Rec-ID | Code | Recommendation |
---|---|---|
REC325-4336 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services, in consultation with the Queensland Police Service, incorporate into the workflow of the current Emergency Alert system a process that ensures the inclusion of an ‘urgent approval and distribution without delay’ process for Emergency Alert messages by 1 November 2022. |
REC325-4337 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an urgent multi-agency (including but not limited to the Queensland Police Service and Brisbane City Council) review of the workflow, of the current Emergency Alert system, including requesting, composing, authorising and issuing of Emergency Alerts by 1 November 2022. |
REC325-4329 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services implement the Australian Warning System for all nationally agreed hazards by 1 November 2023. Implementation should include guidance and training to all local governments and agencies operationally involved in disaster management, with emphasis on those agencies with hazard specific responsibility. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that do not have pre-formatted messages and polygons engage with Queensland Fire and Emergency Services and determine whether their local disaster management group capability could be improved through the development of pre-formatted polygons and messages. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that currently use pre-formatted messages within the Emergency Alert system review and, where necessary, redraft messages using the principles of Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4318 | 12 - EM agency and authority | Permanent SEOCON: That, to improve NSW’s ability to prepare and respond to floods and other disasters, Government establish a new Deputy Commissioner of NSW Police Force to take on permanently the SEOCON role. This role, in addition to current SEOCON functions, would be responsible for: |
REC324-4306 | 6 - Insurance and legal liability | NSW Reconstruction Authority: That, to provide rapid and effective recovery from floods (and other disasters) and to provide maximum mitigation of the impacts of future floods (and other disasters), Government establish a permanent state-wide agency, the NSW Reconstruction Authority (NSWRA) dedicated to disaster recovery, reconstruction and preparedness. The NSWRA should: |
REC324-4320 | 12 - EM agency and authority | Knowledge resources to support flood management: That, to provide more accurate and complete data for flood threat identification, warning and modelling systems, Government through the proposed new NSW Reconstruction Authority (NSWRA) work with the Australian Government to: |
REC324-4309 | 12 - EM agency and authority | SES and RFS back-office merger: That, to help protect life and property across NSW in storm and flood events, and to improve resourcing and NSW State Emergency Service (SES) frontline capability, Government implement, before the next storm season, a merger of the SES and NSW Rural Fire Services (RFS) back-office and corporate service functions, while maintaining their separate legislative identity, brand, uniform and volunteer membership. This ‘joined-up’ RFS/SES corporate support structure would be under the command of the RFS given its corporate and operational maturity and would be responsible for: |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
REC324-4316 | 12 - EM agency and authority | Resilience NSW and recovery: That, in order to enhance NSW disaster preparedness, response and recovery, and meet the needs of the people of NSW prior to, during and after a disaster, and provide clarity on agency roles and responsibilities, Resilience NSW be reshaped to ‘Recovery NSW’. The new agency will be more streamlined and agile to drive recovery in the first 100 days post disaster. To achieve this, Resilience NSW’s functions should be reallocated as follows: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4291 | 12 - EM agency and authority | That the NSW Government consider abolishing Resilience NSW if it is unable to ensure: |
REC323-4292 | 12 - EM agency and authority | That the NSW Government consider a restructure of the NSW State Emergency Service with consideration to: realigning the focus of the organisation to harness local knowledge and networks; coordinating more closely with other rescue agencies to bolster its capacity to respond; and increasing salaried staff and resources, and driving volunteer recruitment. |
REC323-4283 | 8 - Communications and warnings | That the NSW Government work with the community broadcasting sector to identify ways in which community broadcasters could be better supported to provide critical services during natural disasters, with a view to providing them adequate long term funding. |
REC323-4284 | 8 - Communications and warnings | That the NSW Government review its public awareness and communication strategies in relation to natural disasters. |
REC323-4288 | 8 - Communications and warnings | That the NSW Government work with the Commonwealth to develop a national cross-agency app to integrate all community services and agencies into a single platform so that everyone can receive accurate and timely information from one source during emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2469 | 12 - EM agency and authority | Entities with disaster management responsibilities need to integrate the eight priorities identified within the Emergency Management Sector Adaptation Plan for Climate Change into their disaster management planning cycle. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1267 | 8 - Communications and warnings | That emergency management authorities react with heightened awareness and action when BoM issues flood watches and related warnings. |
REC297-1266 | 8 - Communications and warnings | That Government supports the anticipated SES State Flood Warning proposals aimed at improving public warnings and communication, and that the proposed warning system is consistent with the National Frameworks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1335 | 12 - EM agency and authority | Explore alternative emergency management models including the alternative model proposed above to establish a South Australian Emergency Management Office and State Relief and Recovery Office within the South Australian Fire and Emergency Services Commission, to ensure that all the objects and guiding principles of the Emergency Management Act 2004, and State Emergency Management Plan are addressed efficiently and effectively. |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1325 | 12 - EM agency and authority | Review and reinstate the State Emergency Management Training Officer and State Emergency Management Planning Officer (capability development) positions to operate with a broad, strategic and leadership focus. |
REC295-1322 | 12 - EM agency and authority | Consider opportunities to identify synergies between the incident management systems used in SA being the, Australasian Interservice Incident Management System (AIIMS) and ICCS Plus. This might include joint training and exercising in roles that are common across both systems. |
REC295-1298 | 12 - EM agency and authority | That the State Emergency Service, in consultation with key stakeholders, identify and implement a robust system and procedures for prioritising, allocating and coordinating multiple tasks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
REC271-1529 | 8 - Communications and warnings | As part of the above, both the Banana Shire Council and SunWater ensure Emergency Alert messages are pre-formatted, consistent, polygons are identified according to risk, and that they are tested and practiced with the State Disaster Coordination Centre. |
REC271-1528 | 8 - Communications and warnings | Prior to September 2015, SunWater and the Banana Shire Council jointly develop a multi-channel, common warning strategy, including common language and consistent messaging, for residents downstream of |
REC271-1527 | 8 - Communications and warnings | Prior to September 2015, the Banana Shire Council develops a multi-channel warning strategy and associated public information campaign, including common language and consistent messaging, for the Banana Shire. |
REC271-1525 | 6 - Insurance and legal liability | The Department of Energy and Water Supply, in conjunction with SunWater, seek clarification of the dam owners’ legal obligation to comply with Emergency Action Plans and, if required, investigate how a more flexible approach may be adopted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2532 | 12 - EM agency and authority | The next Director of Aviation Safety has leadership and management experience and capabilities in cultural change of large organisations. Aviation or other safety industry experience is highly desirable. |
REC258-2546 | 12 - EM agency and authority | The Civil Aviation Safety Authority changes its organisational structure to a client-oriented output model. |
REC258-2558 | 12 - EM agency and authority | The Civil Aviation Safety Authority applies a project management approach to the completion of all Civil Aviation Safety Regulation Parts not yet in force, with drafting to be completed within one year and consultation completed one year later, with: |
REC258-2545 | 12 - EM agency and authority | The Australian Transport Safety Bureau transfers its safety education function to the Civil Aviation Safety Authority. |
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2553 | 12 - EM agency and authority | The Civil Aviation Safety Authority establishes a safety oversight risk management hierarchy based on a categorisation of operations. Rule making and surveillance priorities should be proportionate to the safety risk. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
REC258-2547 | 12 - EM agency and authority | The Civil Aviation Safety Authority establishes small offices at specific industry centres to improve monitoring, service quality, communications and collaborative relationships. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2790 | 12 - EM agency and authority | The committee recommends that an expert aviation safety panel be established to ensure quality control of ATSB investigation and reporting processes along the lines set out by the committee. |
REC236-2797 | 12 - EM agency and authority | The committee recommends that all meetings between the ATSB and CASA, whether formal or informal, where particulars of a given investigation are being discussed be appropriately minuted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2856 | 12 - EM agency and authority | I recommend that BPC establish an onshore presence as recommended by Lieutenant Commander Livingstone. |
REC227-2854 | 12 - EM agency and authority | I recommend that the Christmas Island VMRS be given autonomy to maintain operational readiness for the VMRS rescue vessel(s) and an appropriate budget be provided to allow this to take place. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0524 | 8 - Communications and warnings | That the Premier issue clear and unambiguous guidelines to all Government Ministers specifying the timing of notifications to the public of any matters that may affect public health or safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2942 | 6 - Insurance and legal liability | That a flood risk reinsurance facility, or reinsurance pool, be established which would have two primary functions: |
REC187-2959 | 6 - Insurance and legal liability | That every APRA-authorised general insurer adopt and comply with the General Insurance Code of Practice. |
REC187-2926 | 6 - Insurance and legal liability | That flood premium discounts be provided for home building insurance for eligible homes: |
REC187-2948 | 6 - Insurance and legal liability | That: |
REC187-2964 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice such that the General Insurance Code Compliance Committee: |
REC187-2931 | 6 - Insurance and legal liability | That the definition of a home for the purposes of flood cover and flood premium discounts be any building for which a homeowner purchases a home insurance policy. |
REC187-2953 | 6 - Insurance and legal liability | That all home building insurance policies providing sum insured cover be modified by the end of 2014 so as to include replacement value cover in the event of total loss of the home. That during the transition period insurers consider how the design features of home building replacement value policies should respond following a natural disaster, including the conditions under which cash settlements are to be offered and finalised. |
REC187-2920 | 6 - Insurance and legal liability | That a system of premium discounts be introduced in order that most purchasers of home insurance, home contents and home unit insurance policies in areas subject to flood risk be eligible for discounts against the full cost of flood insurance. |
REC187-2936 | 6 - Insurance and legal liability | That the questions of flood cover as standard in small business policies and access to discounted premiums for small business policyholders should be revisited once the recommended arrangements for homes, home units and home contents are in place. |
REC187-2941 | 6 - Insurance and legal liability | That homes at high and extreme risk of flood be provided with discounts initially and that they be assessed regularly for mitigation work already undertaken and the potential for further mitigation. |
REC187-2958 | 6 - Insurance and legal liability | That, in order to give general insurance policyholders the same legal remedies as other consumers, unfair contract terms laws be applied to general insurance. |
REC187-2925 | 6 - Insurance and legal liability | That the following five principles underpin the design of a system of premium discounts: |
REC187-2947 | 6 - Insurance and legal liability | That the Agency charge insurers a small administrative fee for each policy ceded to the reinsurance facility. |
REC187-2963 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice to require that: |
REC187-2930 | 6 - Insurance and legal liability | That flood premium discounts be provided, in the same manner as for homes, to the bodies corporate of eligible properties, and on the same basis as for detached homes. |
REC187-2952 | 6 - Insurance and legal liability | That lending institutions remind mortgagors annually of their obligations to hold home insurance and of the risks of under-insurance in order to minimise non-insurance and under-insurance of homes. |
REC187-2968 | 6 - Insurance and legal liability | That the Government give priority to introducing legislation necessary to ensure that all home, contents and home unit insurance policies include flood cover and to establish a new national agency for flood risk management and flood reinsurance purposes. |
REC187-2919 | 6 - Insurance and legal liability | That all home insurance, home contents and home unit insurance policies include flood cover. |
REC187-2935 | 6 - Insurance and legal liability | That flood premium discounts not be provided to small businesses and that the reinsurance facility not offer reinsurance for small businesses. |
REC187-2940 | 6 - Insurance and legal liability | That for home contents insurance policies, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $100,000. For contents with a value greater than $100,000 policyholders then pay the full cost of the portion of risk exceeding $100,000. |
REC187-2957 | 6 - Insurance and legal liability | That the Commonwealth Government introduce a standard definition of flood in the form proposed in the ‘Reforming flood insurance: Clearing the waters’ consultation paper. |
REC187-2924 | 6 - Insurance and legal liability | That whenever flood cover is included in home building insurance policies: |
REC187-2945 | 6 - Insurance and legal liability | That to facilitate flood risk information being made publicly available, Commonwealth, State and Territory governments grant indemnities to the providers of flood risk information if the information is obtained and provided in good faith and in the absence of any gross negligence. |
REC187-2962 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend clause 4.5 of the General Insurance Code of Practice to extend the time within which claimants in natural disasters have the right to make further claims or lodge reviews after the finalisation of an initial claim to seven months from the date of the relevant natural disaster, regardless of when the initial claim was finalised. |
REC187-2929 | 6 - Insurance and legal liability | That all home unit insurance policies include flood cover, in the same manner as for homes. |
REC187-2951 | 6 - Insurance and legal liability | That access to insurance be enhanced through the development of alternative payment options, in particular: |
REC187-2967 | 6 - Insurance and legal liability | That the current formula for the cost of rebuilding of State and Territory assets under the Natural Disaster Relief and Recovery Arrangements be changed to expenditure before any insurance recoveries by the State or Territory rather than net of any insurance recoveries. |
REC187-2934 | 6 - Insurance and legal liability | That all insurers offering small business insurance be obliged to include flood cover on an opt-out basis, instead of an opt-in/opt-out basis as at present, in all of their small business package policies. |
REC187-2939 | 6 - Insurance and legal liability | That for body corporate insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000 times the number of units. For properties with a value greater than $500,000 times the number of units policyholders then pay the full cost of the portion of risk exceeding $500,000 times the number of units. |
REC187-2956 | 6 - Insurance and legal liability | That a ‘health warning’ be provided by insurers to the purchasers of home and contents policies that do not include full flood cover or full replacement cover. The health warning should be provided: |
REC187-2923 | 6 - Insurance and legal liability | That home building and home contents insurance should not be made compulsory. |
REC187-2944 | 6 - Insurance and legal liability | That the Commonwealth seek reimbursement of some portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2961 | 6 - Insurance and legal liability | That the Insurance Council of Australia repeal clauses 4.3 and 4.4 of the General Insurance Code of Practice, so that claims arising from natural disasters are subject to the same minimum standards as other claims — including the four month time limit for a determination on liability and the nature of the loss/damage with respect to the claim. |
REC187-2928 | 6 - Insurance and legal liability | That there be limitations on the size of the discount available to high-value homes. |
REC187-2950 | 6 - Insurance and legal liability | That the Commonwealth engage with the insurance industry and the States and Territories in planning for the future coordination of charitable and government payments to individuals to assist with recovery after future natural disasters. |
REC187-2966 | 6 - Insurance and legal liability | That the Commonwealth and State governments provide funding for legal advice and assistance with insurance disputes following natural disasters. |
REC187-2933 | 6 - Insurance and legal liability | That discounts be provided, in the same manner as for homes, to home contents insurance policies for eligible properties. |
REC187-2938 | 6 - Insurance and legal liability | That for home building insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000. For properties with a value greater than $500,000 policyholders then pay the full cost of the portion of risk exceeding $500,000. |
REC187-2955 | 6 - Insurance and legal liability | That, in endorsing the Government proposal for a Key Facts Statement, the Key Facts Statement list replacement cover and all natural disaster events, identified as ‘standard cover’ in the Insurance Contracts Regulations 1985. That insurers issue a Key Facts Statement to policy holders with all new policies written and all policy renewals on an annual basis. |
REC187-2922 | 6 - Insurance and legal liability | That all home building insurance policies include flood cover. |
REC187-2943 | 6 - Insurance and legal liability | That the Commonwealth Government guarantee payment of claims from the reinsurance pool by ensuring that, whenever a funding shortfall occurs in the pool through claims exceeding the funds held in the pool, the Commonwealth would meet the shortfall. |
REC187-2960 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the Code of Practice to impose a four month time limit (subject to exceptional circumstances) to make a determination as to liability and the nature of the loss or damage with respect to a claim. That, should a claimant not receive a determination within the four month period, the claim be automatically escalated to an internal dispute resolution complaint and the insurer notify the Code Compliance Committee of the breach of the Code. |
REC187-2927 | 6 - Insurance and legal liability | The levels of the discounts and the phasing out periods be reviewed from time to time. |
REC187-2949 | 6 - Insurance and legal liability | That all home, contents and home unit insurance policies cover the policyholder for storm surge, tsunami and landslide, where the storm surge, tsunami or landslide is the result of another event that is covered under the policy and regardless of whether the insured property directly suffers damage from the underlying insured event. |
REC187-2965 | 6 - Insurance and legal liability | That ASIC conduct a review of the General Insurance Code of Practice three years after the amendments recommended to the Code in this Review are implemented, in order to assess the effectiveness of the Code with a view to determining whether an ASIC Regulatory Guide for claims handling should then be introduced. |
REC187-2932 | 6 - Insurance and legal liability | That all home contents insurance policies include flood cover. |
REC187-2937 | 6 - Insurance and legal liability | That flood premium discounts be delivered through a model that requires insurers to retain and price a portion of the risk with the remainder to be ceded to the reinsurance facility at a discounted reinsurance premium. |
REC187-2954 | 6 - Insurance and legal liability | That subsection 35(2) of the Insurance Contracts Act 1984 be amended so that policyholders are not deemed to be clearly informed of a deviation from ‘standard cover’ by simply being provided a copy of the insurance policy or product disclosure statement. |
REC187-2921 | 6 - Insurance and legal liability | The Commonwealth Government guarantee the payment of claims by ensuring that, whenever a funding shortfall occurs in the reinsurance facility through claims exceeding the funds held in the facility, the Commonwealth would meet the shortfall and the Commonwealth would seek reimbursement of a portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3442 | 12 - EM agency and authority | That emergency services continue to take the lead role in marine emergencies and operate under their respective legislation, the Emergency Management Act and the State’s emergency management arrangements. |
REC158-3443 | 12 - EM agency and authority | That emergency services increase their capability/capacity to respond to marine emergencies by undertaking the necessary training, increasing their awareness of port and ship operations and ensuring knowledge of the roles/responsibilities of the relevant authorities and stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3900 | 12 - EM agency and authority | That agencies integrate condition information into their asset management decision-making practices and use it as the basis for validating asset valuations and depreciation calculations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3658 | 12 - EM agency and authority | All emergency services stations should be provided with access keys to, and maps showing, all gates providing access to RailCorp tracks within their geographic area of responsibility. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3708 | 12 - EM agency and authority | RailCorp should employ a Chief Safety Information Officer to manage the collection, collation, and dissemination of safety information within RailCorp. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3703 | 6 - Insurance and legal liability | Alcohol and drug testing should be mandatory for any train driver or guard involved in any accident or incident. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3700 | 12 - EM agency and authority | The RailCorp defects unit should be combined with the passenger fleet maintenance division of RailCorp. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3766 | 12 - EM agency and authority | Staffing arrangements for ITSRR should be reviewed by it to ensure that adequate staff are employed in field positions, actively monitoring the safety of rail operations and compliance with conditions of accreditation. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3689 | 12 - EM agency and authority | All RMC communications related staff should be selected upon the basis of the ability to convey information clearly, accurately and concisely and to follow strict communications protocols. |
REC121-3752 | 12 - EM agency and authority | RailCorp should establish clear safety accountability statements and reporting lines for all management positions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |