Rec-ID | Code | Recommendation |
---|---|---|
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1429 | 2 - Emergency powers | A dynamic online list of positions and contact details is published for those able to authorise Emergency Alert, and made accessible to local government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0095 | 11 - Evacuation and shelters | Planning and consultation be undertaken by EMQ with all levels of the Disaster Management system to ensure that necessary risk-based disaster evacuation plans are prepared at Local, District and State levels, supported by necessary community education and preparedness programs. |
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
REC165-0086 | 2 - Emergency powers | Suggested escalation trigger points be discussed with District Disaster Coordinators and Local Disaster Coordinators, and if considered practical and useful, be incorporated in Local, District and State Disaster Management Plans. |
REC165-0081 | 2 - Emergency powers | District and State levels utilise the current Act to make pre-emptive declarations of a disaster event (likely disasters) so as to be proactive in leading and controlling disaster events. All levels of the system should immediately notify other levels if they activate the Disaster Management arrangements. The Public Safety Preservation Act 1986 be amended to provide powers for Police Officers to provide an immediate response in the event of a rapid onset disaster event such as a landslide. |