Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4111 | 42 - Culture and Heritage | Australian, state, territory and local governments should explore further opportunities to leverage Indigenous land and fire management insights, in the development, planning and execution of public land management activities. |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4110 | 42 - Culture and Heritage | Australian, state, territory and local governments should engage further with Traditional Owners to explore the relationship between Indigenous land and fire management and natural disaster resilience. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3822 | 42 - Culture and Heritage | That Government adopt the principle that cultural burning is one component of a broader practice of traditional Aboriginal land management and is an important cultural practice, not simply another technique of hazard reduction burning. |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3869 | 42 - Culture and Heritage | That, in order to ensure Aboriginal people can access appropriate support during evacuation, Resilience NSW work with Local Emergency Management Committees and Aboriginal Affairs to ensure: |
REC315-3823 | 42 - Culture and Heritage | That, in order to increase the respectful, collaborative and effective use of Aboriginal land management practices in planning and preparing for bush fire, Government commit to pursuing greater application of Aboriginal land management, including cultural burning, through a program to be coordinated by Aboriginal Affairs and Department of Planning, Industry and Environment working in partnership with Aboriginal communities. This should be accompanied by a program of evaluation alongside the scaled-up application of these techniques. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0799 | 18 - Access to fire ground | Develop and implement a program of cost-effective road improvement works that can enhance flood evacuation capacity in the short-medium term. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3360 | 42 - Culture and Heritage | DEWHA should participate in training programs and exercises relevant to an oil spill in the marine environment. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3228 | 42 - Culture and Heritage | The Committee recommends that the Australian Government, in consultation with Indigenous Australians and other coastal stakeholders, commission work to provide a national repository identifying Indigenous and non-Indigenous cultural heritage sites in vulnerable coastal areas. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |