REC324-4320 | 12 - EM agency and authority | Knowledge resources to support flood management: That, to provide more accurate and complete data for flood threat identification, warning and modelling systems, Government through the proposed new NSW Reconstruction Authority (NSWRA) work with the Australian Government to: |
REC324-4319 | 26 - Research | Climate and weather research: That, to enable effective mitigation and adaptation measures in response to changing climate risks, Government establish NSW as a world centre of disaster research and technology development. This should include: |
REC324-4318 | 12 - EM agency and authority | Permanent SEOCON: That, to improve NSW’s ability to prepare and respond to floods and other disasters, Government establish a new Deputy Commissioner of NSW Police Force to take on permanently the SEOCON role. This role, in addition to current SEOCON functions, would be responsible for: |
REC324-4317 | 32 - Doctrine, standards, and reform | Flood rescue capability: That, to help improve the protection of life across NSW in flood events: |
REC324-4316 | 12 - EM agency and authority | Resilience NSW and recovery: That, in order to enhance NSW disaster preparedness, response and recovery, and meet the needs of the people of NSW prior to, during and after a disaster, and provide clarity on agency roles and responsibilities, Resilience NSW be reshaped to ‘Recovery NSW’. The new agency will be more streamlined and agile to drive recovery in the first 100 days post disaster. To achieve this, Resilience NSW’s functions should be reallocated as follows: |
REC324-4315 | 36 - Volunteers | The Community First Responders Program: That, to better coordinate community efforts to save life and property during a disaster, Government create a ‘Community First Responders Program’, funding appropriate community equipment and training, particularly in high-risk catchments along the east coast of NSW. This training would be delivered by combat and/or other appropriate government agencies. This program could support and empower community led initiatives such as disaster response, evacuation centres and the provision of services such as psychological first aid. |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4309 | 12 - EM agency and authority | SES and RFS back-office merger: That, to help protect life and property across NSW in storm and flood events, and to improve resourcing and NSW State Emergency Service (SES) frontline capability, Government implement, before the next storm season, a merger of the SES and NSW Rural Fire Services (RFS) back-office and corporate service functions, while maintaining their separate legislative identity, brand, uniform and volunteer membership. This ‘joined-up’ RFS/SES corporate support structure would be under the command of the RFS given its corporate and operational maturity and would be responsible for: |
REC324-4308 | 26 - Research | Compound mental helath studies: That, to inform Government policies and programs for mental health and disasters, Government commission a longitudinal study on the effect of consecutive disasters on community mental health. |
REC324-4307 | 9 - Community education | Flood education: That, to build disaster resilience in future generations as floods and other natural disasters are a fact of Australian life, the Department of Education should design, implement and deliver an evidence-based, targeted education campaign (like sun exposure) in schools (new disaster curriculum). |
REC324-4306 | 6 - Insurance and legal liability | NSW Reconstruction Authority: That, to provide rapid and effective recovery from floods (and other disasters) and to provide maximum mitigation of the impacts of future floods (and other disasters), Government establish a permanent state-wide agency, the NSW Reconstruction Authority (NSWRA) dedicated to disaster recovery, reconstruction and preparedness. The NSWRA should: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4302 | 32 - Doctrine, standards, and reform | Disaster adaptation plans for all towns: That, to establish realistic expectations of safe spaces to live and deliver much needed housing quickly, Government through NSWRA working with local government: |
REC324-4301 | 32 - Doctrine, standards, and reform | Floodplains as assets: That, to establish the capacity and maximise the economic, social and environmental potential and consequently unlock the value of NSW floodplains, Government adopt the following guiding principles for floodplain management: |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2393 | 15 - Inter-service cooperation | In recognising the success of the work of both the volunteer based Rural Fire Service and the full time Fire and Rescue NSW (FRNSW) members in joint operations – both agencies should be represented at major briefings or press conferences to reinforce successful integrated collaborative efforts rather than individual agency achievements |
REC302-2394 | 15 - Inter-service cooperation | Take immediate steps to eliminate fire boundaries for call and dispatch purposes to create an agnostic approach to the threat of fires from both a departmental and organisational perspective |
REC302-2395 | 32 - Doctrine, standards, and reform | Remove those policies, guidelines, memoranda of understanding and committees that are made redundant as a result of adopting recommendation #2 while updating any remaining policies that are considered to still be relevant |
REC302-2396 | 15 - Inter-service cooperation | The Commissioners of Fire and Rescue NSW (FRNSW) and the RFS issue an instruction to FRNSW ComCen that while AVL capability is being made available to the RFS vehicle fleet, no offers of assistance by one agency to the other in combatting a fire is rejected or delayed if what is being offered is appropriate |
REC302-2397 | 12 - EM agency and authority | Use the model and system in place at the Ambulance Service of NSW as a benchmark for call taking, dispatch and the provision of situational awareness when deploying resources. This will overcome the lack of a feedback loop in current bushfire operations |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
REC302-2400 | 15 - Inter-service cooperation | Until a single call centre is developed, continue deployments of a senior RFS officer to Fire and Rescue NSW ComCen on a 24/7 day basis. This arrangement should determine the quickest most suitable resource and who is ‘in charge’ of an incident |
REC302-2401 | 12 - EM agency and authority | While the proposal to establish an integrated call and dispatch centre is being implemented, Fire and Rescue NSW should take steps to civilianise ComCen and maintain experienced senior officers from both agencies as supervisors similar to how the NSW Police Force and Ambulance Service of NSW operate |
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2403 | 12 - EM agency and authority | Take steps to ensure that both fire commissioners are seeking opportunities to engender a culture in their respective organisations that seeks to attract and foster the volunteer ethos and experience |
REC302-2404 | 8 - Communications and warnings | Review the effectiveness of emergency public information arrangements, and give consideration to embedding an ABC Manager (not a journalist) into the RFS headquarters during emergencies to broadcast warnings to the community that can be pooled to commercial media outlets |
Rec-ID | Code | Recommendation |
---|---|---|
REC279-1227 | 36 - Volunteers | Improve Analysis and Reporting: By December 2014, improve analysis and reporting on management information about volunteers, including: a) numbers, contribution, skills, profile, availability and turnover b) reasons for joining and leaving c) gaps in data completeness and quality This should enable SES to demonstrate an improvement in the completeness and accuracy of management information by April 2015 |
REC279-1228 | 36 - Volunteers | Volunteer Workforce Plan: By December 2014, develop a volunteer workforce plan to focus resources for recruitment and retention on areas of greatest need. The plan should be based on regional capability plans that assess in a consistent way: a) how many volunteers they have and need b) the gaps and risks around volunteer numbers, skills and training |
REC279-1229 | 12 - EM agency and authority | Recruitment Guidelines and Resources: By April 2015, update its recruitment guidelines and resources, and support units in better targeting recruitment |
REC279-1230 | 36 - Volunteers | Volunteer Retention: By April 2015, develop strategies and resources to improve volunteer retention, including: a) induction and development of leaders b) health checks for units to identify and address areas for improvement c) pathways for volunteers to take on greater responsibility d) consultation and communication e) recognition for volunteers and their employers |
REC279-1231 | 16 - Training and behaviour | Training Strategy: By April 2015, develop a training strategy that identifies volunteer training priorities and provides for ongoing review to ensure operational currency, flexibility of delivery and evaluation |
REC279-1232 | 16 - Training and behaviour | Volunteer Charter: by December 2014, agree a charter with volunteers that clarifies roles and expectations including commitments by: a) SES to support volunteers to prepare for and respond to emergencies b) SES to make the best use of volunteers’ time by introducing user-friendly systems and reducing the administrative burden on them c) volunteers to turn-out when called to respond to emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC266-1534 | 21 - Role of Commonwealth Government | The Australian National Audit Office (ANAO) recommends that the Attorney‐General’s Department significantly improve the administration of disaster relief and recovery funding by: |
REC266-1535 | 21 - Role of Commonwealth Government | To provide improved oversight and assurance in its administration of the Natural Disaster Relief and Recovery Arrangements, the Australian National Audit Office (ANAO) recommends that the Attorney‐General’s Department: |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
REC258-2527 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development plays a stronger policy role in the State Safety Program. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2529 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority utilise the provision in their bilateral Memorandum of Understanding to accredit CASA observers to ATSB investigations. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2531 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority’s Board exercises full governance control. The nonexecutive directors should possess a range of appropriate skills and backgrounds in aviation, safety, management, risk, regulation, governance and government. |
REC258-2532 | 12 - EM agency and authority | The next Director of Aviation Safety has leadership and management experience and capabilities in cultural change of large organisations. Aviation or other safety industry experience is highly desirable. |
REC258-2533 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority: |
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
REC258-2535 | 32 - Doctrine, standards, and reform | Airservices Australia, in conjunction with the Department of Infrastructure and Regional Development and the Civil Aviation Safety Authority, reconsiders the policy on ‘Assessment of Priorities’ that stipulates that air traffic controllers sequence arriving aircraft based on category of operation, rather than on the accepted international practice of ‘first come, first served’. |
REC258-2536 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority amend the wording of their existing Memorandum of Understanding to make it more definitive about interaction, coordination, and cooperation. |
REC258-2537 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority delegates responsibility for the day-to-day operational management of airspace to Airservices Australia, including the designation of air routes, short term designations of temporary Restricted Areas, and temporary changes to the classification of airspace for operational reasons. |
REC258-2538 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development and Department of Defence (and appropriate agencies) establish an agreed policy position on safety oversight of civil operations into joint user and military airports. |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2545 | 12 - EM agency and authority | The Australian Transport Safety Bureau transfers its safety education function to the Civil Aviation Safety Authority. |
REC258-2546 | 12 - EM agency and authority | The Civil Aviation Safety Authority changes its organisational structure to a client-oriented output model. |
REC258-2547 | 12 - EM agency and authority | The Civil Aviation Safety Authority establishes small offices at specific industry centres to improve monitoring, service quality, communications and collaborative relationships. |
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2553 | 12 - EM agency and authority | The Civil Aviation Safety Authority establishes a safety oversight risk management hierarchy based on a categorisation of operations. Rule making and surveillance priorities should be proportionate to the safety risk. |
REC258-2554 | 32 - Doctrine, standards, and reform | Recreational Aviation Administration Organisations, in coordination with the Civil Aviation Safety Authority, develop mechanisms to ensure all aircraft to be regulated under CASR Part 149 are registered. |
REC258-2555 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority changes the current two-tier regulatory framework (act and regulations) to a three-tier structure (act, regulations and standards), with: |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2558 | 12 - EM agency and authority | The Civil Aviation Safety Authority applies a project management approach to the completion of all Civil Aviation Safety Regulation Parts not yet in force, with drafting to be completed within one year and consultation completed one year later, with: |
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
REC258-2560 | 29 - Operational Health and Safety | The Civil Aviation Safety Authority devolve to Designated Aviation Medical Examiners the ability to renew aviation medical certificates (for Classes 1, 2, and 3) where the applicant meets the required standard at the time of the medical examination. |
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
REC258-2562 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority amends the current Terms of Reference of the Industry Complaints Commissioner so that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1536 | 16 - Training and behaviour | The Australian defence Force Explosive Ordnance Disposal course be reviewed by Manager Joint Training - Air Force, to ensure the assessments meet the learning outcomes specificed in the relevant Training Management Package. |
REC257-1537 | 32 - Doctrine, standards, and reform | Commanding Officer Defence Explosive Ordnance Training School review and enforce Standard Operating Procedures to ensure that appropriate explosive ordnance accounting and handling practices, in accordance with Defence doctrine, are adhered to during all training activities. |
REC257-1538 | 32 - Doctrine, standards, and reform | Commanding Officer Defence Explosive Ordnance Training School amend relevant instructions, both generally and specifically, so as to ensure that explosive ordnance used in training serials is logged in real time, in accordance with extant doctrine. |
REC257-1539 | 25 - Inquiry, audit, lessons management and after action review | Defence Security Authority conduct an investigation into the whereabouts of items of anaccounted explosive ordnance issued to Defence Explosive Ordnance Training School Exercise Marrangaroo. |
REC257-1540 | 16 - Training and behaviour | Commanding Officer Defence Explosive Ordnance Training School, assisted by Joint Logistics Command Regional Explosive Ordnance Serices staff, conduct explosive ordnance accounting training for all instructional staff as a matter of priority and that such training be conducted for Defence Explosive Ordnance Training School staff on an annual basis. |
REC257-1541 | 17 - Assets and technology | A Stryker unit, or an upgraded firefighting unit, be present at the range sentry point, remain manned and ready to deploy during range activites, with its driver in direct radio contact with the Range Safety Officer. Upon the range being declared clear by the Safety Officer inspecting the range after a demolition serial, the firefighting unit must proceed forward to the range wile the periphery of the range continues to be inspected by the Safety Officer, and remain on the range until the Safety officer declares that the area is clear of fire or that it is otherwise appropriate for the fireghting unit to leave the range area. |
REC257-1542 | 17 - Assets and technology | Firefighitng capability at Marrangaroo Training Area be upgraded so that Australian Defence Force members are not placed in situations of unacceptable risk. Specifically, those participating in range practices must have access to a firefighting vehicle close by and easily deployed, and capable of throwing a large quantity of water an appreciable distance into areas adjacent to the ranges, should a fire occur. |
REC257-1543 | 32 - Doctrine, standards, and reform | Range Standing Orders be amended to include a direction that no Defence vehicle is to leave the administration area of Marrangaroo Training Area during a bushfire, except to leave Marrangaroo Training Area itself through the main gate, unless it is a properly equipped bushfire fighitng vehicle havig at least four wheel drive capabiliy and self-protection equipment. |
REC257-1544 | 17 - Assets and technology | Defence should not procure any firefighting vehicle for Marrangaroo Training Area without first consulting relevant personnel within the Rural Fire Service on an appropriate type of vehicle, and obtaining training for the personnel proposed to use it. Alternatively, Defence should explore contracted firefighitng support during periods of live-fire on Marrangaroo Training Area. |
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
REC257-1546 | 25 - Inquiry, audit, lessons management and after action review | Defence undertake a review of its ability to respond to a fire within Marrangaroo Training Area, whether bushfire or structural. The underlying assumption should be that the only response available to fight a fire within Marrangaroo Training Area will be provided by Defence. Further, such response must occur while a fire is in its initial stages. A review must either acknowledge the risk of fire occurring in th future, or upgrade Defence's firefighting capability at Marrangaroo Training Area. |
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
REC257-1548 | 25 - Inquiry, audit, lessons management and after action review | The Regional Director-Defence Support-Northern NSW, make contact with Deputy Commissioner ~~~~~ Director of Operational Services Rural Fire Service, to arrange a headquarters driven bipartite review of the events of 16 October 2013 with a review to mitigation of future fire events generally, and with specific reference to: |
REC257-1549 | 32 - Doctrine, standards, and reform | Marrangaroo Training Area Range Standing Orders should be reviewed to impose a requirement that the Officer in Charge of any live-firing practice ascertain and consider current weather parameters, temperature, humidity, wind strength and direction, registered at Mt Boyce immediately prior to any demolition serial. The setting of those parameters and their limits should be decided in consulation with the Bureau of Meteorology and Rural Fire Service and inserted into Range Standing Orders. |
REC257-1550 | 32 - Doctrine, standards, and reform | Defence engage with both the Bureau of Meteorology and the Rural Fire Service to determine a more suitable index system. In the interim, Range Standing Orders be amended so that live-firing on the ranges on Marrangaroo Training Area not be permitted where the Forest Fire Danger Index for either the Central Ranges District or Greater Sydney Region is 12, it being the threshold for HIGH Fire Danger Rating or above. put another way, and in a practical sense, Range Standing Orders should, as an interim measure, require the Officer in Charge Practice and the Range Control Officer to consider the Forest Fire Danger Index for both Central Ranges District AND Greater Sydney Region on the day of any given serial. If either index is as 12 or above, live-firing should not be permitted. Any indication in Range Standing Orders or elsewhere that live-firing is permitted on Marrangaroo Training Area when the Fire Danger rating is HIGH should be rescinded. |
REC257-1551 | 32 - Doctrine, standards, and reform | The use of Internal and External ranges at MTA for patrolling activities be prohibited. |
REC257-1552 | 32 - Doctrine, standards, and reform | Authority be given to the regional Environmental Officer to close a range or impose live-firing restriction in addition to any set out in Range Standing Orders if circumstances so warrant. |
REC257-1553 | 32 - Doctrine, standards, and reform | On matters relating directly to safety or risk, or when live-firing may occur, where there is ambiguity or apparent inconsistency, the most conservative or restrctive order should be followed until formal clarification has been provided. |
REC257-1554 | 32 - Doctrine, standards, and reform | All documents be reviewed to remove ambiguity and perceived inconsistencies. Marrangaroo Training Area Range Standing Orders be subject to further examination, with particular consideration of the bushfire mitigation strategies referred to in the Bushfire Management Plan 2011-2014 before amendments to Chapter 10 are made. the basis upon which Range Standing Orders might fix a cut-off point for live-firing exercises should depend on continued bushfire strategies. Range Standing orders and Marrangaroo Training Area Bushfire Management Plan be reviewed annually. if hazard reduction has not occurred or the fire trails degraded, Range Standing Orders should take into account of heightened risk. |
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1561 | 24 - Govt responsibility | State and territory governments should be required to report on the following accountability requirements: |
REC256-1562 | 32 - Doctrine, standards, and reform | The Australian Government should: |
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1566 | 24 - Govt responsibility | State and territory governments should prioritise and accelerate implementation of the Enhancing Disaster Resilience in the Built Environment Roadmap, including reviewing the regulatory components of vendor disclosure statements. The Land Use Planning and Building Codes Taskforce should be tasked to identify and consider options for regular, low-cost dissemination of hazard information to households by governments and insurers. |
REC256-1567 | 24 - Govt responsibility | State and territory governments should: |
REC256-1568 | 24 - Govt responsibility | State governments, where they have not already done so, should provide local governments with statutory protection from liability for releasing natural hazard information and making changes to local planning schemes where such actions have been taken ‘in good faith’ and in accordance with state planning policy and legislation. |
REC256-1569 | 32 - Doctrine, standards, and reform | The provisions in the Queensland Sustainable Planning Act 2009 for injurious affection should be repealed. |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
REC256-1571 | 24 - Govt responsibility | State and territory taxes and levies on general insurance should be phased out and replaced with less distortionary taxes. |
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
REC256-1574 | 32 - Doctrine, standards, and reform | The Australian Government should establish a framework for the development of benchmark prices for the reconstruction of essential public assets. This should set out the broad parameters that state and territory governments should follow, without prescribing particular prices to be used. |
REC256-1575 | 24 - Govt responsibility | State and territory governments should develop benchmark prices for the reconstruction of essential public assets and submit these to the Australian Government for approval within one year. In developing these prices, they should consult with local governments and relevant experts, and draw on asset management plans. The prices should be reviewed and updated over time. |
REC256-1576 | 21 - Role of Commonwealth Government | Within three years, the Australian Government should develop and implement a framework for untied grants for community recovery assistance to state and territory governments. This framework should take into account factors such as the type, location and scale of a disaster, and the number of people affected. |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC255-1578 | 32 - Doctrine, standards, and reform | The ANAO recommends that the Department of Defence review the minimum information necessary to be reported for each emergency DACC task to discharge accountability obligations, identify costs, undertake cost recovery where appropriate, maintain records for future use and learn from emergency DACC activities |
REC255-1579 | 38 - Agency/Department Reporting | The ANAO recommends that the Department of Defence take steps to strengthen the priority afforded by Defence units to meeting these reporting requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0817 | 32 - Doctrine, standards, and reform | That section 3(c) of the Rural Fires Act 1997, which sets out the objects of the Act, be extended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0818 | 32 - Doctrine, standards, and reform | That section 9(4)(b) of the Rural Fires Act 1997, which sets out the functions of the NSW Rural Fire Service, be amended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0819 | 32 - Doctrine, standards, and reform | That section 56 of the Rural Fires Act 1997 be amended to give the Commissioner of the NSW Rural Fire Service the power to direct a Bush Fire Management Committee to amend its Bush Fire Risk Management Plan if it is inadequate, in the opinion of the Commissioner. |
REC237-0820 | 32 - Doctrine, standards, and reform | That the Rural Fires Act 1997 be amended to allow the Commissioner of the NSW Rural Fire Service to carry out hazard reduction on land without the consent of the owner after reasonable attempts to contact the landowner have failed, without serving a notice under section 66 of the Rural Fires Act. |
REC237-0821 | 32 - Doctrine, standards, and reform | That the definition of “bush fire hazard reduction work” in the Dictionary of the Rural Fires Act 1997 be amended to include the establishment or maintenance of fire trails. |
REC237-0822 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report to the Commissioner of the NSW Rural Fire Service within one month of the end of the financial year on activities undertaken to reduce bush fire hazards on managed land during the preceding financial year. |
REC237-0823 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report monthly to the Commissioner of the NSW Rural Fire Service on activities undertaken to reduce bush fire hazards on managed land during the preceding month and the reasons why any planned activities did not take place. |
REC237-0824 | 32 - Doctrine, standards, and reform | That section 100I of the Rural Fires Act 1997 be amended to allow hazard reduction certificates to be issued for annual low impact works for a period of three years, where appropriate. |
REC237-0825 | 1 - Land-use and building regs | That the NSW Rural Fire Service hold discussions with the Department of Planning and Infrastructure and Local Government NSW on ways to improve compliance with development consents under section 76A of the Environmental Planning and Assessment Act 1979. |
REC237-0826 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service hold discussions with the Commonwealth Department of Sustainability, Environment, Water, Population and Communities about hazard reduction and roadside vegetation, including potential changes to the NSW Bush Fire Environmental Assessment Code. |
REC237-0827 | 32 - Doctrine, standards, and reform | The Panel notes and endorses the NSW bush fire management system based on a multi-agency, tenure blind approach using locally focused Bush Fire Management Committees, Bush Fire Management Plans and the Bush Fire Environmental Assessment Code as best practice. |
REC237-0828 | 9 - Community education | That the NSW Rural Fire Service develop a strategy to better inform the community and NSW Rural Fire Service members about the NSW bush fire management system and its components. |
REC237-0829 | 9 - Community education | That Bush Fire Risk Management Plans be posted on the NSW Rural Fire Service website. |
REC237-0830 | 9 - Community education | That Bush Fire Risk Management Plans be tabled at Local Emergency Management Committees for comment. |
REC237-0831 | 32 - Doctrine, standards, and reform | That Bush Fire Management Committees be required to take into account fuel age and fire frequency thresholds when developing Bush Fire Risk Management Plans |
REC237-0832 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service investigate use of appropriate modelling, such as PHOENIX RapidFire and the Bayesian Network analysis, to quantify the level of bush fire risk to critical values and assets. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
Rec-ID | Code | Recommendation |
---|---|---|
REC235-2809 | 32 - Doctrine, standards, and reform | The Australian National Audit Office recommends that the Department of Regional Australia, Local Government, Arts and Sport improve the arrangements for conducting value for money reviews of Victorian reconstruction projects by pursuing amendments to the operating protocol with Victoria to require that, at regular intervals, the Taskforce is provided with information on all reconstruction projects being delivered within the scope of the National Partnership Agreement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2810 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Australian Government Reconstruction Inspectorate and the National Disaster Recovery Taskforce seek to maximise the benefits from their value for money review activities by obtaining more timely and comprehensive information on project progress and completion from the Queensland Reconstruction Authority, to enable the preliminary value for money assessments to be finalised based on the scope and cost of works that were actually delivered (rather than estimates). |
REC234-2811 | 32 - Doctrine, standards, and reform | In order to maximise the envisaged benefits from the Inspectorate’s program of value for money reviews, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce improve the application of the sampling approach to make it more representative of the |
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
REC234-2813 | 38 - Agency/Department Reporting | To strengthen its oversight of Queensland reconstruction progress, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC231-2829 | 32 - Doctrine, standards, and reform | The Australian National Audit Office (ANAO) recommends that the Department of Regional Australia, Local Government, Arts and Sport, in preparation for the forthcoming reviews of the National Partnership Agreements, identify the most effective means of obtaining the project level information on the respective reconstruction programs required by the Agreements to be reported on and, if appropriate, seek amendments to the Agreements. |
REC231-2830 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Department of Regional Australia, Local Government, Arts and Sport improve its monitoring of the delivery of the Natural Disaster Recovery Work Plans for Queensland and Victoria by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2872 | 21 - Role of Commonwealth Government | Boost the number of frontline meteorologists to build response capacity in regional forecasting centres. |
REC207-2873 | 21 - Role of Commonwealth Government | Boost the Bureau’s flood warning capacity by: |
REC207-2874 | 32 - Doctrine, standards, and reform | Formalise and standardise service levels provided to emergency services. |
REC207-2875 | 32 - Doctrine, standards, and reform | Agree clear allocation of responsibilities to state and local government for flood management, with defined boundaries on the Bureau’s role and: |
REC207-2876 | 21 - Role of Commonwealth Government | Focus the Bureau’s evolving environmental information role on natural hazards in the first instance. |
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2878 | 21 - Role of Commonwealth Government | Complete workforce planning project and succession plans as a matter of urgency. |
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2880 | 32 - Doctrine, standards, and reform | Ensure the Bureau puts in place necessary planning and governance arrangements to develop its bid for capital funding to maintain its critical supercomputing capacity |
REC207-2881 | 17 - Assets and technology | Extend ICT governance arrangements to all applications and subject in-house development to rigorous approval processes. |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
REC207-2883 | 32 - Doctrine, standards, and reform | Start a project to introduce organisational process thinking with a view to standardising processes and product specifications. |
REC207-2884 | 32 - Doctrine, standards, and reform | Focus leadership practices to re-orient culture away from customisation and experimentation and towards reliable, efficient and consistent documented processes |
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
REC207-2886 | 21 - Role of Commonwealth Government | Explore options to limit forecaster intervention in site-specific web forecasts. |
REC207-2887 | 21 - Role of Commonwealth Government | Centralise media services and establish protocols for media activity. |
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2891 | 21 - Role of Commonwealth Government | Cease or reduce the Ionospheric Prediction Service or offer it as a commercial service. |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
REC207-2894 | 21 - Role of Commonwealth Government | Phase out seasonal prediction development and modelling and rely on products generated elsewhere |
REC207-2895 | 21 - Role of Commonwealth Government | Fund delivery of improved seasonal forecasting services by: |
REC207-2896 | 21 - Role of Commonwealth Government | Lower yield options identified by the Bureau: |
REC207-2896 | 21 - Role of Commonwealth Government | Lower yield options identified by the Bureau: |
REC207-2897 | 21 - Role of Commonwealth Government | Additional frontline meteorologists and specialised centres and systems: |
REC207-2898 | 21 - Role of Commonwealth Government | Upgrade to the Bureau’s supercomputing capacity: |
REC207-2899 | 21 - Role of Commonwealth Government | Improved seasonal forecasting capabilities: |
REC207-2900 | 21 - Role of Commonwealth Government | Explore use of social media to enhance data gathering from authorised and informal sources and to disseminate weather information |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1895 | 32 - Doctrine, standards, and reform | Reforms to address barriers to effective climate change adaptation should be assessed on a case-by-case basis to determine whether they are likely to deliver net benefits to the community. This should include consideration of any risks to their implementation. |
REC205-1896 | 24 - Govt responsibility | Australian governments should implement policies that help the community deal with the current climate by improving the flexibility of the economy. This would also build adaptive capacity to deal with future climate change. This includes reforms to: |
REC205-1897 | 9 - Community education | The Australian Government initiative to improve the coordination and dissemination of flood-risk information should proceed in the most cost-effective way, be regularly updated and be expanded over time to encompass other natural hazards. Guidelines to improve the quality and consistency of risk information should also be regularly updated and take climate change into account where feasible. |
REC205-1898 | 24 - Govt responsibility | To help clarify roles and responsibilities of local government for climate change adaptation, the state and Northern Territory governments should publish and maintain a comprehensive list of laws that delegate regulatory roles to local governments. This would assist both state and local governments to assess whether local governments have the capacity to discharge their roles effectively. |
REC205-1899 | 24 - Govt responsibility | Local governments’ uncertainty about their legal liability is a barrier to effective climate change adaptation. State governments should clarify the legal liability of councils with respect to climate change adaptation matters and the processes required to manage that liability. |
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1904 | 24 - Govt responsibility | State and territory taxes and levies on general insurance constitute a barrier to effective adaptation to climate change. State and territory governments should phase out these taxes and replace them with less distortionary taxes. |
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2906 | 21 - Role of Commonwealth Government | In order to improve the effectiveness of National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), with similar benefits for State or Territory regulators, attention should be given to the following actions. |
REC189-2907 | 29 - Operational Health and Safety | a) For the purposes of designing and implementing its regulatory activities, National Offshore Petroleum Safety Authority (NOPSA) should continue to identify priority hazards and risks and their underlying causes, in consultation with the NOPSA Advisory Board and stakeholders (see Theme 9, Stakeholder engagement). |
REC189-2908 | 21 - Role of Commonwealth Government | To ensure that NOPSEMA is in a strong position to perform its functions effectively: |
REC189-2909 | 32 - Doctrine, standards, and reform | Equipping the regulator with a wider range of compliance tools under the legislation should continue to be a policy priority. The aim should be to enhance the regulator’s capacity to secure compliance in an appropriately graduated way. The opportunity should be taken to ensure that the regulator and inspectors can, in appropriate cases, bring proceedings that do not require referral to the Commonwealth Director of Public Prosecutions, such as actions for civil penalties or injunctions. |
REC189-2910 | 21 - Role of Commonwealth Government | NOPSA should: |
REC189-2911 | 29 - Operational Health and Safety | The review team recommend that: |
REC189-2912 | 29 - Operational Health and Safety | The review team recommend that the safety case system be strengthened by including provisions for a design notification scheme along the lines of that under the British Offshore Safety Case Regulations. |
REC189-2913 | 21 - Role of Commonwealth Government | In developing and improving its policies and practices for stakeholder engagement, NOPSA should ensure that: |
REC189-2914 | 32 - Doctrine, standards, and reform | The review team recommend that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3274 | 21 - Role of Commonwealth Government | The Minister should appoint a senior policy adviser to investigate and report on the best means to implement the recommendations contained in this Chapter 3 of this report. |
REC177-3275 | 32 - Doctrine, standards, and reform | Well Operations Management Plan (WOMPs) submitted by licensees to the regulator(s) should continue to be the primary framework document for achieving well integrity. |
REC177-3276 | 32 - Doctrine, standards, and reform | WOMPs should be comprehensive and freestanding, rather than an overarching document cross‐referencing many other documents (although the Inquiry also recommends a freestanding well control manual; this should be a guide to rig and onshore personnel on good oilfield practice). |
REC177-3277 | 32 - Doctrine, standards, and reform | The concept of ‘good oilfield practice’ should be supplemented by the requirement to incorporate into WOMPs non‐exhaustive minimum compliance standards in relation to well control: for example, stipulations as to when BOPs and/or well control systems must be in place and when they can be removed and minimum barrier requirements (a number of other factors that should be stipulated are outlined in other recommendations below). |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3280 | 32 - Doctrine, standards, and reform | Well construction and management plans should include provision for an independent compliance review of well integrity (i) in the event of stipulated triggers; and (ii) at least once in the period between perceived achievement of well integrity and production. The independent compliance review should be undertaken by an expert who is not involved in the day‐to‐day drilling operations. Reviews should be completed in sufficient time to enable results to be implemented in a meaningful manner. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3283 | 32 - Doctrine, standards, and reform | A separate, identifiable barrier manual should be agreed upon and used by licensees, rig operators, and cementing contractors. These manuals should set out best industry practice in relation to achieving and maintaining well integrity. They should describe barrier types, barrier standards, general principles of well integrity, testing and verification methods and technologies, standard operating procedures (including procedures for the capture and communication of relevant information within and between relevant stakeholder entities). Barrier manuals should address blowout control during drilling, completion, re‐entry, tie‐back of casing strings and so on. Barrier manuals should be the subject of expert external review, and should be regularly updated. |
REC177-3284 | 32 - Doctrine, standards, and reform | Memoranda of Agreement should be entered into between operators in relation to provision of emergency assistance in the event of blowouts. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3287 | 38 - Agency/Department Reporting | Licensees should be subject to an express obligation to inform regulators of problems which arise in the course of installing barriers, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3290 | 38 - Agency/Department Reporting | The successful installation of every barrier should be the subject of written verification within and between licensees and rig operators; and should be the subject of explicit reporting to the relevant regulator(s). |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3292 | 32 - Doctrine, standards, and reform | Licensees should be subject to an express obligation to inform regulators of the proposed removal of a barrier, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. Removal of a barrier should not take place without prior written approval of the relevant regulator(s). |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3296 | 32 - Doctrine, standards, and reform | Use of single strings of intermediate casing to penetrate hydrocarbon bearing zones should be carefully risk assessed. Multiple strings of intermediate casing have the advantage of isolating lost circulation zones and sealing off anomalous pressure zones. If intermediate casing is set in a hydrocarbon zone it should be treated as production casing. |
REC177-3297 | 32 - Doctrine, standards, and reform | A minimum of two barriers should be in place at all times (including during batched operations) whenever it is reasonably practicable to do so. |
REC177-3298 | 32 - Doctrine, standards, and reform | Reliance upon one barrier against a blowout must not take place except with the prior written approval of the relevant regulator and then only in a true emergency situation (see below). |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3300 | 32 - Doctrine, standards, and reform | Licensees and rig operators should install an additional barrier whenever (i) there is any real doubt as to the integrity of any barrier; (ii) whenever the risk of flow from a reservoir increases materially in the course of operations; and (iii) where the consequences of a blowout are grave (for example, for reef systems or shorelines). |
REC177-3301 | 32 - Doctrine, standards, and reform | The industry standard of two barriers should be replaced with the concept of ‘two or more barriers’ as a minimum standard. A minimum standard when operations proceed normally should never be regarded as a sufficient standard in other circumstances. |
REC177-3302 | 32 - Doctrine, standards, and reform | Industry, regulators, and training/research institutions should develop standards that address best practices for cementing operations (including liaising, as appropriate, with overseas regulators) with a view to overcoming problems which can effect the integrity of cemented casing shoes, annulus and cement plugs. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3305 | 32 - Doctrine, standards, and reform | Cement integrity should be evaluated wherever practicable by way of cement evaluation tests, rather than relying on pre‐operational calculations of cement and displacement fluid volumes. |
REC177-3306 | 32 - Doctrine, standards, and reform | It should be standard industry practice to re‐test a cemented casing shoe (that is, after WOC) whenever the plugs do not bump or the float valves apparently fail. Standard industry practice should require consideration of other tests in addition to a repeat pressure test. |
REC177-3307 | 32 - Doctrine, standards, and reform | Any indication of a compromised cemented shoe which cannot be resolved with a high measure of confidence should result in the installation of additional well control barrier(s). |
REC177-3308 | 32 - Doctrine, standards, and reform | Volumes of cement used in connection with barrier installation should be calculated with the assistance of a pro‐forma which records all relevant baseline data, which should be verified by onshore personnel. |
REC177-3309 | 32 - Doctrine, standards, and reform | If performance of barrier installation is outsourced by a licensee, the contractor (for example, the cementing company) should be engaged on terms which clearly require the provision of expert advisory services by the contractor with respect to barrier integrity. |
REC177-3310 | 6 - Insurance and legal liability | Consideration should be given to ways to ensure that contractors who are involved in barrier installation (such as cementing companies) have a direct interest in the performance of works to a proper standard. In particular, consideration should be given to (i) preventing contractors from avoiding the economic consequences of negligent installation of barriers; and/or (ii) imposing specific legislative standards of workmanship on contractors with respect to well control (similar to those which presently apply to licensees). |
REC177-3311 | 32 - Doctrine, standards, and reform | Horizontal or high angle penetration of a reservoir should be avoided wherever practicable until such time as the apparent problems associated with the cementing of a casing shoe in these situations are satisfactorily overcome. If a casing string does penetrate a well horizontally or at a high angle, standard practice should be to install two secondary barriers in addition to the cemented casing shoe. |
REC177-3312 | 32 - Doctrine, standards, and reform | The BOP and rig should not move from a well until barrier integrity has been verified. |
REC177-3313 | 32 - Doctrine, standards, and reform | Barriers should not be installed or removed off‐line. The derrick should be located over a well at the time of removal and installation of any barrier. This will enable more decisive action to be taken in the event a problem arises. |
REC177-3314 | 32 - Doctrine, standards, and reform | Secondary barriers (including PCCCs) should only be installed, tested, and removed with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3315 | 32 - Doctrine, standards, and reform | PCCCs should be installed in a timely manner (for example, to prevent corrosion in the MLS apparatus). Non‐installation in order to park a BOP is not acceptable. |
REC177-3316 | 32 - Doctrine, standards, and reform | Wells should be re‐entered with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3317 | 32 - Doctrine, standards, and reform | Any equipment (including PCCCs) used as, or to install, a barrier should be manufactured for that purpose and be generally recognised as fit for purpose. If equipment is designed in‐house by a licensee or rig operator it should not be approved for use unless and until it is subjected to expert external analysis. |
REC177-3318 | 32 - Doctrine, standards, and reform | Manufacturers should be consulted about how to address non‐routine operational problems affecting their well control equipment. |
REC177-3319 | 32 - Doctrine, standards, and reform | Drilling programs dealing with barrier installation should incorporate relevant aspects of manufacturer’s instructions. |
REC177-3320 | 32 - Doctrine, standards, and reform | Any pro‐formas used by licensees, rig operators and contractors for recording information about installation of barriers should explicitly provide for ‘exception reporting’, that is, the form should include provision for recording any unforseen or untoward events which occur in the course of installation. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3322 | 32 - Doctrine, standards, and reform | Batched drilling operations should only be undertaken after careful assessment of the special risks which such operations give rise to; well control must be maintained during the course of batched drilling operations. |
REC177-3323 | 32 - Doctrine, standards, and reform | Where multiple wells are drilled, operations and occurrences at one well must be carefully assessed for any implications with respect to well control at other wells. |
REC177-3324 | 32 - Doctrine, standards, and reform | The mere fact that the rig is over the platform should not be regarded by licensees or regulators as sufficient justification for reliance on only one barrier. The default position should be that producible wells are shut‐in when a rig is moved on and off a platform, or when a drilling unit is moved between wells on a platform. |
REC177-3325 | 32 - Doctrine, standards, and reform | Relevant personnel from licensees and rig operators should meet face to face to agree on, and document, well control issues/arrangements prior to commencement of drilling operations. Well control should be regarded as a so‐called SIMOP to signify its critical importance to both licensees and rig operators, and to ensure that they each take responsibility for achievement and maintenance of well control. |
REC177-3326 | 32 - Doctrine, standards, and reform | Prior to commencement of drilling operations, senior representatives of the licensee and rig operator should exchange certificates to the effect that their respective key personnel and contractors have been informed in writing of agreed well control arrangements. |
REC177-3327 | 32 - Doctrine, standards, and reform | Information relevant to well control must be captured and communicated within and between licensees and rig operators (and relevant third party contractors), in a manner which ensures it comes to the attention of relevant personnel. In particular, protocols should be developed to ensure that changes in shift and hitch do not operate as communication barriers. |
REC177-3328 | 32 - Doctrine, standards, and reform | All communications between on‐rig and onshore personnel relating to well control should be documented in a timely manner. |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3334 | 32 - Doctrine, standards, and reform | Licensees, rig operators, and relevant third party contractors should develop well control competency standards for their key personnel. Wherever possible, the competencies of key personnel should be benchmarked against their roles and responsibilities. |
REC177-3335 | 32 - Doctrine, standards, and reform | Licensees, rig operators and relevant third party contractors should develop well control competency standards for key personnel in other entities involved in well control operations. |
REC177-3336 | 12 - EM agency and authority | Achievement and maintenance of well control should be written into the job responsibilities of key personnel, at every level up to and including CEOs. That is, a functional line of accountability for well control must exist up to, and including, CEOs. |
REC177-3336 | 12 - EM agency and authority | Achievement and maintenance of well control should be written into the job responsibilities of key personnel, at every level up to and including CEOs. That is, a functional line of accountability for well control must exist up to, and including, CEOs. |
REC177-3337 | 12 - EM agency and authority | Supervision/oversight of well control operations (within licensees, rig operators and by regulators) must occur without assuming adherence to good oilfield practice. The opposite assumption should prevail: namely adherence to good oilfield practice may well be compromised by the pursuit of time and cost savings. |
REC177-3338 | 12 - EM agency and authority | Licensees and rig operators should be astute in ensuring that corporate systems and culture encourage rather than discourage raising of well control issues. For instance, do performance bonuses or rewards actually encourage or discourage reporting of issues? Is there a system in place to enable anonymous reporting of well control concerns? What whistleblower protections are in place? |
REC177-3339 | 32 - Doctrine, standards, and reform | The Inquiry supports the objective (rather than prescriptive) approach to regulation now followed in Australia. However, the pendulum has swung too far away from prescriptive standards. In some areas relating to well integrity there needs to be minimum standards. |
REC177-3340 | 32 - Doctrine, standards, and reform | To better ensure that ‘risks’ are identified and managed in accordance with sound engineering principles and good oilfield practice, it is recommended that regulation 25(1)(a)(i) and (2)(a)(i) of the Management of Well Operations Regulations, be reworded as follows: ‘A titleholder must not commence / continue a well activity if…a well integrity hazard exists in relation to the well’. |
REC177-3341 | 32 - Doctrine, standards, and reform | The definition of ‘good oilfield practice’ in the OPGGS Act is unduly narrow. The current definition is incapable of application except where things ‘are generally accepted as good and safe’. The definition should be amended such that ‘good oilfield practice includes…’. |
REC177-3342 | 32 - Doctrine, standards, and reform | Written (rather than verbal) approval from the DA (or new regulator) should be obtained before the commencement of well activities that lead to a physical change of a wellbore, other than in a true emergency situation (requiring amendment to regulation 17 of the Management of Well Operations Regulations). |
REC177-3343 | 32 - Doctrine, standards, and reform | The OPGGS Act should be amended to allow for a power to suspend a petroleum production licence (in addition to the current power to cancel a licence or suspend its conditions). |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3346 | 21 - Role of Commonwealth Government | A single, independent regulatory body should be created, looking after safety as a primary objective, well integrity and environmental approvals. Industry policy and resource development and promotion activities should reside in government departments and not with the regulatory agency. The regulatory agency should be empowered (if that is necessary) to pass relevant petroleum information to government departments to assist them to perform the policy roles. |
REC177-3347 | 21 - Role of Commonwealth Government | The proposal of the Productivity Commission’s Research Report (Review of Regulatory Burden on the Upstream Petroleum (Oil and Gas) Sector, April 2009) to establish a NOPR should be pursued at a minimum. |
REC177-3348 | 21 - Role of Commonwealth Government | Responsibility for well integrity should be moved to NOPSA (as also proposed by the Productivity Commission). |
REC177-3349 | 21 - Role of Commonwealth Government | In the meantime, the Minister should: |
REC177-3350 | 32 - Doctrine, standards, and reform | The recommendations of the Inquiry in relation to suitable ways of achieving well integrity contained in Chapter 3 be included in a guidance manual that is issued for the assistance of industry and regulators. |
REC177-3351 | 21 - Role of Commonwealth Government | In the future, and in the interests of ensuring that all possible well control options are comprehensively pursued to exhaustion, decisions as to well control response options should be the result of collaboration between the regulator and the operator rather than leaving one party to make unilateral judgements as to the appropriateness of various well control operations. The regulator should provide transparent and contemporaneous explanations to the public of all well control options under consideration at any particular time. |
REC177-3352 | 32 - Doctrine, standards, and reform | The regulator, rather than the responsible Minister, should be given the power to direct an operator to use a particular rig for the purpose of well control operations, if appropriate in the circumstances, and the power should be used in the future if that rig is the best option available. This would necessarily involve the operator fully compensating for the use of the rig and any other associated costs. The Inquiry suggests that this power could be invoked and given effect as a condition of an operator’s licence. |
REC177-3353 | 32 - Doctrine, standards, and reform | The regulatory regime should also impose an obligation on an operator to ascertain the availability, and provide details to the regulator, of any potential relief well rigs, prior to the commencement of drilling operations (including prior to each phase of a drilling operation where applicable). |
REC177-3354 | 32 - Doctrine, standards, and reform | NOPSA develop a policy of engagement with operators so as to enable experts (including safety experts) to canvas all available options for well control in the event of a blowout. |
REC177-3355 | 32 - Doctrine, standards, and reform | The Inquiry also supports Bills and Agostini’s recommendation: ‘…in relation to safety case development and compliance overall, that NOPSA revise its approach to interacting with operators prior to the safety case assessment process and subsequently direct more resources into its advisory functions. We further recommend that NOPSA develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on the latest information, including the interaction with the operator’. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3357 | 21 - Role of Commonwealth Government | In any future similar blowout or offshore emergency situation, the Minister appoint (through either a NOPR or the relevant Department) a senior public servant to establish and oversight a central coordinating body that will facilitate interaction between regulators, industry, AMSA and the owner/operator. Primary responsibility for stopping a blowout should remain with the owner/operator but should be subject to direction from the central coordinating body in consultation with stakeholders (including the owner/operator). |
REC177-3358 | 21 - Role of Commonwealth Government | The body established to undertake a central coordination and facilitation role in the event of any future blowout in Commonwealth waters should undertake to make all relevant information publically available from one, authoritative and easy to access source. |
REC177-3359 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed to clarify the arrangements to apply in Commonwealth waters regarding key roles and responsibilities, including in relation to the ESC, in the event of an oil spill. This should also address any necessary training required. |
REC177-3360 | 42 - Culture and Heritage | DEWHA should participate in training programs and exercises relevant to an oil spill in the marine environment. |
REC177-3361 | 32 - Doctrine, standards, and reform | The National Plan should be revised to ensure that it fully comprehends environmental matters and that it recognises the importance of the prompt implementation of Scientific Monitoring to facilitate the assessment of the environmental impacts of an incident. |
REC177-3362 | 32 - Doctrine, standards, and reform | Procedures for the approval of development projects should ensure that conditions of approval are comprehensive and clearly set out the obligations of their proponents in relation to environmental matters (including expected monitoring and remediation obligations). |
REC177-3363 | 32 - Doctrine, standards, and reform | DEWHA, in concert with AMSA and with expert input, should develop ‘off the shelf’ monitoring programs that can be speedily implemented following incidents in Commonwealth waters. In this context, the utility of the current Scientific Monitoring program should be peer reviewed to inform future policy. |
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
REC177-3365 | 6 - Insurance and legal liability | The National Plan should specify that the cost of responding to an oil spill, or other damage to the offshore marine environment, will be totally met by the owner/operator. This would be consistent with the Inquiry’s recommendation for legislative changes to the regulatory framework concerning owner/operators meeting the cost of monitoring and remediation of environmental damage. |
REC177-3366 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed: |
REC177-3367 | 32 - Doctrine, standards, and reform | Procedures and accountabilities should be established to ensure, in the event of a future incident, that: |
REC177-3368 | 32 - Doctrine, standards, and reform | The regulatory framework should provide that in respect of all activities in Commonwealth waters: |
REC177-3369 | 6 - Insurance and legal liability | The obligation of companies involved in an incident to meet the full costs of monitoring and remediation should be made a condition of approval of proposals under the EPBC Act and OPGGS Act. Suitable arrangements (insurance or otherwise) need to be in place to ensure that companies have this capacity. |
REC177-3370 | 32 - Doctrine, standards, and reform | Environment plans and OSCPs should be made publicly available as a condition of approval of proposals under the OPGGS Act, and should clearly set out Scientific Monitoring requirements in the event of an oil spill. |
REC177-3371 | 21 - Role of Commonwealth Government | The Government should examine the scope for a single environment plan to meet the regulatory requirements of both the OPGGS Act and the EPBC Act. This could possibly be achieved by way of bilateral agreements and accreditation arrangements and/or legislative amendment. |
REC177-3372 | 21 - Role of Commonwealth Government | OSCPs should be endorsed by AMSA prior to regulatory approval to ensure that they align with the National Plan. Once field operations commence, the capability of operators should be assessed against their plans, and exercises conducted to ensure the plans remain effective. |
REC177-3373 | 32 - Doctrine, standards, and reform | Arrangements should be developed to minimise duplication between the EPBC Act and the OPGSS Act Environment Regulation. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3375 | 21 - Role of Commonwealth Government | For the purposes of that review, the Minister should issue a ‘show cause’ notice to PTTEPAA under s 276 of the OPGGS Act. |
REC177-3376 | 21 - Role of Commonwealth Government | In carrying out a review of PTTEPAA’s permit and licence, the Minister should have regard to this Report, particularly (i) the adverse findings set out in this Chapter; and (ii) the extent to which PTTEPAA has implemented the Action Plan submitted to the Inquiry, or otherwise addressed the matters canvassed in this Report. |
REC177-3377 | 32 - Doctrine, standards, and reform | The Minister consider legislative amendments to the OPGGS Act which make clear that |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
REC174-2986 | 32 - Doctrine, standards, and reform | The ANAO recommends that Centrelink assess the reliability of emergency recovery payment data and reports generated from its system(s), and update the approach, standards and procedures for the collection, storage and use of the data. |
REC174-2987 | 9 - Community education | To improve customer awareness of the availability of disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0071 | 32 - Doctrine, standards, and reform | SERCon consider the establishment of a body, such as a State Recovery Committee, with responsibility for the |
REC164-0072 | 32 - Doctrine, standards, and reform | SERCon consider that the proposed State Recovery Committee review the recommended considerations arising from |
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
REC164-0074 | 9 - Community education | SERCon consider a review of existing community-based educational programs, with a view to informing the community |
REC164-0075 | 16 - Training and behaviour | SERCon consider development of an education program for other government and non-government agencies (with |
REC164-0076 | 32 - Doctrine, standards, and reform | SERCon consider meeting with the State Emergency Management Committee, Directors General and agency heads to |
REC164-0077 | 32 - Doctrine, standards, and reform | SERCon consider the continued development of a State Recovery Sub-Plan (including complementary local and district |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3023 | 32 - Doctrine, standards, and reform | That the Commonwealth undertake legislative change that will ensure that when any floating facility reverts to a ‘navigable form’, the relevant provisions of the Navigation Act and the OHSMI Act will apply regardless of any voyage criteria. This will help to ensure that all Australian seafarers are covered. |
REC161-3024 | 32 - Doctrine, standards, and reform | That the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996 Regulations be amended to ensure that the safety case for a floating facility specifically identifies when command structure changes occur (which may be well before departing the site and associated zone). We also recommend that the Offshore Petroleum and Greenhouse Gas Storage Act 2006 be amended so that a vessel becomes a facility when any part of it comes within 500 metres of the site and continues to be a facility until no part of the |
REC161-3025 | 32 - Doctrine, standards, and reform | That Australian Maritime Safety Authority should have a role in assuring continuing marine standards that are not inconsistent with Offshore Petroleum and Greenhouse Gas Storage Act 2006 provisions and that Australian Maritime Safety Authority needs defined powers to assist National Offshore Petroleum Safety Authority (NOPSA) in minimising risk in the offshore petroleum industry. Potential mechanisms for achieving this outcome include: providing Australian Maritime Safety Authority with defined powers and obligations under the Offshore Petroleum and Greenhouse Gas Storage Act 2006, thereby ensuring that the Authority becomes an effective inspector/regulator of vessels while they are deemed to be facilities; or revising the current Commonwealth maritime legislation disapplication provisions of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 with the aim of achieving the same goal. If it can be readily achieved and is an efficient regulatory option, we believe the first option is preferable. |
REC161-3026 | 32 - Doctrine, standards, and reform | That the Commonwealth consider a plain English rewrite of the Navigation Act 1912 with the aim of producing a modern, performance-based Act. |
REC161-3027 | 32 - Doctrine, standards, and reform | That powers should be conferred on National Offshore Petroleum Safety Authority to enable it to effectively regulate safety and integrity for all facilities and pipelines in the water and the WA islands which export gas by pipeline. National Offshore Petroleum Safety Authority’s authority should extend to the nearest valve on the mainland above the shore crossing. |
REC161-3028 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources continue to support a duty of care safety case regime for best practice offshore petroleum industry regulation augmented to include regulation of integrity. Since the safety case is at the centre of the duty of care co-regulatory regime, we consider that the requirement for the implementation of the safety case at facilities involved in the exploitation of petroleum resources should be provided for within the Offshore Petroleum and Greenhouse Gas Storage Act 2006 itself. |
REC161-3029 | 32 - Doctrine, standards, and reform | In relation to safety case development and compliance overall, that National Offshore Petroleum Safety Authority revise its approach to interacting with operators prior to the safety case assessment process and subsequently and direct more resources into its advisory functions. We further recommend that National Offshore Petroleum Safety Authority develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on latest information, including the interaction with the operator. Implementation should be reviewed at a senior level within National Offshore Petroleum Safety Authority. |
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
REC161-3031 | 32 - Doctrine, standards, and reform | That National Offshore Petroleum Safety Authority develop a robust risk assessment matrix for use in assessing and responding to the changing risk associated with each facility and the operator. Further, we recommend that National Offshore Petroleum Safety Authority increase auditing frequency and duration to audit each manned facility on average twice per year (covering each staff swing), but more often if the risk matrix indicates this is necessary; and that audits should average several days actually on major facilities. |
REC161-3032 | 32 - Doctrine, standards, and reform | That the Offshore Petroleum and Greenhouse Gas Storage Act 2006 and its subsidiary regulations be amended to enable National Offshore Petroleum Safety Authority to have a broader range of graduated compliance tools including the ability to impose a civil fine on an operator per day of non compliance with an improvement or prohibition notice. Legislation should also be considered that would enable National Offshore Petroleum Safety Authority to make public, with appropriate safeguards, specific information concerning its enforcement actions including the name of the operator, the breach, and the enforcement action required including potential penalties. |
REC161-3033 | 32 - Doctrine, standards, and reform | That the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996 regulations be amended to explicitly enable assessment of safety culture, leadership, and consideration of operator past history, motivation and current capacity in approvals of safety cases. National Offshore Petroleum Safety Authority should be able to audit against these criteria and challenge operators on these issues. |
REC161-3034 | 12 - EM agency and authority | That National Offshore Petroleum Safety Authority critically review its regulatory manning levels based on its current workload and the recommendations for additional areas of focus and increased auditing presented in this Report. To meet these requirements, we estimate that National Offshore Petroleum Safety Authority requires up to 50 inspectors in total plus associated support staff to bring overall staffing from about 55 to 75. RET should help facilitate the necessary ongoing levy funding in consultation with industry. |
REC161-3035 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources liaise with Ministers with environmental and planning responsibilities, and if necessary Council of Australian Governments, to ensure that environmental requirements for oil and gas projects are not imposed subsequent to safety assessments and do not increase the risk of major accident events. |
REC161-3036 | 32 - Doctrine, standards, and reform | That the Commonwealth and States/Northern Territory legislate to establish a properly resourced and empowered independent national safety investigation capacity to investigate serious oil and gas industry (including pipeline) incidents including near miss events that could have led to a major accident event. We further recommend that the regulatory investigatory powers under the Offshore Petroleum and Greenhouse Gas Storage Act 2006 be reviewed in the context of powers for the proposed independent national safety investigator, noting that the regulator must retain those investigatory powers necessary in order to fulfil its legislative functions. |
REC161-3037 | 32 - Doctrine, standards, and reform | We recommend that the Commonwealth undertake legislative change that will ensure that when any floating facility reverts to a ‘navigable form’, the relevant provisions of the Navigation Act and the OHSMI Act will apply regardless of any voyage criteria. This will help to ensure that all Australian seafarers are covered. |
REC161-3038 | 32 - Doctrine, standards, and reform | We recommend that the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations (MOSO) be amended to ensure that the safety case for a floating facility specifically identifies when command structure changes occur (which may be well before departing the site and associated zone). We also recommend that the OPGGS Act be amended so that a vessel becomes a facility when any part of it comes within 500 metres of the site and continues to be a facility until no part of the vessel remains within 500 metres of the site. |
REC161-3039 | 32 - Doctrine, standards, and reform | We recommend that AMSA should have a role in assuring continuing marine standards that are not inconsistent with Offshore Petroleum and Greenhouse Gas Storage Act (OPGGS) Act provisions and that AMSA needs defined powers to assist NOPSA in minimising risk in the offshore petroleum industry. Potential mechanisms for achieving this outcome include: providing AMSA with defined powers and obligations under the OPGGS Act, thereby ensuring that the Authority becomes an effective inspector/regulator of vessels while they are deemed to be facilities; or revising the current Commonwealth maritime legislation disapplication provisions of the OPGGS Act with the aim of achieving the same goal. If it can be readily achieved and is an efficient regulatory option, we believe the first option is preferable. |
REC161-3040 | 32 - Doctrine, standards, and reform | We recommend the Commonwealth consider a plain English rewrite of the Navigation Act 1912 with the aim of producing a modern, performance-based Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC160-3041 | 21 - Role of Commonwealth Government | To improve the governance arrangements for business continuity management (BCM) in Centrelink ,the Australian National Audit Office (ANAO) |
REC160-3042 | 38 - Agency/Department Reporting | In order to identify key business processes and provide for the regular comparative assessment of Maximum Allowable Outage periods (MAOs), the ANAO recommends that Centrelink: |
REC160-3043 | 21 - Role of Commonwealth Government | The ANAO recommends that Centrelink develop and promulgate a business continuity plan (BCP) template and require business units to develop BCPs that identify: |
REC160-3044 | 38 - Agency/Department Reporting | The ANAO recommends that the Business Continuity, Crisis Management and Security Sub committee: |
REC160-3045 | 38 - Agency/Department Reporting | The ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3128 | 29 - Operational Health and Safety | National Offshore Petroleum Safety Authority (NOPSA) should develop guidelines in consultation with stakeholders to provide clarity and consistency to the process which ultimately will result in better safety outcomes. |
REC149-3129 | 32 - Doctrine, standards, and reform | The consequences of the disapplication of the Navigation Act 1912 should be analysed, the actual consequences identified and unintended consequences addressed. |
REC149-3130 | 32 - Doctrine, standards, and reform | The regulations pertaining to vessels of opportunity or their interpretation should be changed to facilitate a risk based approach to regulation. This approach will be consistent with the approach taken in other jurisdictions. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3134 | 32 - Doctrine, standards, and reform | Improved and agreed guidelines for Safety Case application and assessment, including suggested structure and content, would alleviate many current problems related to Safety Case processes. |
REC149-3135 | 29 - Operational Health and Safety | The initial acceptance of a new facility Safety Case should be in conjunction with inspection of a facility upon commencement of operations. |
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
REC149-3138 | 38 - Agency/Department Reporting | The current KPI measures used by the Regulator and industry need to be reassessed and the performance indicators need to be related to the risk profiles of the industry. The industry needs to develop the indicators, which need to be agreed and measured by the industry in discussion with other stakeholders. The KPI's selected should be published in comparison with the worldwide offshore industry and with other industries. NOPSA should continue discussions with Australian Safety and Compensation Council (ASCC) with a view to adopting their goals. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3140 | 32 - Doctrine, standards, and reform | The industry should provide advice to NOPSA on where the regulations do not provide sufficient clarity and consider developing broad policy/process guidelines in consultation with the regulator to provide clarity and consistency. Regulators should not take personal views or preferences. |
REC149-3141 | 32 - Doctrine, standards, and reform | NOPSA should complete the next revision of Safety Case guidelines in consultation and agreement with stakeholders and continue its program to achieve consistency with a firmer hand from the CEO and management. |
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
REC149-3143 | 21 - Role of Commonwealth Government | The role of the advisory Board, namely to give advice to Ministers and NOPSA when asked, should be made clear to Board members and all stakeholders. The Board and NOPSA should consider the need for a clear description of who does what based on the legislated responsibilities of the NOPSA CEO. |
REC149-3144 | 29 - Operational Health and Safety | The Safety Case proponent should be allowed some flexibility to involve appropriate experience matched with the proposed workforce competencies to enable the Safety Case to be developed with value adding processes. Subsequent to the hiring of the workforce Final Government Response Offshore Petroleum Safety Regulation Inquiry and 2008 Review of NOPSA Operational Activities and preferably before the commencement of operations a review of the Safety Case should take place with the new workforce to ensure they understand the accepted Safety Case, its risks and Safety Management Plan. |
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3147 | 29 - Operational Health and Safety | As all stakeholders have responsibility for safe outcomes, decisions regarding target subjects for safety promotion need to have the support of all stakeholders including NOPSA and the workforce. Industry, which ultimately has the responsibility for managing risk as well as funding the promotion, should take a leadership role in implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3186 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that, in order to assist management decision making and to inform Parliament about performance, Emergency Management Australia (EMA) develop and report appropriate measures for its key emergency management activities and outcomes. |
REC147-3187 | 16 - Training and behaviour | The ANAO recommends that, in order to maximise the benefit of emergency management training activities, EMA review periodically its approach to delivering individual training courses, to ensure the most appropriate delivery mechanism is used commensurate with training objectives. |
REC147-3188 | 12 - EM agency and authority | The ANAO recommends that EMA maintain the Internet site to ensure that material is appropriate, current and readily accessible for users. |
REC148-3189 | 37 - Funding | The ANAO recommends that, to ensure that grant conditions are satisfied, EMA enhance procedures to monitor the progress of projects and follow up those behind schedule or not fulfilling funding agreement requirements. |
REC147-3190 | 32 - Doctrine, standards, and reform | The ANAO recommends that, to facilitate EMA’s response to requests for assistance in overseas emergency management situations, a statement of the broad principles, responsibilities and performance expectations to apply when EMA is involved in overseas operations be developed and agreed between EMA, DFAT, AusAID and other relevant stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC134-3519 | 32 - Doctrine, standards, and reform | The Australian National Audit Office (ANAO) recommends that the Department of Agriculture, Fisheries and Forestry and Animal Health Australia review: |
REC134-3520 | 21 - Role of Commonwealth Government | To improve the management of the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing incorporate into its governance framework: |
REC134-3521 | 32 - Doctrine, standards, and reform | To improve the management of the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing develop and implement procedures for: |
REC134-3522 | 32 - Doctrine, standards, and reform | To improve the effectiveness of deployment arrangements for the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing: |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3620 | 35 - Business and Industry in relation to industry | We recommend that NSW Health continue with its good work and conclude agreements with private health providers specifying roles, and expectations in the case of an infectious disease pandemic. |
REC129-3621 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and establish a time table to finalise all emergency and contingency plans. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3623 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and apply the lessons learnt from Exercise Cumpston to further improve preparedness for major infectious disease emergencies. |
REC129-3624 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and formally establish and oversight a comprehensive program of training, testing and evaluation of plans at the state, area and facility level. |
REC129-3625 | 38 - Agency/Department Reporting | We recommend that NSW Health continue with its good work and establish a performance management framework with targets and indicators to assess progress in preparing for infectious disease emergencies. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3627 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test its surveillance systems for early detection of infectious diseases. |
REC129-3628 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test the capability of its contact tracing system to deal with a public health emergency. |
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
REC129-3630 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and continue to develop systems to bring all the information relevant to the surge in demand for health resources together in real time. |
REC129-3631 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and continue to develop plans to respond to the surge in demand for diagnostic tests and for laboratory personnel. |
REC129-3632 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and develop distinct surge capacity plans within each Area Health Service to manage emergency staffing needs, isolation facilities, intensive care units, assisted ventilation services, hospital beds and medical supplies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3650 | 16 - Training and behaviour | Staff at the Rail Management Centre (RMC) should receive training from RailCorp to enable them to quickly and accurately assess that an emergency has occurred and to provide precise and reliable information to emergency response personnel about the location of the emergency, the available access to the site and the resources necessary. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3654 | 16 - Training and behaviour | All train guards should be trained by RailCorp in the use of the Metronet radio and instructed to use it in any emergency. |
REC121-3655 | 32 - Doctrine, standards, and reform | Procedures should be put in place by RailCorp to ensure that electrical power supply to the area of an accident can be immediately isolated, if necessary, in the event of a rail accident, so as to reduce any risk of exposure of emergency response personnel to injury or harm. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3658 | 12 - EM agency and authority | All emergency services stations should be provided with access keys to, and maps showing, all gates providing access to RailCorp tracks within their geographic area of responsibility. |
REC121-3659 | 32 - Doctrine, standards, and reform | A railway disaster plan, or rail displan, should be developed by RailCorp and the emergency services to ensure co-ordinated inter-agency response to rail accidents and incidents on the RailCorp network. |
REC121-3660 | 32 - Doctrine, standards, and reform | The rail displan should include the use by all emergency response personnel of a uniform incident command system, involving procedures for such matters as the establishment of inner and outer perimeters, control of access to the site, orderly evacuation of injured passengers and the establishment of a staging area remote from the accident site, in a unified command structure with the site controller co-ordinating the various emergency services through representatives of each service. |
REC121-3661 | 32 - Doctrine, standards, and reform | The rail displan should include provision for the appointment of a rail emergency management co-ordinator at the RMC, and an on-site rail commander with the sole function of assisting and supporting the emergency services during the rescue phase of the emergency response. |
REC121-3662 | 32 - Doctrine, standards, and reform | The rail displan should provide for the site controller to have complete control of the site, with other agencies co-ordinating with and supporting him or her, until the rescue phase of the emergency response has been completed. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3664 | 20 - Role of police | The location of the command post for site control at the scene of any rail accident should be identified by NSW Police by a distinctive flashing light. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3667 | 32 - Doctrine, standards, and reform | RailCorp should develop and implement an emergency response plan for management of all rail accidents. Such a plan should be subsumed by the rail displan in the case of serious accidents or incidents. |
REC121-3668 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include action checklists of the steps that each employee is required to take, and the order for specific employees to follow in case of emergency. |
REC121-3669 | 16 - Training and behaviour | All operational rail staff should be trained by RailCorp in the action check list relevant to each. |
REC121-3670 | 16 - Training and behaviour | The RailCorp emergency response plan should be provided to all emergency response agencies. The officers of each emergency service should be trained in any rail specific features of the plan, so as to better ensure inter-agency co-ordination in the circumstances of an emergency. |
REC121-3671 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include a requirement for the debriefing of all senior rail and emergency response personnel involved in any rail accident, so as to determine the way or ways in which emergency response arrangements for rail accidents can be continually improved, and thereafter implement such improvements. |
REC121-3672 | 16 - Training and behaviour | All emergency response personnel should be specifically trained in the features of railways which are relevant to their work, such as the location and means of operation of all emergency door releases on trains, the location and use of signal telephones, the methods by which electrical power can be isolated and the means by which they can readily identify and obtain information from the on-site rail commander. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3674 | 32 - Doctrine, standards, and reform | Uniform verbal descriptions identifying that power has been isolated should be developed by RailCorp and utilised by all railway personnel, electrical service providers and all emergency response personnel. |
REC121-3675 | 16 - Training and behaviour | All rail employees should be trained by their employer to commence any emergency communication with the words “Emergency, emergency, emergency”, thereafter to identify themselves, the train, its location, what has occurred, the approximate passenger load and whether death or injuries have occurred. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3677 | 16 - Training and behaviour | A training centre for emergency services personnel should be established by RailCorp. The emergency services personnel should be required to undertake training at such a centre, which should be equipped with features replicating railway infrastructure and rolling stock. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3679 | 32 - Doctrine, standards, and reform | The rail safety regulator should set standards for the design, manufacture, testing and commissioning of rolling stock to ensure that the rolling stock is fit for its purpose. |
REC121-3680 | 29 - Operational Health and Safety | All trains must be fitted with a minimum of two independent engineering defences to minimise the risk of derailment or collision in the event of train driver incapacitation. |
REC121-3681 | 29 - Operational Health and Safety | RailCorp should progressively implement, within a reasonable time, level 2 automatic train protection with the features identified in chapter 8 of this report. |
REC121-3682 | 29 - Operational Health and Safety | All new rolling stock should be designed to be compatible with at least level 2 automatic train protection discussed in chapter 7 of this report. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3685 | 32 - Doctrine, standards, and reform | The ITSRR should impose a standard in relation to the collection and use of data from data loggers. |
REC121-3686 | 32 - Doctrine, standards, and reform | The standard in relation to the collection and use of data from data loggers should provide that such information must be accessed in the circumstances of any accident or incident and can be accessed to monitor driver performance generally. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3688 | 32 - Doctrine, standards, and reform | Communications procedures must be standardised throughout the rail network, so that all railway employees describe the same subject matter in an identical way. |
REC121-3689 | 12 - EM agency and authority | All RMC communications related staff should be selected upon the basis of the ability to convey information clearly, accurately and concisely and to follow strict communications protocols. |
REC121-3690 | 32 - Doctrine, standards, and reform | All communications protocols must be strictly enforced by all accredited rail organisations. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3692 | 32 - Doctrine, standards, and reform | Communications protocols and procedures should be standardised and mandated by regulations making them a condition of accreditation. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3696 | 32 - Doctrine, standards, and reform | Defects reporting, recording and rectification should be integrated with the RailCorp regimes for train maintenance. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3698 | 32 - Doctrine, standards, and reform | No RailCorp train should enter into revenue service or remain in service if, in the opinion of the driver in charge of that train, any defect in it creates a risk of injury. |
REC121-3699 | 32 - Doctrine, standards, and reform | All reported train defects should be certified by a person in a supervisory position in RailCorp as having been rectified. |
REC121-3700 | 12 - EM agency and authority | The RailCorp defects unit should be combined with the passenger fleet maintenance division of RailCorp. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3701 | 32 - Doctrine, standards, and reform | Train inspections should be carried out at the time of stabling RailCorp trains, as well as a part of train preparation prior to entering service. |
REC121-3702 | 29 - Operational Health and Safety | Random alcohol testing should be continued. |
REC121-3703 | 6 - Insurance and legal liability | Alcohol and drug testing should be mandatory for any train driver or guard involved in any accident or incident. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3705 | 32 - Doctrine, standards, and reform | The ITSRR should develop standards for periodic medical examinations which include the following: |
REC121-3706 | 29 - Operational Health and Safety | RailCorp should establish a comprehensive safety document management system. |
REC121-3707 | 29 - Operational Health and Safety | The safety document management system should provide for the distribution of electronic versions of safety documentation to relevant staff. |
REC121-3708 | 12 - EM agency and authority | RailCorp should employ a Chief Safety Information Officer to manage the collection, collation, and dissemination of safety information within RailCorp. |
REC121-3709 | 29 - Operational Health and Safety | RailCorp should provide access to electronic versions of safety documentation for all operational staff at their workplace. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3711 | 29 - Operational Health and Safety | The ITSRR should establish an electronic document control system to enable effective and reliable information to be gathered for monitoring the safety of the New South Wales rail system. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3714 | 16 - Training and behaviour | RailCorp should use its simulators in an interactive manner. |
REC121-3715 | 16 - Training and behaviour | RailCorp should use its simulators to train drivers and guards in methods of dealing with degraded operations on the rail network. |
REC121-3716 | 16 - Training and behaviour | Train driver and guard training should encourage teamwork and discourage authority gradients. |
REC121-3717 | 16 - Training and behaviour | RailCorp must establish a task analysis for particular categories of employees, to identify the specific skills and responsibility of those employees or groups of employees, and thereafter undertake a training needs analysis, to develop the skills required in particular areas. |
REC121-3718 | 16 - Training and behaviour | Training should be based upon a needs analysis, to determine what skills a particular person will require to carry out the tasks of any position safely and efficiently, and instruction and practice, to acquire and demonstrate those skills. |
REC121-3719 | 16 - Training and behaviour | The position of team leader should be created by RailCorp to be responsible for a group of approximately 30 train drivers, with responsibility to ensure that each train driver’s training needs are being met and that any safety concerns of train drivers are being properly addressed. The team leaders are to have direct access to the Chief Executive of RailCorp if any safety concerns they have are not addressed. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3724 | 13 - Mapping and data quality | The ITSRR should establish a data and information management system, containing all data and information that it requires, to continually monitor the safety of the New South Wales rail system. |
REC121-3725 | 13 - Mapping and data quality | The data and information management system should be compatible with any data and information management system established by the ATSB for the designated interstate rail network, provided that the establishment of a compatible system does not reduce the amount or quality of the information obtained by ITSRR below the optimum levels which it needs to conduct trend analysis, and otherwise properly manage the safety of rail operations in New South Wales. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3727 | 32 - Doctrine, standards, and reform | The relevant legislation should be amended to provide expressly that OTSI and the Chief Investigator have the power to initiate a rail accident or incident investigation. |
REC121-3728 | 32 - Doctrine, standards, and reform | Any barriers to communication between OTSI and ITSRR should be removed, so as to ensure that any findings made by OTSI in relation to any investigation it conducts are reported immediately to ITSRR. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3730 | 32 - Doctrine, standards, and reform | Legislation should be enacted and any necessary arrangements made, to enable the ATSB to review any reports of any investigation by a rail organisation or the OTSI into any serious incident or accident in New South Wales. |
REC121-3731 | 29 - Operational Health and Safety | RailCorp should develop a plan to be submitted to ITSRR to address the deficiencies in the safety culture of RailCorp, including: |
REC121-3732 | 29 - Operational Health and Safety | If ITSRR accepts such a plan as an appropriate response to the existing weak safety culture, ITSRR should approve it and monitor the effectiveness of the plan. |
REC121-3733 | 29 - Operational Health and Safety | RailCorp’s approach to occupational health and safety should be proactive and involve the systematic analysis of all current hazards, risks and controls and an assessment of their adequacy to reduce the risk of injury to, or death of, employees to an acceptable level. |
REC121-3734 | 29 - Operational Health and Safety | RailCorp should integrate its management of occupational health and safety into its overall safety management. |
REC121-3735 | 29 - Operational Health and Safety | Risk assessments of occupational health and safety issues by RailCorp should include an analysis of broader public safety risks and not be confined to narrow occupational health and safety issues. |
REC121-3736 | 32 - Doctrine, standards, and reform | The RailCorp passenger containment policy must be abandoned. |
REC121-3737 | 29 - Operational Health and Safety | There must be a minimum of two independent methods of self-initiated emergency escape for passengers from all trains at all times. |
REC121-3738 | 29 - Operational Health and Safety | All passenger trains must be fitted with an internal passenger emergency door release. |
REC121-3739 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must be fitted with external emergency door releases which do not require any special key or other equipment to operate. |
REC121-3740 | 29 - Operational Health and Safety | The internal passenger emergency door release should be fitted with a facility which prevents it from operating unless the train is stationary. |
REC121-3741 | 29 - Operational Health and Safety | The operation of the train doors should have an override facility whereby the train driver or the guard can override an internal passenger emergency door release system if the door release is interfered with when there is no emergency. There should be an alarm, together with an intercom, in the train guard’s compartment so that, if a passenger attempts to initiate an emergency door release, there is an appropriate delay during which time an alarm sounds in the train guard’s compartment and the guard can then, after first attempting to speak via the intercom to the person concerned, if necessary, override the door release, and make an appropriate announcement over the intercom system in the train. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3743 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must have the external emergency door release clearly marked with the words “Emergency Door Release”. |
REC121-3744 | 16 - Training and behaviour | All RailCorp operational personnel should be trained in the location and operation of external emergency door release mechanisms. |
REC121-3746 | 16 - Training and behaviour | All emergency services personnel should be trained in the location and operation of emergency door release mechanisms on all rail cars. |
REC121-3747 | 29 - Operational Health and Safety | All trains should have windows available through which passengers can escape. |
REC121-3748 | 29 - Operational Health and Safety | All new rail cars must have appropriate signage and lighting identifying escape routes in the case of emergency. |
REC121-3749 | 29 - Operational Health and Safety | All new rolling stock must be designed with an area of the roof through which emergency services personnel can access a rail car without encountering wiring or other equipment. That access point must be clearly marked with words such as “emergency services cut here”. |
REC121-3750 | 32 - Doctrine, standards, and reform | ITSRR should initiate and/or participate in the development of a national standard for crashworthiness of all passenger trains. |
REC121-3751 | 16 - Training and behaviour | RailCorp should make it a condition of employment that all level 2 managers have or obtain a formal qualification in system safety management. |
REC121-3752 | 12 - EM agency and authority | RailCorp should establish clear safety accountability statements and reporting lines for all management positions. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3754 | 29 - Operational Health and Safety | The RailCorp Board should ensure that RailCorp has an adequate and integrated safety management system, including adequate systems for risk assessment, clearly defined safety responsibilities and accountabilities for persons holding management positions, and specific performance criteria against which evaluations can be made of safety performance and accountability for safety performance of all managers. |
REC121-3755 | 29 - Operational Health and Safety | The RailCorp Board should require a full review of the safety competence of RailCorp managers to ensure that each has the ability to bring about those safety reforms recommended in this report which are applicable to his or her position. |
REC121-3756 | 16 - Training and behaviour | RailCorp should ensure that where the safety competency of any manager is deficient such manager is required to undertake professional development courses to raise his or her safety competency level to an adequate standard. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3759 | 29 - Operational Health and Safety | A Safety Reform Program Director (hereafter referred to as SRPD), reporting directly to the Chief Executive of RailCorp, should be retained to manage, as head of a Safety Reform Program Office, any safety reform program being undertaken by RailCorp. The SRPD should work with the Chief Executive and senior management to ensure the implementation of an integrated safety management system and the cultural change required. The SRPD must have qualifications suitable for recognition by the Australian Institute of Project Management as a master program director. He or she should report to and be under the control of the Chief Executive, to ensure that the accountability of the Chief Executive is not reduced. The SRPD should co-ordinate and integrate any existing rail safety reform programs and, in consultation with and with the authority of the Chief Executive he or she should: |
REC121-3760 | 32 - Doctrine, standards, and reform | The Advisory Board established under the Transport Legislation Amendment (Safety and Reliability) Act 2003 must be abolished. |
REC121-3761 | 32 - Doctrine, standards, and reform | Legislative changes should be enacted to ensure the complete independence of ITSRR from the Minister for Transport Services. |
REC121-3762 | 32 - Doctrine, standards, and reform | The Chief Executive of ITSRR should have sole accountability and responsibility for the regulation of rail safety in New South Wales. |
REC121-3763 | 32 - Doctrine, standards, and reform | The ITSRR should publish guidelines to be followed by accredited organisations. |
REC121-3764 | 29 - Operational Health and Safety | The ITSRR should not grant accreditation to any rail organisation unless it has an integrated safety management system in accordance with any safety management system regulation and the guidelines published from time to time by ITSRR. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3766 | 12 - EM agency and authority | Staffing arrangements for ITSRR should be reviewed by it to ensure that adequate staff are employed in field positions, actively monitoring the safety of rail operations and compliance with conditions of accreditation. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3769 | 32 - Doctrine, standards, and reform | The ITSRR should continue to participate in the development of a national system for rail safety regulation, provided that any ultimate agreement between the States and Territories and the Australian Government does not produce a safety outcome for New South Wales that is less than would be achieved by the implementation of all the recommendations contained in this report. |
REC121-3770 | 32 - Doctrine, standards, and reform | A safety management system regulation should be promulgated, specifying the requirements of safety management systems in all accredited organisations, using Annexure I to this report as a guide |
REC121-3771 | 32 - Doctrine, standards, and reform | RailCorp should establish an integrated safety management system which includes the following: |
REC121-3772 | 32 - Doctrine, standards, and reform | RailCorp should establish a safety management system containing the 29 elements identified in the SMSEP report which is in volume 2 of this report. |
REC121-3773 | 32 - Doctrine, standards, and reform | The ITSRR should ensure that RailCorp establishes a safety management system containing the 29 elements identified in the SMSEP report, and ensure the ongoing monitoring and improvement of the safety management system established. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3645 | 32 - Doctrine, standards, and reform | It is recommended that the Board: |
REC119-3646 | 32 - Doctrine, standards, and reform | It is recommended that the Board develop response time standards for metropolitan and rural rescue services to guide committees in determining the number, type and location of rescue units (page 25). |
REC119-3647 | 32 - Doctrine, standards, and reform | It is recommended that the Board: |
REC119-3648 | 38 - Agency/Department Reporting | It is recommended that providers supply data to the Board: |
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC118-3642 | 26 - Research | Establish a Regional Centre of Excellence for Tsunamis to focus Australian and international science/research and collaboration on the challenge of understanding tsunamis and mitigating their consequences. |
REC118-3643 | 21 - Role of Commonwealth Government | Consolidate the Australian Government decision to establish an Australian Tsunami Warning System through a long-term government commitment to ensure a sustainable and effective national tsunami warning system beyond the current four-year initiative. |
REC118-3644 | 21 - Role of Commonwealth Government | That the Prime Minister’s Science, Engineering and Innovation Council requests that the Australian Government, through the Australian Emergency Management Committee, develops an effective pathway to incorporate hazard science into emergency management policy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3633 | 38 - Agency/Department Reporting | The ANAO recommends that, to provide better information to contribute to strategic assessments, decisions and reporting, the Attorney-General’s Department, with input and guidance from the Department of the Prime Minister and Cabinet: |
REC117-3634 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter- Terrorism Committee, pursue the adoption of a more strategic approach to determining the National Capability Development Exercise Programme so that: |
REC117-3635 | 15 - Inter-service cooperation | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, seek to create systematic mechanisms for better targeting and evaluating inter- agency coordination within the National Capability Development Exercise Programme and continuous improvement cycle. |
REC117-3636 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in conjunction with the National Counter-Terrorism Committee’s exercise management advisers, explore options for the incorporation of more contemporary and varied testing and training aids in the National Capability Development Exercise Programme. |
REC117-3637 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, pursue a more strategic and systematic approach to the measurement of performance via the National Capability Development Exercise Programme by: |
REC117-3638 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee: |
REC117-3639 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the National Counter-Terrorism Committee, strengthens the reporting on the National Capability Development Exercise Programme through: |
REC117-3640 | 37 - Funding | The ANAO recommends that the Attorney-General’s Department better monitor and account for the expenditure of individual exercise costs under the National Capability Development Exercise Programme, through: |
REC117-3641 | 38 - Agency/Department Reporting | The ANAO recommends that, to ensure the outcomes of evaluations are effectively used to enhance the national counter-terrorism arrangements, the Attorney-General’s Department and the Department of the Prime Minister and Cabinet take appropriate measures to ensure: |