Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1343 | 25 - Inquiry, audit, lessons management and after action review | That the Government conduct a review of fire prevention |
REC299-1344 | 25 - Inquiry, audit, lessons management and after action review | That a review of the cross‑tenure approach be undertaken to determine its effectiveness and to address issues that arise in fire prevention on private and public land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1405 | 37 - Funding | That the Department of Justice & Regulation broadens Budget Paper 3 response time measures to more comprehensively cover emergency responses to fires, rescues and other emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1087 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • practice and ensures that, by taking a risk management approach, it is suitable for fire prevention, mitigation and suppression in all parts of the Hazelwood mine; and review its ‘Mine Fire Service Policy and Code of Practice’ so that it refects industry best • work plan for the Hazelwood mine. incorporate the revised ‘Mine Fire Service Policy and Code of Practice’ into the approved |
REC264-1086 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • consequences of fire in the worked out areas of the Hazelwood mine, and an assessment of the most effective fre protection for the exposed coal surfaces; conduct, assisted by an independent consultant, a risk assessment of the likelihood and • controls are in place to eliminate or reduce the risk of fre; and prepare an implementation plan that ensures the most effective and reasonably practicable • implement the plan |
REC264-1072 | 25 - Inquiry, audit, lessons management and after action review | The State empower and require the Auditor-General or another appropriate agency, to: • oversee the implementation of these recommendations and the commitments made by the State and GDF Suez during this Inquiry; and • report publicly every year for the next three years on the progress made in implementing recommendations and commitments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
REC217-1814 | 37 - Funding | The funding model for works on levees and their ongoing maintenance be revised, to be primarily based on the beneficiary pays principle. The state government should give consideration to wholly funding, or contributing to, the initial upgrade of high priority levees to an agreed standard. The construction of any new public levees will be the subject of a cost‐benefit analysis to be undertaken by DSE and the public authority, and be supported by a floodplain management study. Levees deemed low priority will be wholly the responsibility of the beneficiaries. |
REC217-1845 | 37 - Funding | The state government should provide core, ongoing funding to the responsible authority for the FloodSafe community education program. Funding should be provided for education about prevention, response and recovery phases and include information on rates notices about the height of particular floods. |
REC217-1842 | 37 - Funding | The state government review the current funding approach used for the operation, maintenance and upgrade of river gauges, with a view to improving the river gauge network. |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1733 | 25 - Inquiry, audit, lessons management and after action review | That a review of the Country Fire Authority Act 1958 and the Country Fire Authority Regulations 2004 be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0329 | 21 - Role of Commonwealth Government | The Fire Services Commissioner requests the Federal Government to revise the National SEWS Guidelines |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0214 | 37 - Funding | The State replace the Fire Services Levy with a property-based levy and introduce concessions for low-income earners. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0186 | 21 - Role of Commonwealth Government | The Commonwealth, states and territories continue to pursue the National Action Plan to Reduce Bushfire Arson in Australia, giving priority to producing a nationally consistent framework for data collection and evaluating current and proposed programs in order to identify and share best-practice approaches. |
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3496 | 21 - Role of Commonwealth Government | The Bureau of Meteorology contact list for severe weather warning be strategically managed in consultation with Emergency Service Organisations, to identify critical contacts. The Bureau of Meteorology must ensure the detail for these critical contacts remains up to date. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3470 | 37 - Funding | That the Victorian Government provide recurring funding for a significant increase in regionally-based, permanent, or long-tenured, fire management personnel dedicated to the prescribed burning program. The increase in personnel should be consistent with the level required to achieve an annual prescribed burning target of 385,000 hectares. |
REC155-3469 | 37 - Funding | That the Victorian Government establish a five year rolling fund which allows unused prescribed burning monies to be rolled over into future financial years for the purpose of subsequent prescribed burning activities. |
REC155-3466 | 25 - Inquiry, audit, lessons management and after action review | A comprehensive review of the effectiveness of the increased prescribed burning target in meeting ecological and bushfire suppression needs should be conducted every three years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2318 | 37 - Funding | When the research into prescribed burning and optimum fire protection described in Chapter 11, and the financial analysis of appropriate funding levels for prevention and suppression recommended in Chapter 15, are completed, DSE should develop a business case with Department of Treasury and Finance for assured funding to an agreed level over a three-year rolling cycle. |
REC104-2243 | 37 - Funding | That Government reviews the funding for DSE for the 2004-2005 fire season to ensure that appropriate resources are available for fire prevention planning and preparedness. |
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2308 | 37 - Funding | That Government funding for Community Development Officers engaged in community support and rebuilding incorporates flexible resources to enable the purchase of services from a range of providers to ensure choice for those requiring support. |
REC104-2242 | 37 - Funding | That the financial arrangements incorporate full cost recovery for prescribed burning to be undertaken over a number of weekends utilising Project Firefighters, CFA volunteers and MFESB members. |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2241 | 37 - Funding | That the financial models incorporate changes in public land use, particularly ‘Our Forests Our Future’, and the subsequent changes in fire management priorities. |
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2240 | 37 - Funding | That Government supports the immediate development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |
REC104-2245 | 37 - Funding | That DSE includes the cost of tracks, as above, in the development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2244 | 37 - Funding | That DSE assesses the environmental and monetary cost of establishment and rehabilitation of temporary tracks, per 100 km, constructed during firefighting operations, and compare this with the recurrent costs of a program of maintaining existing tracks. |
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3252 | 37 - Funding | The Committee recommends that an equitable funding system be implemented which relates premiums to: |
REC061-3417 | 37 - Funding | The Committee recommends that an equitable funding system be implemented which relates premiums to: |
REC061-3251 | 37 - Funding | The Committee recommends that the Government act urgently to make the existing system of funding the fire services fair and equitable to all Victorians. |
REC061-3416 | 37 - Funding | The Committee recommends that the Government act urgently to make the existing system of funding the fire services fair and equitable to all Victorians. |
REC061-3249 | 37 - Funding | That the cost of a Bureau of Emergency Services Telecommunications centre be recovered through user charges. |
REC061-3414 | 37 - Funding | That the cost of a Bureau of Emergency Services Telecommunications centre be recovered through user charges. |
REC061-3258 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3423 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3253 | 37 - Funding | The Committee recommends that any change to the funding system reflect in a reduction of the total price charged to consumers through premiums by the insurance industry. |
REC061-3418 | 37 - Funding | The Committee recommends that any change to the funding system reflect in a reduction of the total price charged to consumers through premiums by the insurance industry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3959 | 37 - Funding | It is recommended that an annual grant be made to the Association for distribution among the brigades for the purposes of purchase of equipment of which the brigades are in urgent need. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3997 | 40 - Equipment and consumables | That suitable metal receptacles be fitted under the spittoons of all smoking compartments of country trains, to receive pipe ashes, lighted tobacco, cigars, cigarettes, matches, or other inflammable matter used by smokers. |