Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-2021 | 40 - Equipment and consumables | Review temporary bridge stockpile for adequacy (DSG). |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2054 | 40 - Equipment and consumables | Personal protective equipment (masks, gowns, gloves, goggles) – review supply/distribution arrangements. |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2053 | 40 - Equipment and consumables | Personal protective equipment (masks, gowns, gloves, goggles) – enhance stocktake methods. |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0947 | 20 - Role of police | That Tasmania Police develops and implements a program for examining emergency management arrangements and facilities in Australia. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0946 | 20 - Role of police | That Tasmania Police establishes a section within its structure with responsibility for developing and maintaining contemporary expertise in emergency management, progressing innovation, assisting organisational change initiatives and supporting its responsibilities in state emergency management arrangements. |
REC247-0945 | 20 - Role of police | That Tasmania Police conducts a review to ensure emergency management is treated as a priority and a core function throughout the organisation, including the development of contemporary capabilities, and is supported by an appropriate culture. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2726 | 20 - Role of police | That the Queensland Fire and Rescue Service enters into discussion with the Queensland Police Service regarding the possibility for the Queensland Police Service to assist with prosecutions that may arise out of fire safety matters. |
REC239-2757 | 20 - Role of police | That the Queensland Police Service executive team reassesses its preparedness to collaborate with other agencies to deliver a whole of Government approach to delivering community safety. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2689 | 20 - Role of police | That, where appropriate, the Commissioner of Police appoints appropriately trained and experienced public service officers to appropriate roles in the disaster management system to support District Disaster Coordinators in their vital roles. |
REC239-2752 | 20 - Role of police | That the roll-out of the Queensland Police Service digital technology should take into consideration adopting and facilitating new processes including the police response to domestic violence. |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2750 | 20 - Role of police | That the Queensland Police Service: |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2748 | 20 - Role of police | That the Queensland Police Service considers adopting the broader use of ANPR in line with other Australian jurisdictions in consultation with the Privacy Commissioner. |
REC239-2747 | 20 - Role of police | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative automated number plate recognition models should form part of the design architecture. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1636 | 40 - Equipment and consumables | Update the Asset and Equipment Register for all assets and equipment. |
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1635 | 40 - Equipment and consumables | Conduct a stocktake of all assets and equipment in all regions for Bushfires NT and Volunteer Brigades. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
REC209-1640 | 40 - Equipment and consumables | Conduct a stocktake of all PPE and implement a top up program to bring all PPE to a fully operational standard. |
REC209-1639 | 40 - Equipment and consumables | An equipment replacement schedule for all Bushfires NT equipment be developed. |
REC209-1638 | 40 - Equipment and consumables | The Assets and Equipment Register be reviewed prior to each fire season. |
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1637 | 40 - Equipment and consumables | Implement maintenance schedules for all common assets and shared equipment. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3006 | 20 - Role of police | That the recommendations contained in the Police Operational Debrief Report of 22 October 2007 to 7 November 2007, submitted to the Coroner, be further considered by the Tasmania Police for adoption where considered appropriate by Tasmania Police. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0085 | 20 - Role of police | The Commissioner of Police, through a dedicated Assistant Commissioner (supported by a cohort of Assistant Commissioners to ensure adequate coverage), be assigned responsibility for overall control of each natural Disaster Management event in Queensland as the preferred arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3988 | 40 - Equipment and consumables | The Commission recommends that buckets of sand or other apparatus for extinguishing fire be kept in any chamber where high powered electricity is used. |