Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4205 | 26 - Research | We recommend that DELWP in partnership with Parks Victoria, Country Fire Authority, Fire Rescue Victoria and councils as appropriate, collect empirical evidence after bushfire events to assess the effectiveness of different fuel management treatments, including planned burning, mulching, slashing and mineral earth breaks, and build an evidence base to the effectiveness of these treatments. |
REC321-4208 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) develops financial reporting to monitor fuel management costs and estimate future costs. |
REC321-4209 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) systemically documents and publicly reports reasons why it does not complete planned burns. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4177 | 38 - Agency/Department Reporting | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in conjunction with legislated fuel management organisations – develop a common set of objectives, metrics and reporting requirements for fuel management that form part of a compulsory regime that enables the Victorian Government to report publicly on a holistic fuel management program. The reporting requirements should: |
REC318-4176 | 26 - Research | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) lead the development and distribution of evidence-based land and fuel management tools for use by all legislated fuel management organisations to ensure a common approach to fuel management. |
REC318-4172 | 26 - Research | The Inspector-General for Emergency Management recommends that the State support the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) and its partners to expand the Safer Together program to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1342 | 6 - Insurance and legal liability | That fire managers responsible for planned burns be |
REC299-1340 | 26 - Research | That any such pilot program ought to be managed by the relevant indigenous organisations, with support provided by DELWP and its partner agencies and the development and the evaluation of any pilot program should be overseen by an independent and reputable academic or research institution. |
REC299-1339 | 26 - Research | That Government provide support in the form of funding for the Return to the Firestick project, and that a formal pilot scheme be established where data can be collected, collated and analysed and the effectiveness of this approach be compared against current burning practices. |
REC299-1346 | 26 - Research | DELWP and its partner agencies, in conjunction with the Department of Health and Human Services, should undertake research into the specific effects on health of people affected by planned burns and the information should be made public. The study should include the direct impact of smoke on affected populations and impacts on water, food supplies and livestock. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1081 | 26 - Research | The State should continue the long-term health study, and: • extend the study to at least 20 years; • appoint an independent board, which includes Latrobe Valley community representatives, to govern the study; and • direct that the independent board publish regular progress reports |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1836 | 26 - Research | Flood studies will be undertaken to determine the flood extent on the basis of a greater than 1 in 100 ARI, where appropriate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0416 | 26 - Research | the state establish appropriate arrangements to ensure the capacity to maintain technical expertise for flood intelligence is initiated, including appropriate agreements with commercial experts. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0215 | 26 - Research | The Commonwealth establish a national centre for bushfire research in collaboration with other Australian jurisdictions to support pure, applied and long-term research in the physical, biological and social sciences relevant to bushfires and to promote continuing research and scholarship in related disciplines. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0171 | 17 - Assets and technology | The State, in conjunction with Emergency Management Australia and the Department of Defence, develop an agreement that allows Commonwealth aerial resources that are suitable for firefighting and support activities to be incorporated in preparedness plans and used on days of high fire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0170 | 17 - Assets and technology | The Country Fire Authority and the Department of Sustainability and Environment amend their policies on aerial preparedness and standby arrangements, their dispatch protocols and the management of aircraft in order to do the following: ■ require that at locations that attract the risk assessment or preparedness level A on code red days all personnel needed for air operations must be on standby by 10.00 am; ■ establish a system that enables the dispatch of aircraft to fires in high-risk areas without requiring a request from an Incident Controller or the State Duty Officer. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2977 | 38 - Agency/Department Reporting | The Department of Human Services should create evaluation guidelines for recovery operations, including links to planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2998 | 38 - Agency/Department Reporting | Reports on the training exercises should be retained in an appropriately secured central repository so that consolidated results of the exercises can be drawn together effectively. |
REC169-2997 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet and Victoria Police, in consultation with departments, should standardise reporting on training exercises conducted under Part 6 of the Act and the CIP framework to promote greater consistency and to enable better identification of lessons learned and continuous improvement. |
REC169-2989 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet should lead the development of a performance management framework for measuring, monitoring and reporting on the implementation of Part 6 of the Act and the CIP framework. The framework should include key indicators, targets and reporting arrangements for assessing the extent to which departments, agencies and industry have fulfilled their obligations, as well as measures for monitoring achievement of joint objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
REC158-3429 | 38 - Agency/Department Reporting | That the nominated marine safety authority is required to ensure that incident notification and data recording requirements for Victorian commercial ports are consistent and adhered to. |
REC158-3428 | 38 - Agency/Department Reporting | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner and senior emergency services personnel, is responsible for monitoring the implementation and auditing against appropriate performance standards, risk management guidelines and good practice guidelines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3506 | 26 - Research | The Office of the Emergency Services Commissioner facilitate further research into technologies that will reduce the need for the public to speak to an operator during an emergency as a component of the proposed emergency warning and alert system and Victorian Emergency Information Line. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
REC155-3472 | 26 - Research | That the Department of Sustainability and Environment and its partner agencies conduct or commission research, and a possible trial study, to determine the potential of thinning and other silvicultural practices – whether alone or in combination with prescribed burning – as a means of reducing fuel loads and as a bushfire management strategy in Victoria’s forests. |
REC155-3471 | 6 - Insurance and legal liability | That the Victorian Government replace or compensate for water taken from domestic, stock and irrigation dams, or water needed for essential use, in the event of a fire, regardless of where the bushfire starts. |
REC155-3481 | 6 - Insurance and legal liability | That the Victorian Government establish a clear and consistent Bushfire Fencing Policy for damage caused by all future bushfires and prescribed burns. The Bushfire Fencing Policy should include the following provisions: |
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3593 | 26 - Research | Analysing information from the joint CFA/DSE Post 2006 Wildfire Community Survey about public perceptions of information provision during January bushfires. Note implications for the VBIL and other information provision methods |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3927 | 6 - Insurance and legal liability | That PSB and PIRVIC review their service agreement to ensure that PIRVIC is compensated for its costs in providing PSB with the specified level of service. |
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2290 | 38 - Agency/Department Reporting | That instances where demand for air support outstrips the supply of State Fleet Aircraft available are recorded. |
REC104-2193 | 38 - Agency/Department Reporting | That if ‘link’ burns continue to be used, then on-site weather sequences and fuel conditions marking successful (‘within explicit prescription’) and unsuccessful burns be documented. |
REC104-2217 | 6 - Insurance and legal liability | That CFA, in their education and information packages, encourage appropriate insurance cover, and ensure that insurance becomes a part of the householder’s annual checklist. |
REC104-2289 | 38 - Agency/Department Reporting | That the joint agencies introduce a system of performance measures for reporting the effectiveness of aircraft in firefighting operations. |
REC104-2201 | 26 - Research | That DSE undertake a formal study of the level of prescribed burning in south western Australia for its possible application in Victoria by comparing respective fuel arrays, terrain, weather, ground access, staff, prescribed burning days, areas conducive to prescribed burning and fire response systems. |
REC104-2286 | 17 - Assets and technology | That CFA, having regard to terrain, continue to review the mix of firefighting appliances currently in service. In particular, consideration should be given to the number and distribution of smaller ‘slip-on’ type equipment. |
REC104-2200 | 38 - Agency/Department Reporting | That DSE: |
REC104-2231 | 6 - Insurance and legal liability | That DSE commences discussion with the Victorian WorkCover Authority in respect to employer liability for those staff being released to, and directed, by another agency in fire prevention and suppression activities. |
REC104-2195 | 38 - Agency/Department Reporting | That the creation of buffers by chaining and then burning swaths of mallee be explicitly monitored for: |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2194 | 38 - Agency/Department Reporting | That the success of current buffers in terms of assisting suppression operations be continually reviewed, evaluated and documented. |
REC104-2218 | 6 - Insurance and legal liability | That Government work with the insurance industry to explore options for incentives such as a reduction in premiums for those who take appropriate self-protection measures on their properties, similar to incentives for anti-theft home security |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3246 | 38 - Agency/Department Reporting | The Committee recommends that performance monitoring standards be established, reviewed and maintained through a common reporting system by the Minister for Police and Emergency Services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3949 | 17 - Assets and technology | It is recommended that the A.R.P. dams or earth tanks be kept filled during possible danger periods. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |