend that if it has not already done so, the New South Wales Police Force acquires the audio surveillance technology that in similar circumstances would allow a device to be monitored in the Police Forward Command Post and/or the Police Operations Centre and that the organisation ensures that its capacity in this regard keeps pace with technological advances in the area. |
REC292-2375 | 32 - Doctrine, standards, and reform | I recommend that the ADF Review, in consultation with the police forces of the states and territories, examine the guidance available to ADF officers and state and territory police regarding: the role of ADF liaison officers; the availability of ADF assistance in the absence of a call-out; and the procedures to apply in relation to requests for, and the provision of, equipment or advice by the ADF. |
REC292-2362 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force review its policies to ensure that the usual arrangements for placing a sniper coordinator in the Police Forward Command Post are departed from only for sound operational reasons that are recorded. |
REC292-2338 | 32 - Doctrine, standards, and reform | I recommend that the Commissioner of Police issue guidelines to assist officers to determine when they should exercise their powers of arrest and take an accused into custody rather than proceeding by way of a court attendance notice. |
REC292-2368 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force develop a policy regarding the use of distraction devices and the training of officers in their use. |
REC292-2347 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force consider developing a pro forma debriefing sheet containing standard questions relevant to all or most high risk situations, which can be supplemented by the negotiation coordinator and the tactical commander to maximise the likelihood of all available relevant information being obtained during hostage debriefings. Such measures would also aid contemporaneous documentation of information derived from debriefs and assist in relaying all relevant information to command. |
REC292-2374 | 32 - Doctrine, standards, and reform | I recommend that the ADF Review give consideration to amending the Australia–New Zealand Counter-Terrorism Committee protocols to ensure that they provide sufficient guidance as to the respective roles of the ADF and state police tactical groups. Such guidance should accord with the legislative framework in Part IIIAAA of the Defence Act 1903 (Cth). |
REC292-2361 | 32 - Doctrine, standards, and reform | I recommend that the Minister for Police consider whether the provisions of the Terrorism (Police Powers) Act2002 should be amended to ensure that police officers have sufficient legal protection to respond to terrorist incidents in a manner most likely to minimise the risk to members of the public. |
REC292-2382 | 32 - Doctrine, standards, and reform | I recommend that the Minister for Police undertake a review of the Law Enforcement Conduct Commission Act 2016 with a view to enabling the Law Enforcement Conduct Commission to facilitate urgent debriefs and confidential internal reviews of critical incidents focused on improving current practice. |
REC292-2367 | 32 - Doctrine, standards, and reform | I recommend that the Australia New Zealand Policing Advisory Agency liaise with the Australia–New Zealand Counter-Terrorism Committee to determine whether policies requiring the consideration of more proactive intervention should be developed for responding to terrorist sieges. |
REC292-2344 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force review the division of tasks among the various officers responsible for responding to major high-risk situations to enable Police Forward Commanders to focus exclusively on their primary goals and that officers engaged in matters not directly related to the resolution of the incident be required to report to an officer other than the Police Forward Commander |
REC292-2373 | 32 - Doctrine, standards, and reform | I recommend that the ADF Review confer with state and territory governments about the criteria governing applications for the ADF to be called out pursuant to the Defence Act 1903(Cth) with a view to determining: whether further guidance is required on the criteria to be used by states and territories in determining whether to apply for Commonwealth assistance; and if so, what criteria ought to be stipulated. |
REC292-2359 | 32 - Doctrine, standards, and reform | I recommend that the New South Wales Police Force develop policies that require the recording of negotiation strategies and tactics, demands made by a hostage taker, and any progress towards resolution (or lack thereof ) in a form readily accessible by commanders and negotiators. |
REC292-2380 | 24 - Govt responsibility | I recommend that the New South Wales Police Force, in conjunction with NSW Health, establish a Fixated Threat Assessment Centre to identify and gather information about fixated persons, assess the risks they pose, and attempt to mitigate such risks through early intervention. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1532 | 32 - Doctrine, standards, and reform | The evacuation sub-plan component of the Local Disaster Managment Plan should be reviewed, including any identified triggers for activation. Ideally, the plan should be tested in a live, multi-agency exercise prior to next summer. |
REC271-1531 | 32 - Doctrine, standards, and reform | Banana Shire Council completes business continuity planning as a matter of priority, including documentation and testing of the plan. |
REC271-1525 | 6 - Insurance and legal liability | The Department of Energy and Water Supply, in conjunction with SunWater, seek clarification of the dam owners’ legal obligation to comply with Emergency Action Plans and, if required, investigate how a more flexible approach may be adopted. |
REC271-1524 | 9 - Community education | SunWater provide downstream residents with easily understood information regarding operation of the dam, and the impacts that various outflows may have for them, in accordance with mapping prepared for the Emergency Action Plan. This information should be complementary to any information from the Banana Shire Council. |
REC271-1523 | 9 - Community education | Banana Shire Council coordinates the development of a strategy to significantly enhance public education regarding local disaster management arrangements within the Banana Shire, focusing on key identified risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0811 | 9 - Community education | Monitor, investigate and address community response to flood warnings |
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
REC238-0810 | 9 - Community education | Undertake, coordinate and evaluate community education programs on flood risk and response. |
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
REC238-0809 | 9 - Community education | Ensure the SES has the long-term capacity to plan and exercise for the full range of flood events in the Hawkesbury-Nepean Valley |
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
REC238-0806 | 33 - Relief and recovery | Review the adequacy of current arrangements for infrastructure reconstruction following a major flood event in the Hawkesbury-Nepean Valley. |
REC238-0805 | 33 - Relief and recovery | Develop a Hawkesbury-Nepean Flood Recovery Plan, which identifies strategies and arrangement for recovery from severe floods in the Hawkesbury-Nepean Valley. |
REC238-0812 | 9 - Community education | Develop mechanisms and arrangements to promote and provide greater access to flood risk information. |
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
Rec-ID | Code | Recommendation |
---|---|---|
REC235-2809 | 32 - Doctrine, standards, and reform | The Australian National Audit Office recommends that the Department of Regional Australia, Local Government, Arts and Sport improve the arrangements for conducting value for money reviews of Victorian reconstruction projects by pursuing amendments to the operating protocol with Victoria to require that, at regular intervals, the Taskforce is provided with information on all reconstruction projects being delivered within the scope of the National Partnership Agreement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2811 | 32 - Doctrine, standards, and reform | In order to maximise the envisaged benefits from the Inspectorate’s program of value for money reviews, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce improve the application of the sampling approach to make it more representative of the |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1596 | 24 - Govt responsibility | Department of Broadband, Communications and the Digital Economy to review the content of the Government’s digital business website at www.digitalbusiness.gov.au and liaise with the Department of Industry, Innovation, Climate Change, Science, Research and Tertiary Education, which manages the www.business.gov.au, to ensure these business advice sites provide appropriate information regarding business continuity planning in the event of telecommunications outages. |
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2865 | 9 - Community education | Management of community expectations: further development of tools that would allow the community to more easily |
REC216-2864 | 9 - Community education | Management of community expectations: continued community education. |
REC216-2863 | 9 - Community education | Management of community expectations: better understanding of what different groups within a community expect. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1872 | 32 - Doctrine, standards, and reform | Fire services can improve outcomes by implementing standard procedures that ensure the welfare and safety of crews and the public are not compromised |
REC215-1880 | 24 - Govt responsibility | Regulators can help to achieve improved outcomes by involving fire services in the planning and licensing processes |
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
REC215-1878 | 32 - Doctrine, standards, and reform | Regulators can help to achieve improved outcomes by acknowledging that changes to legislation and the BPEM guidelines may be required to help address the identified issues |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0603 | 9 - Community education | The Queensland Government, in consultation with councils, should determine which urban areas in Queensland do not have access to flood information from a current flood study. The Queensland Government should rank those areas in order of priority in accordance with their need for updated flood information by reference to factors including: a. population b. sophistication of land use planning and emergency management measures already in place in those areas c. currency of any flood risk information available to the council d. approximate frequency of damaging floods in the area according to the historical record |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0689 | 9 - Community education | Councils should conduct education campaigns directed to ensuring that all residents and property owners in areas identified as being at risk of backflow flooding are aware of the circumstances in which backflow flooding can occur, the hazard it presents and what should be done if it occurs. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0615 | 9 - Community education | Flood maps, and property specific flooding information intended for use by the general public, should be readily interpretable and should, where necessary, be accompanied by a comprehensible explanatory note. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0614 | 9 - Community education | Councils and the Queensland Government should display on their websites all flood mapping they have commissioned or adopted. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0680 | 9 - Community education | Queensland Urban Utilities, and other distributor-retailers and councils, that have identified a practice of stormwater drains being connected to sewerage infrastructure, should conduct a program of education to raise public awareness that this practice is illegal and impedes the operation of the sewerage infrastructure. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0604 | 9 - Community education | By reference to the order of priority determined in accordance with recommendation 2.5, the Queensland Government and councils should together ensure that the council responsible for each urban area in Queensland has access to current flood study information. This will include determining: a. a process or processes by which the flood studies will be completed, including the involvement of the Queensland Government and relevant councils b. how, and from whom, the necessary technical and financial resources will be obtained c. a reasonable timeframe by which all flood studies required will be completed. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1920 | 6 - Insurance and legal liability | The Attorney General gives urgent consideration to determining an ex gratia payment for: |
REC204-1910 | 6 - Insurance and legal liability | As part of its review of its contract management processes, Tourism WA (with the Board of Tourism WA taking a lead role) should amend its contract template for event sponsorship to ensure that: |
REC204-1917 | 32 - Doctrine, standards, and reform | The review of the Health Act 1911 (WA) should include the following amendments: |
REC204-1907 | 32 - Doctrine, standards, and reform | The Department of Sport and Recreation facilitate the development of an Adventure Activity Standard for ultramarathons in order to determine a minimum safety standard for the sport. |
REC204-1916 | 25 - Inquiry, audit, lessons management and after action review | Local Emergency Management Committee (LEMC) processes should be reviewed to ensure that: |
REC204-1915 | 24 - Govt responsibility | The Department of Regional Development and Lands should ensure that event organisers and government agencies responsible for sponsoring and approving events have a greater level of awareness about the requirements of section 91 licences under the Land Administration Act 1977 (WA). |
REC204-1913 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Attorney General consider conducting a review of the Civil Liability Act 2002 (WA) in light of the 2011 Kimberley Ultramarathon. Such a review should consider issues such as the effectiveness given to competitor waivers under the Act and the potential difficulties of establishing proceedings and enforcing a judgement against foreign‐based providers of recreational activities. |
REC204-1921 | 32 - Doctrine, standards, and reform | The Coroner’s Act 1996 should be amended to give the Coroner jurisdiction to investigate fires that do not cause death, and that the Coroner should be suitably resourced to undertake investigations of the kind the subject of this Report. |
REC204-1911 | 24 - Govt responsibility | As part of the review of its due diligence processes, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0483 | 9 - Community education | the state ensure: • where external assistance is provided to Victoria during emergencies, communities are advised of the specific purpose of that assistance, through media and other information channels; and • all agencies provide incident management personnel with information regarding the arrangements for tasking Australian Defence Force resources and that this advice is reinforced during emergencies where Australian Defence Force support is provided. |
REC199-0431 | 9 - Community education | the state allocate core funding for the ongoing delivery of the ‘FloodSafe’ program to flood prone communities across Victoria. |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0430 | 9 - Community education | the state undertake a community education program to inform households of their respective flood risk. This may include information on rate notices of heights of houses above flood level and educating people about flash flooding. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1741 | 9 - Community education | A. The CFA further develop community education programs to specifically engage culturally and linguistically diverse (CALD) communities to address the importance of ethnic diversity. |
REC197-1733 | 25 - Inquiry, audit, lessons management and after action review | That a review of the Country Fire Authority Act 1958 and the Country Fire Authority Regulations 2004 be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2924 | 6 - Insurance and legal liability | That whenever flood cover is included in home building insurance policies: |
REC187-2940 | 6 - Insurance and legal liability | That for home contents insurance policies, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $100,000. For contents with a value greater than $100,000 policyholders then pay the full cost of the portion of risk exceeding $100,000. |
REC187-2957 | 6 - Insurance and legal liability | That the Commonwealth Government introduce a standard definition of flood in the form proposed in the ‘Reforming flood insurance: Clearing the waters’ consultation paper. |
REC187-2929 | 6 - Insurance and legal liability | That all home unit insurance policies include flood cover, in the same manner as for homes. |
REC187-2945 | 6 - Insurance and legal liability | That to facilitate flood risk information being made publicly available, Commonwealth, State and Territory governments grant indemnities to the providers of flood risk information if the information is obtained and provided in good faith and in the absence of any gross negligence. |
REC187-2962 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend clause 4.5 of the General Insurance Code of Practice to extend the time within which claimants in natural disasters have the right to make further claims or lodge reviews after the finalisation of an initial claim to seven months from the date of the relevant natural disaster, regardless of when the initial claim was finalised. |
REC187-2934 | 6 - Insurance and legal liability | That all insurers offering small business insurance be obliged to include flood cover on an opt-out basis, instead of an opt-in/opt-out basis as at present, in all of their small business package policies. |
REC187-2951 | 6 - Insurance and legal liability | That access to insurance be enhanced through the development of alternative payment options, in particular: |
REC187-2967 | 6 - Insurance and legal liability | That the current formula for the cost of rebuilding of State and Territory assets under the Natural Disaster Relief and Recovery Arrangements be changed to expenditure before any insurance recoveries by the State or Territory rather than net of any insurance recoveries. |
REC187-2923 | 6 - Insurance and legal liability | That home building and home contents insurance should not be made compulsory. |
REC187-2939 | 6 - Insurance and legal liability | That for body corporate insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000 times the number of units. For properties with a value greater than $500,000 times the number of units policyholders then pay the full cost of the portion of risk exceeding $500,000 times the number of units. |
REC187-2956 | 6 - Insurance and legal liability | That a ‘health warning’ be provided by insurers to the purchasers of home and contents policies that do not include full flood cover or full replacement cover. The health warning should be provided: |
REC187-2928 | 6 - Insurance and legal liability | That there be limitations on the size of the discount available to high-value homes. |
REC187-2944 | 6 - Insurance and legal liability | That the Commonwealth seek reimbursement of some portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2961 | 6 - Insurance and legal liability | That the Insurance Council of Australia repeal clauses 4.3 and 4.4 of the General Insurance Code of Practice, so that claims arising from natural disasters are subject to the same minimum standards as other claims — including the four month time limit for a determination on liability and the nature of the loss/damage with respect to the claim. |
REC187-2933 | 6 - Insurance and legal liability | That discounts be provided, in the same manner as for homes, to home contents insurance policies for eligible properties. |
REC187-2950 | 6 - Insurance and legal liability | That the Commonwealth engage with the insurance industry and the States and Territories in planning for the future coordination of charitable and government payments to individuals to assist with recovery after future natural disasters. |
REC187-2966 | 6 - Insurance and legal liability | That the Commonwealth and State governments provide funding for legal advice and assistance with insurance disputes following natural disasters. |
REC187-2922 | 6 - Insurance and legal liability | That all home building insurance policies include flood cover. |
REC187-2938 | 6 - Insurance and legal liability | That for home building insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000. For properties with a value greater than $500,000 policyholders then pay the full cost of the portion of risk exceeding $500,000. |
REC187-2955 | 6 - Insurance and legal liability | That, in endorsing the Government proposal for a Key Facts Statement, the Key Facts Statement list replacement cover and all natural disaster events, identified as ‘standard cover’ in the Insurance Contracts Regulations 1985. That insurers issue a Key Facts Statement to policy holders with all new policies written and all policy renewals on an annual basis. |
REC187-2927 | 6 - Insurance and legal liability | The levels of the discounts and the phasing out periods be reviewed from time to time. |
REC187-2943 | 6 - Insurance and legal liability | That the Commonwealth Government guarantee payment of claims from the reinsurance pool by ensuring that, whenever a funding shortfall occurs in the pool through claims exceeding the funds held in the pool, the Commonwealth would meet the shortfall. |
REC187-2960 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the Code of Practice to impose a four month time limit (subject to exceptional circumstances) to make a determination as to liability and the nature of the loss or damage with respect to a claim. That, should a claimant not receive a determination within the four month period, the claim be automatically escalated to an internal dispute resolution complaint and the insurer notify the Code Compliance Committee of the breach of the Code. |
REC187-2932 | 6 - Insurance and legal liability | That all home contents insurance policies include flood cover. |
REC187-2949 | 6 - Insurance and legal liability | That all home, contents and home unit insurance policies cover the policyholder for storm surge, tsunami and landslide, where the storm surge, tsunami or landslide is the result of another event that is covered under the policy and regardless of whether the insured property directly suffers damage from the underlying insured event. |
REC187-2965 | 6 - Insurance and legal liability | That ASIC conduct a review of the General Insurance Code of Practice three years after the amendments recommended to the Code in this Review are implemented, in order to assess the effectiveness of the Code with a view to determining whether an ASIC Regulatory Guide for claims handling should then be introduced. |
REC187-2921 | 6 - Insurance and legal liability | The Commonwealth Government guarantee the payment of claims by ensuring that, whenever a funding shortfall occurs in the reinsurance facility through claims exceeding the funds held in the facility, the Commonwealth would meet the shortfall and the Commonwealth would seek reimbursement of a portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2937 | 6 - Insurance and legal liability | That flood premium discounts be delivered through a model that requires insurers to retain and price a portion of the risk with the remainder to be ceded to the reinsurance facility at a discounted reinsurance premium. |
REC187-2954 | 6 - Insurance and legal liability | That subsection 35(2) of the Insurance Contracts Act 1984 be amended so that policyholders are not deemed to be clearly informed of a deviation from ‘standard cover’ by simply being provided a copy of the insurance policy or product disclosure statement. |
REC187-2926 | 6 - Insurance and legal liability | That flood premium discounts be provided for home building insurance for eligible homes: |
REC187-2942 | 6 - Insurance and legal liability | That a flood risk reinsurance facility, or reinsurance pool, be established which would have two primary functions: |
REC187-2959 | 6 - Insurance and legal liability | That every APRA-authorised general insurer adopt and comply with the General Insurance Code of Practice. |
REC187-2931 | 6 - Insurance and legal liability | That the definition of a home for the purposes of flood cover and flood premium discounts be any building for which a homeowner purchases a home insurance policy. |
REC187-2948 | 6 - Insurance and legal liability | That: |
REC187-2964 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice such that the General Insurance Code Compliance Committee: |
REC187-2920 | 6 - Insurance and legal liability | That a system of premium discounts be introduced in order that most purchasers of home insurance, home contents and home unit insurance policies in areas subject to flood risk be eligible for discounts against the full cost of flood insurance. |
REC187-2936 | 6 - Insurance and legal liability | That the questions of flood cover as standard in small business policies and access to discounted premiums for small business policyholders should be revisited once the recommended arrangements for homes, home units and home contents are in place. |
REC187-2953 | 6 - Insurance and legal liability | That all home building insurance policies providing sum insured cover be modified by the end of 2014 so as to include replacement value cover in the event of total loss of the home. That during the transition period insurers consider how the design features of home building replacement value policies should respond following a natural disaster, including the conditions under which cash settlements are to be offered and finalised. |
REC187-2925 | 6 - Insurance and legal liability | That the following five principles underpin the design of a system of premium discounts: |
REC187-2941 | 6 - Insurance and legal liability | That homes at high and extreme risk of flood be provided with discounts initially and that they be assessed regularly for mitigation work already undertaken and the potential for further mitigation. |
REC187-2958 | 6 - Insurance and legal liability | That, in order to give general insurance policyholders the same legal remedies as other consumers, unfair contract terms laws be applied to general insurance. |
REC187-2930 | 6 - Insurance and legal liability | That flood premium discounts be provided, in the same manner as for homes, to the bodies corporate of eligible properties, and on the same basis as for detached homes. |
REC187-2947 | 6 - Insurance and legal liability | That the Agency charge insurers a small administrative fee for each policy ceded to the reinsurance facility. |
REC187-2963 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice to require that: |
REC187-2919 | 6 - Insurance and legal liability | That all home insurance, home contents and home unit insurance policies include flood cover. |
REC187-2935 | 6 - Insurance and legal liability | That flood premium discounts not be provided to small businesses and that the reinsurance facility not offer reinsurance for small businesses. |
REC187-2952 | 6 - Insurance and legal liability | That lending institutions remind mortgagors annually of their obligations to hold home insurance and of the risks of under-insurance in order to minimise non-insurance and under-insurance of homes. |
REC187-2968 | 6 - Insurance and legal liability | That the Government give priority to introducing legislation necessary to ensure that all home, contents and home unit insurance policies include flood cover and to establish a new national agency for flood risk management and flood reinsurance purposes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3276 | 32 - Doctrine, standards, and reform | WOMPs should be comprehensive and freestanding, rather than an overarching document cross‐referencing many other documents (although the Inquiry also recommends a freestanding well control manual; this should be a guide to rig and onshore personnel on good oilfield practice). |
REC177-3306 | 32 - Doctrine, standards, and reform | It should be standard industry practice to re‐test a cemented casing shoe (that is, after WOC) whenever the plugs do not bump or the float valves apparently fail. Standard industry practice should require consideration of other tests in addition to a repeat pressure test. |
REC177-3322 | 32 - Doctrine, standards, and reform | Batched drilling operations should only be undertaken after careful assessment of the special risks which such operations give rise to; well control must be maintained during the course of batched drilling operations. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3365 | 6 - Insurance and legal liability | The National Plan should specify that the cost of responding to an oil spill, or other damage to the offshore marine environment, will be totally met by the owner/operator. This would be consistent with the Inquiry’s recommendation for legislative changes to the regulatory framework concerning owner/operators meeting the cost of monitoring and remediation of environmental damage. |
REC177-3284 | 32 - Doctrine, standards, and reform | Memoranda of Agreement should be entered into between operators in relation to provision of emergency assistance in the event of blowouts. |
REC177-3311 | 32 - Doctrine, standards, and reform | Horizontal or high angle penetration of a reservoir should be avoided wherever practicable until such time as the apparent problems associated with the cementing of a casing shoe in these situations are satisfactorily overcome. If a casing string does penetrate a well horizontally or at a high angle, standard practice should be to install two secondary barriers in addition to the cemented casing shoe. |
REC177-3327 | 32 - Doctrine, standards, and reform | Information relevant to well control must be captured and communicated within and between licensees and rig operators (and relevant third party contractors), in a manner which ensures it comes to the attention of relevant personnel. In particular, protocols should be developed to ensure that changes in shift and hitch do not operate as communication barriers. |
REC177-3355 | 32 - Doctrine, standards, and reform | The Inquiry also supports Bills and Agostini’s recommendation: ‘…in relation to safety case development and compliance overall, that NOPSA revise its approach to interacting with operators prior to the safety case assessment process and subsequently direct more resources into its advisory functions. We further recommend that NOPSA develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on the latest information, including the interaction with the operator’. |
REC177-3370 | 32 - Doctrine, standards, and reform | Environment plans and OSCPs should be made publicly available as a condition of approval of proposals under the OPGGS Act, and should clearly set out Scientific Monitoring requirements in the event of an oil spill. |
REC177-3298 | 32 - Doctrine, standards, and reform | Reliance upon one barrier against a blowout must not take place except with the prior written approval of the relevant regulator and then only in a true emergency situation (see below). |
REC177-3316 | 32 - Doctrine, standards, and reform | Wells should be re‐entered with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3335 | 32 - Doctrine, standards, and reform | Licensees, rig operators and relevant third party contractors should develop well control competency standards for key personnel in other entities involved in well control operations. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3275 | 32 - Doctrine, standards, and reform | Well Operations Management Plan (WOMPs) submitted by licensees to the regulator(s) should continue to be the primary framework document for achieving well integrity. |
REC177-3305 | 32 - Doctrine, standards, and reform | Cement integrity should be evaluated wherever practicable by way of cement evaluation tests, rather than relying on pre‐operational calculations of cement and displacement fluid volumes. |
REC177-3320 | 32 - Doctrine, standards, and reform | Any pro‐formas used by licensees, rig operators and contractors for recording information about installation of barriers should explicitly provide for ‘exception reporting’, that is, the form should include provision for recording any unforseen or untoward events which occur in the course of installation. |
REC177-3343 | 32 - Doctrine, standards, and reform | The OPGGS Act should be amended to allow for a power to suspend a petroleum production licence (in addition to the current power to cancel a licence or suspend its conditions). |
REC177-3283 | 32 - Doctrine, standards, and reform | A separate, identifiable barrier manual should be agreed upon and used by licensees, rig operators, and cementing contractors. These manuals should set out best industry practice in relation to achieving and maintaining well integrity. They should describe barrier types, barrier standards, general principles of well integrity, testing and verification methods and technologies, standard operating procedures (including procedures for the capture and communication of relevant information within and between relevant stakeholder entities). Barrier manuals should address blowout control during drilling, completion, re‐entry, tie‐back of casing strings and so on. Barrier manuals should be the subject of expert external review, and should be regularly updated. |
REC177-3310 | 6 - Insurance and legal liability | Consideration should be given to ways to ensure that contractors who are involved in barrier installation (such as cementing companies) have a direct interest in the performance of works to a proper standard. In particular, consideration should be given to (i) preventing contractors from avoiding the economic consequences of negligent installation of barriers; and/or (ii) imposing specific legislative standards of workmanship on contractors with respect to well control (similar to those which presently apply to licensees). |
REC177-3326 | 32 - Doctrine, standards, and reform | Prior to commencement of drilling operations, senior representatives of the licensee and rig operator should exchange certificates to the effect that their respective key personnel and contractors have been informed in writing of agreed well control arrangements. |
REC177-3354 | 32 - Doctrine, standards, and reform | NOPSA develop a policy of engagement with operators so as to enable experts (including safety experts) to canvas all available options for well control in the event of a blowout. |
REC177-3369 | 6 - Insurance and legal liability | The obligation of companies involved in an incident to meet the full costs of monitoring and remediation should be made a condition of approval of proposals under the EPBC Act and OPGGS Act. Suitable arrangements (insurance or otherwise) need to be in place to ensure that companies have this capacity. |
REC177-3297 | 32 - Doctrine, standards, and reform | A minimum of two barriers should be in place at all times (including during batched operations) whenever it is reasonably practicable to do so. |
REC177-3315 | 32 - Doctrine, standards, and reform | PCCCs should be installed in a timely manner (for example, to prevent corrosion in the MLS apparatus). Non‐installation in order to park a BOP is not acceptable. |
REC177-3334 | 32 - Doctrine, standards, and reform | Licensees, rig operators, and relevant third party contractors should develop well control competency standards for their key personnel. Wherever possible, the competencies of key personnel should be benchmarked against their roles and responsibilities. |
REC177-3363 | 32 - Doctrine, standards, and reform | DEWHA, in concert with AMSA and with expert input, should develop ‘off the shelf’ monitoring programs that can be speedily implemented following incidents in Commonwealth waters. In this context, the utility of the current Scientific Monitoring program should be peer reviewed to inform future policy. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3302 | 32 - Doctrine, standards, and reform | Industry, regulators, and training/research institutions should develop standards that address best practices for cementing operations (including liaising, as appropriate, with overseas regulators) with a view to overcoming problems which can effect the integrity of cemented casing shoes, annulus and cement plugs. |
REC177-3342 | 32 - Doctrine, standards, and reform | Written (rather than verbal) approval from the DA (or new regulator) should be obtained before the commencement of well activities that lead to a physical change of a wellbore, other than in a true emergency situation (requiring amendment to regulation 17 of the Management of Well Operations Regulations). |
REC177-3280 | 32 - Doctrine, standards, and reform | Well construction and management plans should include provision for an independent compliance review of well integrity (i) in the event of stipulated triggers; and (ii) at least once in the period between perceived achievement of well integrity and production. The independent compliance review should be undertaken by an expert who is not involved in the day‐to‐day drilling operations. Reviews should be completed in sufficient time to enable results to be implemented in a meaningful manner. |
REC177-3309 | 32 - Doctrine, standards, and reform | If performance of barrier installation is outsourced by a licensee, the contractor (for example, the cementing company) should be engaged on terms which clearly require the provision of expert advisory services by the contractor with respect to barrier integrity. |
REC177-3325 | 32 - Doctrine, standards, and reform | Relevant personnel from licensees and rig operators should meet face to face to agree on, and document, well control issues/arrangements prior to commencement of drilling operations. Well control should be regarded as a so‐called SIMOP to signify its critical importance to both licensees and rig operators, and to ensure that they each take responsibility for achievement and maintenance of well control. |
REC177-3353 | 32 - Doctrine, standards, and reform | The regulatory regime should also impose an obligation on an operator to ascertain the availability, and provide details to the regulator, of any potential relief well rigs, prior to the commencement of drilling operations (including prior to each phase of a drilling operation where applicable). |
REC177-3368 | 32 - Doctrine, standards, and reform | The regulatory framework should provide that in respect of all activities in Commonwealth waters: |
REC177-3296 | 32 - Doctrine, standards, and reform | Use of single strings of intermediate casing to penetrate hydrocarbon bearing zones should be carefully risk assessed. Multiple strings of intermediate casing have the advantage of isolating lost circulation zones and sealing off anomalous pressure zones. If intermediate casing is set in a hydrocarbon zone it should be treated as production casing. |
REC177-3314 | 32 - Doctrine, standards, and reform | Secondary barriers (including PCCCs) should only be installed, tested, and removed with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3362 | 32 - Doctrine, standards, and reform | Procedures for the approval of development projects should ensure that conditions of approval are comprehensive and clearly set out the obligations of their proponents in relation to environmental matters (including expected monitoring and remediation obligations). |
REC177-3377 | 32 - Doctrine, standards, and reform | The Minister consider legislative amendments to the OPGGS Act which make clear that |
REC177-3301 | 32 - Doctrine, standards, and reform | The industry standard of two barriers should be replaced with the concept of ‘two or more barriers’ as a minimum standard. A minimum standard when operations proceed normally should never be regarded as a sufficient standard in other circumstances. |
REC177-3319 | 32 - Doctrine, standards, and reform | Drilling programs dealing with barrier installation should incorporate relevant aspects of manufacturer’s instructions. |
REC177-3341 | 32 - Doctrine, standards, and reform | The definition of ‘good oilfield practice’ in the OPGGS Act is unduly narrow. The current definition is incapable of application except where things ‘are generally accepted as good and safe’. The definition should be amended such that ‘good oilfield practice includes…’. |
REC177-3308 | 32 - Doctrine, standards, and reform | Volumes of cement used in connection with barrier installation should be calculated with the assistance of a pro‐forma which records all relevant baseline data, which should be verified by onshore personnel. |
REC177-3324 | 32 - Doctrine, standards, and reform | The mere fact that the rig is over the platform should not be regarded by licensees or regulators as sufficient justification for reliance on only one barrier. The default position should be that producible wells are shut‐in when a rig is moved on and off a platform, or when a drilling unit is moved between wells on a platform. |
REC177-3352 | 32 - Doctrine, standards, and reform | The regulator, rather than the responsible Minister, should be given the power to direct an operator to use a particular rig for the purpose of well control operations, if appropriate in the circumstances, and the power should be used in the future if that rig is the best option available. This would necessarily involve the operator fully compensating for the use of the rig and any other associated costs. The Inquiry suggests that this power could be invoked and given effect as a condition of an operator’s licence. |
REC177-3367 | 32 - Doctrine, standards, and reform | Procedures and accountabilities should be established to ensure, in the event of a future incident, that: |
REC177-3292 | 32 - Doctrine, standards, and reform | Licensees should be subject to an express obligation to inform regulators of the proposed removal of a barrier, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. Removal of a barrier should not take place without prior written approval of the relevant regulator(s). |
REC177-3313 | 32 - Doctrine, standards, and reform | Barriers should not be installed or removed off‐line. The derrick should be located over a well at the time of removal and installation of any barrier. This will enable more decisive action to be taken in the event a problem arises. |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3361 | 32 - Doctrine, standards, and reform | The National Plan should be revised to ensure that it fully comprehends environmental matters and that it recognises the importance of the prompt implementation of Scientific Monitoring to facilitate the assessment of the environmental impacts of an incident. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3300 | 32 - Doctrine, standards, and reform | Licensees and rig operators should install an additional barrier whenever (i) there is any real doubt as to the integrity of any barrier; (ii) whenever the risk of flow from a reservoir increases materially in the course of operations; and (iii) where the consequences of a blowout are grave (for example, for reef systems or shorelines). |
REC177-3318 | 32 - Doctrine, standards, and reform | Manufacturers should be consulted about how to address non‐routine operational problems affecting their well control equipment. |
REC177-3340 | 32 - Doctrine, standards, and reform | To better ensure that ‘risks’ are identified and managed in accordance with sound engineering principles and good oilfield practice, it is recommended that regulation 25(1)(a)(i) and (2)(a)(i) of the Management of Well Operations Regulations, be reworded as follows: ‘A titleholder must not commence / continue a well activity if…a well integrity hazard exists in relation to the well’. |
REC177-3277 | 32 - Doctrine, standards, and reform | The concept of ‘good oilfield practice’ should be supplemented by the requirement to incorporate into WOMPs non‐exhaustive minimum compliance standards in relation to well control: for example, stipulations as to when BOPs and/or well control systems must be in place and when they can be removed and minimum barrier requirements (a number of other factors that should be stipulated are outlined in other recommendations below). |
REC177-3307 | 32 - Doctrine, standards, and reform | Any indication of a compromised cemented shoe which cannot be resolved with a high measure of confidence should result in the installation of additional well control barrier(s). |
REC177-3323 | 32 - Doctrine, standards, and reform | Where multiple wells are drilled, operations and occurrences at one well must be carefully assessed for any implications with respect to well control at other wells. |
REC177-3350 | 32 - Doctrine, standards, and reform | The recommendations of the Inquiry in relation to suitable ways of achieving well integrity contained in Chapter 3 be included in a guidance manual that is issued for the assistance of industry and regulators. |
REC177-3366 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed: |
REC177-3312 | 32 - Doctrine, standards, and reform | The BOP and rig should not move from a well until barrier integrity has been verified. |
REC177-3328 | 32 - Doctrine, standards, and reform | All communications between on‐rig and onshore personnel relating to well control should be documented in a timely manner. |
REC177-3359 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed to clarify the arrangements to apply in Commonwealth waters regarding key roles and responsibilities, including in relation to the ESC, in the event of an oil spill. This should also address any necessary training required. |
REC177-3373 | 32 - Doctrine, standards, and reform | Arrangements should be developed to minimise duplication between the EPBC Act and the OPGSS Act Environment Regulation. |
REC177-3317 | 32 - Doctrine, standards, and reform | Any equipment (including PCCCs) used as, or to install, a barrier should be manufactured for that purpose and be generally recognised as fit for purpose. If equipment is designed in‐house by a licensee or rig operator it should not be approved for use unless and until it is subjected to expert external analysis. |
REC177-3339 | 32 - Doctrine, standards, and reform | The Inquiry supports the objective (rather than prescriptive) approach to regulation now followed in Australia. However, the pendulum has swung too far away from prescriptive standards. In some areas relating to well integrity there needs to be minimum standards. |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2993 | 24 - Govt responsibility | The Department of Premier and Cabinet should clarify the requirements in relation to establishing Security and Continuity Networks in designated sectors, so that there is a shared understanding of those requirements. |
REC169-2992 | 24 - Govt responsibility | The Department of Premier and Cabinet should identify risks arising from the joined-up nature of the approach to protecting essential services and critical infrastructure, and to assist departments and agencies to develop associated risk management arrangements at the whole-of-government level. |
REC169-2991 | 24 - Govt responsibility | The Department of Premier and Cabinet should provide definitive guidance on identifying essential services for declaration to better inform relevant departments in discharging their responsibilities under Part 6 of the Act. |
REC169-2996 | 32 - Doctrine, standards, and reform | The Department of Premier and Cabinet should provide clear guidance on terms such as ‘audit’, ‘auditor’ and ‘adequacy of the exercise’ to assist departments, Victoria Police and industry to implement requirements more reliably. |
REC169-2990 | 24 - Govt responsibility | The Department of Premier and Cabinet should clarify the roles and responsibilities of departments and agencies under Part 6 of the Act and CIP framework to reduce confusion and gaps. |
REC169-2995 | 24 - Govt responsibility | The Department of Premier and Cabinet, in consultation with Victoria Police, should develop clear guidance to distinguish between declared essential services and critical infrastructure to assist departments, Victoria Police and industry in implementing Part 6 of the Act and the CIP framework more effectively. |
REC169-2988 | 32 - Doctrine, standards, and reform | The Department of Premier and Cabinet should establish clear oversight and coordination of the arrangements for both Part 6 of the Terrorism (Community Protection) Act 2003 and the CIP framework by an appropriate body, such as the Government Security and Continuity Network Coordination Group with expanded responsibilities. |
REC169-2994 | 24 - Govt responsibility | Representatives of lead departments should obtain necessary security clearances so appropriate officers can access information relevant to their sectors. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3004 | 17 - Assets and technology | That the Tasmania Fire Service consider improvements in radio units installed in breathing apparatus: |
REC166-3000 | 32 - Doctrine, standards, and reform | That the Tasmania Fire Service establish clear systems and protocols for dealing with fires. |
REC166-3009 | 25 - Inquiry, audit, lessons management and after action review | That the Tasmania Fire Service conduct an audit of all shopping centres to ensure that there exists within those centres adequate fire protection and evacuation systems. |
REC166-3005 | 32 - Doctrine, standards, and reform | That the Coroner prepare a discussion paper and draft guidelines for the clarification of investigative roles of the Tasmania Police Service, the Tasmania Fire Service, and the Coroners Office for adoption in relation to future fires where a Coroner’s Inquest is established. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0071 | 32 - Doctrine, standards, and reform | SERCon consider the establishment of a body, such as a State Recovery Committee, with responsibility for the |
REC164-0076 | 32 - Doctrine, standards, and reform | SERCon consider meeting with the State Emergency Management Committee, Directors General and agency heads to |
REC164-0077 | 32 - Doctrine, standards, and reform | SERCon consider the continued development of a State Recovery Sub-Plan (including complementary local and district |
REC164-0072 | 32 - Doctrine, standards, and reform | SERCon consider that the proposed State Recovery Committee review the recommended considerations arising from |
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
REC164-0074 | 9 - Community education | SERCon consider a review of existing community-based educational programs, with a view to informing the community |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
REC125-3895 | 32 - Doctrine, standards, and reform | That all agencies develop drainage asset management plans, consistent with best practice, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3423 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3247 | 32 - Doctrine, standards, and reform | The Committee recommends that the Ministry for Police and Emergency Services seek common national fire standards. |
REC061-3422 | 9 - Community education | The Committee recommends that the FireVision concept used by the Metropolitan Fire Brigades Board be extended through the Directorate of School Education's Interactive Television Program to all emergency services and in particular to rural fire and emergency services. |
REC061-3244 | 32 - Doctrine, standards, and reform | The Committee recommends that, following the development of standards of fire cover, related standards be established for: |
REC061-3415 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
REC061-3242 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3258 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3412 | 32 - Doctrine, standards, and reform | The Committee recommends that the Ministry for Police and Emergency Services seek common national fire standards. |
REC061-3410 | 32 - Doctrine, standards, and reform | The Committee recommends that, following the development of standards of fire cover, related standards be established for: |
REC061-3257 | 9 - Community education | The Committee recommends that the FireVision concept used by the Metropolitan Fire Brigades Board be extended through the Directorate of School Education's Interactive Television Program to all emergency services and in particular to rural fire and emergency services. |
REC061-3408 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3250 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |