REC321-4214 | 1 - Land-use and building regs | We recommend that DELWP determines which elements of different regional planning approaches are the most effective and implements these across the state. |
REC321-4215 | 1 - Land-use and building regs | We recommend that DELWP develops more holistic bushfire-management planning that focuses on the best mix of risk treatments rather than planned burning alone. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4211 | 1 - Land-use and building regs | We recommend that CFA (in consultation with FRV) improves planning on private land to ensure risk assessments and plans are conducted consistently across public and private land to address state-wide bushfire risk based on where and how they can most effectively reduce risk. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1337 | 19 - Offences | The Government should: |
REC299-1338 | 19 - Offences | The Government introduce an amendment to the Country Fire Authority Act 1958 or other instruments which imposes significant penalties and strengthens enforcement, including via infringement notices, for offences against Total Fire Ban requirements before the 2017‑2018 fire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2037 | 1 - Land-use and building regs | Make property level information on landslide hazards publicly available |
REC286-2087 | 41 - Emergency Management exercises | Develop and exercise Severe Storm Emergency Management Plan. |
REC286-2050 | 1 - Land-use and building regs | Ensure landuse planning and building systems, including appeal mechanisms, are transparent, equitable and integrated at the municipal, State and national levels. |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-2055 | 29 - Operational Health and Safety | Personal protective equipment (masks, gowns, gloves, goggles) – review fit-testing vs fit-checking. |
REC286-1445 | 41 - Emergency Management exercises | Develop, implement, review and exercise inter-agency community evacuation and recovery plans across the State. |
REC286-1474 | 1 - Land-use and building regs | Raised access routes. |
REC286-2023 | 1 - Land-use and building regs | Locate and design new public infrastructure so that it can continue to operate during flood events. |
REC286-2082 | 41 - Emergency Management exercises | Undertake inter-agency severe storm exercises. |
REC286-2046 | 1 - Land-use and building regs | Incentivising safer sites (charge people less rates and discounts for defensive actions by land managers). |
REC286-1471 | 1 - Land-use and building regs | Promote the use of Water Sensitive Urban Design in stormwater systems. |
REC286-2015 | 1 - Land-use and building regs | Build flood capable infrastructure. |
REC286-2061 | 41 - Emergency Management exercises | Review and exercise the Tasmanian Mass Vaccination Plan. |
REC286-2044 | 1 - Land-use and building regs | Develop linkages between landslide risk assessors and building engineers/structural works. |
REC286-1453 | 1 - Land-use and building regs | Review building controls to ensure they are adaptive to changing coastal inundation risks. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2039 | 41 - Emergency Management exercises | Nuance the exercises for flood / dam-break / debris flow to incorporate consideration. |
REC286-2040 | 1 - Land-use and building regs | Further development of Landslide Hazard Banding of the State (MRT). |
REC286-1451 | 1 - Land-use and building regs | Include consideration of coastal inundation in land use planning for new developments and uses. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2025 | 41 - Emergency Management exercises | Exercise heatwave arrangements with a focus on the public administration sector and management of vulnerable people |
REC286-2038 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-2051 | 1 - Land-use and building regs | Establish arrangements to enable the buy-back of specified landslip prone land. |
REC286-2071 | 29 - Operational Health and Safety | Implement a social marking program to promote improved respiratory etiquette and hygiene. |
REC286-1435 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning and Building System reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-1464 | 41 - Emergency Management exercises | Exercise time-critical decision making processes within the context of an earthquake scenario. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1092 | 29 - Operational Health and Safety | CFA and VICSES should: implement risk management processes within regions, districts, brigades and units to understand and manage the local risks associated with their volunteer workforces |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0937 | 19 - Offences | That the legislation and enforcement arrangements are reviewed to ensure there are suitable offences and penalties, investigation and enforcement capabilities, and a rigorous approach is taken to breaches of the law. |
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0942 | 1 - Land-use and building regs | That the Government makes land use planning and building construction to prevent and mitigate bushfire risk a high priority and establishes a means to progress improvements in this area, such as a designated body or group, as soon as possible. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0786 | 14 - Incident Mgt Teams | TFS develop written guidelines for the use of IMTs about the use of evacuation in a bushfire context, and triggers for decision-making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0196 | 1 - Land-use and building regs | The State develop and implement a retreat and resettlement strategy for existing developments in areas of unacceptably high bushfire risk, including a scheme for non-compulsory acquisition by the State of land in these areas. |
REC181-0203 | 1 - Land-use and building regs | The State amend s. 32 of the Sale of Land Act 1962 to require that a vendor’s statement include whether the land is in a designated Bushfire-prone Area, a statement about the standard (if any) to which the dwelling was constructed, the bushfire attack level assessment at the time of construction (where relevant) and a current bushfire attack level assessment of the site of the dwelling. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0191 | 1 - Land-use and building regs | The State: ■ amend the Victoria Planning Provisions to require that, when assessing a permit to remove native vegetation around an existing dwelling, the responsible authority and the Department of Sustainability and Environment, as referral authority, take into account fire hazard and give weight to fire protection purposes; ■ develop guidelines for determining the maximum level of native vegetation removal for bushfire risk mitigation, beyond which level the application would be rejected. |
REC181-0200 | 1 - Land-use and building regs | Standards Australia move expeditiously to develop a standard for bushfire sprinklers and sprayers. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0176 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment adopt the title ‘safety officer’ (as opposed to ‘safety adviser’) and require without exception that a safety officer be appointed to every level 3 incident management team. |
REC181-0190 | 1 - Land-use and building regs | The Country Fire Authority amend its guidelines for assessing permit applications for dwellings, nondwellings and subdivisions in the Bushfire-prone Overlay in order to accommodate the amendments to the Wildfire Management Overlay that are implemented as a result of recommendation 39 and make the guidelines available to municipal councils and the public. The revised guidelines should do the following: ■ substantially restrict new developments and subdivisions in those areas of highest risk in the Bushfire-prone Overlay; ■ set out the CFA’s guidelines for assessing permit applications for dwellings, non-dwellings and subdivisions—including the minimum defendable space requirements for different risk levels; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ emphasise the need for enduring permit conditions—in particular, conditions for the creation and maintenance of minimum defendable space to be maintained for the life of the development. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0199 | 1 - Land-use and building regs | The State modify its adoption of the Building Code of Australia for the following purposes: ■ to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ to apply bushfire construction provisions to non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities; ■ other than in exceptional circumstances, to apply a minimum AS 3959-2009 construction level of BAL-12.5 to all new buildings and extensions in bushfire-prone areas. |
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0174 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures for investigating safety incidents and ‘near-misses’ to ensure that all dangerous incidents, including back-burns, are fully investigated and that all relevant people are consulted and informed of the results. |
REC181-0189 | 1 - Land-use and building regs | The State amend the Victoria Planning Provisions relating to bushfire to ensure that the provisions give priority to the protection of human life, adopt a clear objective of substantially restricting development in the areas of highest bushfire risk—giving due consideration to biodiversity conservation—and provide clear guidance for decision makers. The amendments should take account of the conclusions reached by the Commission and do the following: ■ outline the State’s objectives for managing bushfire risk through land-use planning in an amended state planning policy for bushfire, as set out in clause 15.07 of the Victoria Planning Provisions; ■ allow municipal councils to include a minimum lot size for use of land for a dwelling, both with and without a permit, in a schedule to each of the Rural Living Zone, Green Wedge Zone, Green Wedge A Zone, Rural Conservation Zone, Farming Zone and Rural Activity Zone; ■ amend clause 44.06 of the Victoria Planning Provisions to provide a comprehensive Bushfire-prone Overlay provision. |
REC181-0198 | 1 - Land-use and building regs | The Australian Building Codes Board do the following: ■ amend the performance requirements in the Building Code of Australia to ensure that they incorporate reducing the risk of ignition from ember attack; ■ work with Standards Australia to effect expeditious continuing review and development of AS 3959, Construction of Buildings in Bushfire-prone Areas, and other bushfire-related standards referred to in the Building Code of Australia; ■ negotiate with Standards Australia and SAI Global Ltd an arrangement for free online access to AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, the other Australian standards referred to in AS 3959-2009, and any other bushfire-related Australian standards referred to in the Building Code of Australia; ■ amend the Building Code of Australia to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ include in the Building Code of Australia bushfire construction provisions for non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0188 | 1 - Land-use and building regs | The State implement a regional settlement policy that: ■ takes account of the management of bushfire risk, including that associated with small, undeveloped rural lots; ■ includes a process for responding to bushfire risk at the planning stage for new urban developments in regional cities, the process being similar to that used for new developments in Melbourne’s Urban Growth Zone. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0197 | 1 - Land-use and building regs | Standards Australia do the following: ■ amend the objective of AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, to ensure that it incorporates reducing the risk of ignition from ember attack; ■ review, and amend as appropriate, the testing methods prescribed in its standards for Tests on Elements of Construction for Buildings Exposed to Simulated Bushfire Attack (AS 1530.8.1 and AS 1530.8.2) to ensure that, so far as is possible, the methods provide a reliable predictor of the performance of construction elements under bushfire conditions. |
REC181-0205 | 1 - Land-use and building regs | The State initiate the development of education and training options to improve understanding of bushfire risk management in the building and planning regimes by: ■ providing regular training and guidance material to planning and building practitioners; ■ providing regular training and guidance material to planning and building practitioners. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3008 | 1 - Land-use and building regs | That any building fitted with heat-activated closing devices or fire and smoke doors be assessed to establish if it constitutes a fire hazard under section 165 of the Building Act 2000 and that, where appropriate, such doors be replaced with smoke activated doors. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3462 | 41 - Emergency Management exercises | DPI should formalise the approach and framework for evaluating simulation exercises and response to Emergency Animal Disease incidents with guidelines to define the nature of the review process. This should include: |
REC154-3459 | 41 - Emergency Management exercises | To improve response preparedness, DPI should clearly link the selection of simulation exercises to the risk management framework to target coverage of high risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3882 | 41 - Emergency Management exercises | The Office of the Emergency Services Commissioner convene a working group of key emergency services and emergency management agencies to develop a flow chart based on scenario testing, to support decision making and the assessment of response requirements to medical, hazardous materials and CBR emergencies including their transition from one type to another. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2335 | 41 - Emergency Management exercises | That the fire agencies develop a program to significantly increase the amount of joint training and exercises undertaken. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2270 | 29 - Operational Health and Safety | That DSE and CFA continue to stress firefighter safety as their highest priority for incident managers and fire ground supervisors |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2250 | 41 - Emergency Management exercises | That DSE and CFA work in cooperation with the Municipal Emergency Response Coordinators to develop and conduct joint exercises that practise the skills and test procedures for operations of the Municipal Emergency Coordination Centre, Municipal Recovery Centre and Incident Control Centres. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3998 | 19 - Offences | That a by-law be made forbidding, under a heavy penalty, any persons travelling in such trains to throw lighted tobacco, cigars, cigarettes, pipe ashes, matches, or other inflammable matter on the railway line or right-of-way, or in any part of a railway carriage except the receptacles duly provided for the purpose. |