Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4077 | 26 - Research | Australian, state and territory governments should support ongoing research and evaluation into aerial firefighting. This research and evaluation should include: |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4132 | 26 - Research | The material published as part of this Royal Commission should remain available and accessible on a long-term basis for the benefit of individuals, communities, organisations, businesses and all levels of government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1457 | 26 - Research | Improve understanding of how coastal inundation events interact with riverine flood events. |
REC286-2032 | 26 - Research | Quantify the effect of heatwaves on vulnerable people. |
REC286-2092 | 26 - Research | Investigate usefulness of satellite data for PPRR (prevention, preparedness, response, recovery) planning. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1456 | 26 - Research | Improve understanding of the weather systems that cause storm surge events to improve predictability and warnings. |
REC286-2024 | 26 - Research | Improve knowledge and understanding of the effect heatwaves coinciding with other hazard events have on the effectiveness and capability of response and recovery capabilities |
REC286-2090 | 26 - Research | Increase understanding of the Puysegur Trench dynamics to improve certainty around the likelihood and magnitude of future Tsunamis. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2079 | 26 - Research | Develop capacity to utilise the new high-resolution satellite products now available. |
REC286-2048 | 26 - Research | Conduct research into changes of owners’ and occupiers stated and revealed risk tolerance and preference for treatment measures before and after natural hazard events. |
REC286-1480 | 26 - Research | Deliver Flood Studies. |
REC286-2045 | 26 - Research | Investigate the potential effectiveness of economic and financial mechanisms to manage the risk appetites of land owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC278-1221 | 26 - Research | The committee recommends that the Australian Government, in cooperation with the Tasmanian Government: • recognise the need to identify the ecological and biodiversity impacts of fire on fire sensitive vegetation communities, organic soils and endemic fauna species in the Tasmanian Wilderness World Heritage Area; and • allocate long-teerm funding to the Commonwealth Scientific and Industrial Research Organisation and/or the Tasmanian Government to assist with the development of fire assessment and modelling specifically suited to the Tasmanian Wilderness World Heritage Area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1430 | 26 - Research | Formal research is commissioned or meta-analysis is undertaken to provide a better understanding of the effectiveness of warnings and other relevant message testing. The outcomes are disseminated to all disaster management entities and learnings used to inform practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0867 | 7 - Inter-agency communication | That Tasmania Fire Service reviews the communication systems used for all emergency management operations, ensures operators are qualified, and ensures there is appropriate accountability. |
REC247-0866 | 26 - Research | That fire agencies continue to develop their predictive modelling capability for use in actively managing fires. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0859 | 7 - Inter-agency communication | That police and other emergency services examine options for achieving radio interoperability between them in the absence of an integrated radio system. |
REC247-0937 | 19 - Offences | That the legislation and enforcement arrangements are reviewed to ensure there are suitable offences and penalties, investigation and enforcement capabilities, and a rigorous approach is taken to breaches of the law. |
REC247-0849 | 26 - Research | That Tasmania Fire Service supports the relevant authorities to continue developing methodologies to forecast and simulate fire risk. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0858 | 7 - Inter-agency communication | That all agencies and the Government support moving to an integrated communications technology for police and the emergency services. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0902 | 7 - Inter-agency communication | That evacuation centres and other centres have a standard operating procedure for communications. |
REC247-0921 | 26 - Research | That Tasmania Fire Service promotes a structured approach to research across Australia, to provide a shared understanding and the capacity to benchmark and judge performance. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2588 | 7 - Inter-agency communication | That Tasmania Police, Tasmania Fire Service (TFS), Ambulance Tasmania and State Emergency Services (SES) investigate ways of providing secure and confidential radio communications. |
REC245-2589 | 7 - Inter-agency communication | That TFS and Ambulance Tasmania work together to resolve problems around congestion, particularly during the fire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0967 | 26 - Research | That a Rural Fire Research and Investigation Team be established to coordinate and communicate fire research knowledge, including fire behaviour as well as coordinate fire investigations and complaints for the state. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2654 | 26 - Research | That the Department of Health determines the underlying causes for the rapid growth in demand for Queensland Ambulance Service emergency responses and implements strategies to address these causes and reduce the cost per head of population to service this demand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2821 | 26 - Research | The National Health and Medical Research Council, in conjunction with key stakeholders, work collaboratively to provide more support for initiatives to increase international infectious disease research collaborations and build research capacity, particularly with neighbouring countries in the Asia-Pacific region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2838 | 26 - Research | The committee notes the linkage between climate change and extreme weather events and recommends that the Bureau of Meteorology and CSIRO conduct further research to increase understanding in the areas of: |
REC229-2837 | 26 - Research | The committee recommends that the Bureau of Meteorology and CSIRO continue to improve projections and forecasts of extreme weather events at a more local level. |
REC229-2836 | 26 - Research | The committee recommends that the Commonwealth government, through the Bureau of Meteorology and CSIRO, continues to support data collection and research to improve forecasting of extreme weather events, especially early warning capabilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0681 | 19 - Offences | Councils and distributor-retailers should agree to protocols for the exchange of information about suspected illegal connections, the steps being taken to investigate them or the basis for concluding that no investigation is required, and the results of any investigations or enforcement actions. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0149 | 26 - Research | The Productivity Commission be tasked to assess the economic effects of recent major bushfires on the Australian economy to determine the cost effectiveness of prescribed burning as a mitigation strategy. |
REC176-0148 | 26 - Research | At the conclusion of the current Bushfire CRC funding agreement the Commonwealth establish a new permanent bushfire research institute. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3198 | 26 - Research | The Committee recommends that the Department of Climate Change continue to fund research to: |
REC145-3229 | 26 - Research | The Committee recommends that the Australian Government urgently commission further research on socioeconomic vulnerability to climate change impacts, particularly in coastal communities. |
REC145-3196 | 26 - Research | The Committee recommends that the Australian Government increase its investment in coastal based climate change research on: |
REC145-3216 | 26 - Research | Noting the gap in research on legal issues and climate change impacts on the coastal zone, the Committee recommends that the Australian Government request that the Australian Law Reform Commission undertake an urgent inquiry into this area, with particular focus on: |
REC145-3194 | 26 - Research | The Committee recommends that the Australian Government commission a study on international coastal zone governance arrangements, policies and programs for addressing coastal climate change impacts, and adaptation strategies. The completed study should be made public. |
REC145-3211 | 26 - Research | The Committee recommends that the Australian Government give the five recommendations calling for information, studies and data, as proposed by the Torres Strait Regional Authority, early and urgent consideration with a view to their implementation. |
REC145-3206 | 26 - Research | The Committee recommends that the Australian Government take urgent action to protect Australians from the threats of dengue fever and chikungunya virus. The knowledge gaps identified by the National Climate Change Adaptation Research Facility research plan with regards to the relationship between climate variation and vector-borne disease should be urgently addressed. The Australian Government should: |
REC145-3202 | 26 - Research | The Committee recommends that the Australian Government establish a coastal zone research network within the National Climate Change Adaptation Research Facility and that it complete a coastal zone research plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC118-3642 | 26 - Research | Establish a Regional Centre of Excellence for Tsunamis to focus Australian and international science/research and collaboration on the challenge of understanding tsunamis and mitigating their consequences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2113 | 26 - Research | The Working Group recommends support for ongoing research into natural hazard risks and an improved understanding of emergency management capability. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2143 | 26 - Research | The Committee recommends that, as part of its study into improving the effectiveness of prescribed burning, the Bushfire Cooperative Research Centre establish a national database that includes areas targeted for fuel reduction, the area of fuel reduction achieved based on a specified standard of on ground verification and the season in which the reduction was achieved. The Committee also recommends that in developing this database the Cooperative Research Centre develop a national standard of fire mapping, which accurately maps the extent, intensity, spread and overall pattern of prescribed and wildfires in Australia. |
REC098-2179 | 26 - Research | The Committee recommends that Program D of the Commonwealth Bushfire Cooperative Research Centre examines the (pending) outcome of the ABCB’s review of the existing Building Code of Australia bushfire |
REC098-2137 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre establish a minimum national standard that is common across all tenures of land for water access and availability for bushfire fighting. |
REC098-2147 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre conduct further research on the impact of weeds on the flammability of land and the most economically and environmentally appropriate way to remove weeds after fire events. |
REC098-2165 | 7 - Inter-agency communication | The Committee recommends that Emergency Management Australia and the Australian Communications Authority work with state and territory bush fire authorities to ensure that that district communication plans |
REC098-2134 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre determine a minimum national standard, taking into account topography and vegetation type, for adequate access to all public lands |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2146 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre conduct further research into the long term effects and effectiveness of grazing as a fire mitigation practice. |
REC098-2164 | 7 - Inter-agency communication | The Committee recommends that: |
REC098-2188 | 26 - Research | The Committee recommends that Program E of the Bushfire Cooperative Centre, which is tasked with the development of the next generation of fire researchers and dissemination of the Centre’s work, be tasked further to collect and respond to feedback, particularly from the on ground volunteer levels of fire brigades, on the practicality of its outputs and their future requirements. |
REC098-2132 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre establish, as part of its program to implement a single fuel classification system, standards which take into account local conditions including topography and vegetation type, for determining appropriate dimensions for asset protection zones. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2145 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre monitor the effect of grazing on mitigating the return of woody weeds to recently fire effected areas across various landscapes including |
REC098-2153 | 7 - Inter-agency communication | The Committee recommends that the state and territory bushfire agencies ensure that, on a district basis, communications are addressed within the district operations plans and that the plans are capable of easy adoption to incident action plans. |
REC098-2182 | 26 - Research | The Committee recommends that the Commonwealth Bushfire Cooperative Research Centre’s research and recommend property protection products and programs under Program D. |
REC098-2130 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre establish, as part of its program to implement a single fuel classification system, a national database that provides information on current levels and rates of accumulation of fuel loads that takes into account vegetation type and climate across all tenures of land, including private land where data is available. |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2144 | 26 - Research | The Committee acknowledges community concerns about smoke pollution as a result of prescribed burning and recommends that the Bushfire Cooperative Research Centre pursue its proposed study into smoke modelling. |
REC098-2180 | 26 - Research | The Committee recommends that (under Programs C and E) the Bushfire Cooperative Research Centre considers the following items as part of a national education program. |